West Jordan, UT
On-Site Contact: Kim Schelin
Phone: (801) 664-6052Branch Manager: Grant Biesinger
Phone: (801) 783-8711Email: Grant.Biesinger@CentiMark.comSenior Project Manager: Trevor Hammond
Phone: (801) 709-8424Email: Trevor.Hammond@CentiMark.comForeman: Jairo Ramirez
Phone: (385) 227-9477Square Footage Completed: 73% 42,489 Sq Ft Completed
Square Footage Remaining: 27% 15,612 Sq Ft Remaining
Days Remaining: 20 Working Days
Insulation Replaced: 320' (2.6"+1") Sq Ft @ $6.50 = $2,080
Deck Replaced: 0 Sq Ft
Project Concerns: If there is a 40% chance or higher for precipitation no tear-off will be started. Forecast indicates that there will be rain/snow multiple days this week. Work has been delayed and will see continued delays due to precipitation.
Safety Initiatives: Temporary Safety Flags & Rails.
Project Comments: Multiple leaks on the old areas of roof where CentiMark has not yet started the re-roofing have been reported and repaired. There was a leak that occurred after the old membrane had been torn off, and snow that was on top of the HVAC unit melted and leaked into the building during the daily construction. CentiMark is working to remedy the situation.