Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Code determining the position of the arms was adjusted with correct dimensions of the new arms
Better data of position obetained
Accomplishments from Previous Week
Resistance force feedback tested
tracking / recording algorithm tested
Sound feedback algorithm developed and implemented
More iterations of extensions piece with different offsets of the slots printed
Construction of base initiated
Range of motion measured
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Alex, Eric, Jackie, & Daniel: Deliver the product to the sponsor
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Answered questions during the sponsor presentation (6/8 in-person)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Revise the poster to better sell OUR product (email 6/9)
Polish the report and webpage (email 6/9)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Durability of the cables
Resources or Information Required but not Available
N/A
Schedule
Summer
Deliver the product
Relax and figure out our next plan after school
Budget (list amount spent and amount remaining)
Total Spent: $4237.93
Total Remaining: $62.07
Progress on Report and Webpage
POLISHED and PRINTED