Post date: Mar 20, 2019 8:28:27 PM
Note from the College below regarding last piece of work for completing Spring and Latham Street work.
Impact to Adjacencies:
• Starting April 1, 2019, Spring Street (south of the Walden Street intersection) will be closed to vehicular
traffic. Vehicles will be diverted west on Walden Street to Hoxsey Street.
• Latham Street will be closed west of the Field House parking lot. Access to the Field House parking lot
will not be impacted.
• Pedestrian access will be maintained through temporary sidewalks and signage will be installed.
• Access to the B&L Building will be maintained.
• Access to the public parking lot at the base of Spring Street will be via Walden Street.
• Williams will be working with the Town for permission to install temporary construction signs to notify
visitors of the road closure and to provide direction to Spring Street and the public parking lot.
• Construction is scheduled for completion by the end of June 2019.
• Work hours will be Monday – Friday, 7AM-5PM with Saturday work planned, as needed, to meet the
completion date.
• Updates and additional notifications will be distributed through the course of construction.