Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finished second prototype - will assemble final prototype and test
Finished poster
Finished website
Accomplishments from Previous Week
Refined CAD
Damper and rigid body analysis
Bought needed materials from Home Depot
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Assemble final prototype (everyone)
Revise final report (everyone)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
6/5, in person
Emailed sponsor survey form
Everything looks okay!
B-BBQ on Friday
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
6/6, poster session
reorganize poster
delete extraneous information
add standards and references
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
6/4, emailed comments from presentation
more material details
more pictures for clarity
practice presentation more
explain analysis done more thoroughly
Risks and Areas of Concern
Limited time left - testing takes time
Resources or Information Required but not Available
N/A
Schedule
Finish poster and website by Friday
Finish report by Sunday
Finished prototype/poster session Wednesday
Budget (list amount spent and amount remaining)
Home Depot
12-24 screws - $1.18
2x Galvanized steel elbow - $6.22
Galvanized steel nipple (1/2" x 12") - $4.98
2x Galvanized steel nipple (1/2" x 8") - $7.96
Cable ties - $2.54
3D printed Ninjaflex 1 inch damper - $18
3D printed Ninjaflex 1 inch damper - $14
Progress on Report and Webpage
Report will be done Sunday
Webpage to be finished today