Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Refined CAD
Made separate CAD for armbar for improved clarity
Improved tolerances to allow parts to fit easier/better
Removed spring mounts
Combined camera mount with damper mounts
Completed further analysis of dampers
Continued rigid body analysis
Bought pipes to redo armbar from Home Depot
Accomplishments from Previous Week
Second iteration of CAD camera mount completed
Updated report
Worked on rigid body analysis
Tested damper samples
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Test assembled prototype (everyone)
Analyse damper/print more as time allows (Andrew, Mark)
Refine rigid body analysis (Ang, Zoe)
Finish poster (everyone)
Finish report (everyone)
Update website (everyone)
Prep parts for final product assembly
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
N/A
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
5/23, in person
Further investigate damping material
Find k value at least if c value not possible
Check when joints will arrive for assembly
Check height, make sure it allows adequate lap room
Fix tolerances on printed parts
Keep in mind overdoing tolerances on rough prints will lead to fine prints being too loose
Fix CAD to reflect real dimensions, to make assembly and presentation easier
CAD was updated
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Will the hinges withstand the forces applied to them?
Are the parts too difficult to machine?
Currently the pipes turn where they connect with the angle - how constrain this movement?
Glue parts together
Hammer pipe so it's no longer perfectly circular
Resources or Information Required but not Available
N/A
Schedule
Assembled and test full assembly on wheelchair
Budget (list amount spent and amount remaining)
N/A
Progress on Report and Webpage
Report turned in for peer review
Webpage updated weekly