Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Established electronics communication to hardware
Built linux workspace
Tested position code and working on testing code with combined arms
Discovered possible broken encoder
ReCAD, recut, and reassembled U-Joints
Testing extension handle prototypes
Accomplishments from Previous Week
Wiring of electronics boxes and WoodenHaptics arms complete
Micro-controllers flashed with necessary software
Installed Ubuntu 16.04 to run Chai3d software
Existing code double-checked for errors
Redesigned the extension handle piece to allow more translational movement
Recut some pieces and re-cabled so the wires have more tension
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Alex & Eric: implement combined arm code, expert trajectory, and resistance.
Jackie & Daniel: test the arms and compute some “numbers”
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Integrate light source into laryngoscope handle (in person 5/12)
Treat roll motor as a stretch goal (in person 5/12)
Re-do some aspects of cabling (in person 5/12)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Split time spent on report writing more evenly (in person 5/11)
Jumper wires available on campus (in person 5/11)
Work on finishing U-joint as soon as possible (in person 5/11)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Dress more professionally for presentations (via email 5/11)
More information on software in presentations (via email 5/11)
More annotations/diagrams and less words in presentations (via email 5/11)
Risks and Areas of Concern
Undetectable roll caused by larger slots on attachment piece (meant to allow for more translational motion)
Durability of 3D printed components, especially new attachment piece
Hidden software errors/problems not discovered through inspection
Resources or Information Required but not Available
N/A
Schedule
Milestones (week 9)
Test the software to track the movement of laryngoscope
Budget (list amount spent and amount remaining)
Total Spent: $4213.77
Total Remaining: $86.23
Progress on Report and Webpage
Revisions for the second draft have been made but will be continued
Some images/CAD files have been added to the website