Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Prototype 2 complete
Pitot Tube Sensor calibration complete
Accomplishments from Previous Week
Prototype 2 completion
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Ideal location to mount pitot tube within vehicle (Keith,Dominic)
Decision on using VW Golf's speed sensor (all of us)
Optimize Prototype 2 (Sal, Jonathan)
Mount quick release modifications to car (Sal, Jonathan)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Offset from railing thickness (02/16/16)
can be solved 3/4" MDF or even 1/8" sheet of plastic same dimensions as the MDF
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Use inserts rather than taping aluminum
bought the inserts
Make changes to Reports before Friday (02/20/16)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Toggle lever mounting space
Mounting area for pitot tube
Resources or Information Required but not Available
N/A
Schedule
Completed Prototype 2
Decisions on whether to use vehicles speed sensor after getting a look at the vehicle again
Ideal locations to place the wind sensor in vehicle
Update Gantt chart.
Budget (list amount spent and amount remaining)
$37.77 spent on MDF, inserts, and assorted 6-32 screws, total remaining in budget is $1779.75
Progress on Report and Webpage
Webpage continuously updated, Report Draft revised due by (02/20/16)