Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Final Chill Puck assembly is complete!
All planned testing has been conducted
Report and Poster are finished, website soon to follow
Accomplishments from Previous Week
Finished project, final report, and poster
Presented final design to sponsor (final design review)
Assignments for Coming Week
Jayant Mathur
Finish refining code
Compile into user-friendly package
Nate Goldberg
Hardware packaging
Assembly instructions
Kristen Matsuno
Update CAD models
Finalize Poster
Nathaniel Liu
Finish website
Assist with assembly instructions and packaging
Sponsor Feedback and Corresponding Action Items
The sponsor was very pleased with the final presentation, and the final hardware setup.
Instructor Feedback and Corresponding Action Items
Professor Tustaniwskyj might be fond of the final control system!
Comments from Other Students
N/A
Risks and Areas of Concern
Assembly of the final hardware could be an issue for the sponsor if documentation is poor.
Resources or Information Required but not Available
N/A
Schedule
Monday 6/12 - 2:00 pm Team meeting
3:00 pm Meeting with professor (?)
Thursday 6/15 - Final Poster Session
Budget (FINAL)
Remaining Funds: $73.84
Progress on Report and Webpage
Report is DONE! Webpage will be completed shortly.