Overview of Status of Analysis, Design, Fabrication, Tests, etc.
New prototypes implemented into testing apparatus
Ordered new forged toggle clamps to begin implementing them into the design
Wiring all run in car for DAQ, only remaining DAQ task is placement of pitot tube sensor in permanent position
Accomplishments from Previous Week
New design adjustments in toggle block machined and tested
Draft of poster design made
Stabilization block machined and tested
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finalize toggle block design (All)
Finish all CAD drawings (All)
Find final location for pitot tube mount (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Drawings and dimensions need to be finalized (in person, machine shop, 3/4/16)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
Resources or Information Required but not Available
n/a
Schedule
Finish all drawings by the evening of 3/8/16
Finish final machined parts by Saturday, 3/12/16
Update Gantt chart.
Budget (list amount spent and amount remaining)
$288.31 total spent; $1711.69 remaining in budget
Progress on Report and Webpage
Webpage, reports, and poster design all being continuously updated