West Jordan, UT
On-Site Contact: Kim Schelin
Phone: (801) 664-6052Branch Manager: Grant Biesinger
Phone: (801) 783-8711Email: Grant.Biesinger@CentiMark.comSenior Project Manager: Trevor Hammond
Phone: (801) 709-8424Email: Trevor.Hammond@CentiMark.comForeman: Jairo Ramirez
Phone: (385) 227-9477Square Footage Completed: 62% 36,395 Sq Ft Completed
Square Footage Remaining: 38% 21,706 Sq Ft Remaining
Days Remaining: 32 Working Days
Insulation Replaced: 0 Sq Ft
Deck Replaced: 0 Sq Ft
Project Concerns: If there is a 40% chance or higher for precipitation no tear-off will be started. Forecast indicates that there will be multiple days this week. Work has been delayed and will see continued delayed due to precipitation.
Safety Initiatives: Temporary Safety Flags & Rails.
Project Comments: Roofing has been started on Bldg E and will continue onto Bldg F. Much of the larger main sections have been completed. Work will now move onto the storefront areas which will progress much slower than the main areas. Work is progressing on schedule and should be completed as expected if work continues as it has. Please Note: minor wrinkling of the membrane during the winter months is to be expected because of temperature swings. This will tighten up as the summer months arrive.