Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Electronic components functioned simultaneously
Able to extrude PLA
Motor Driver needs to be replaced with one that can handle more current
Spool mounts are nearing completion
Accomplishments from Previous Week
Base Plate
Spool mounts machined, mounting holes created and tapped (Nicholas)
Electronic mount created in autocad and will be laser cut (Anny)
Extruder Tip
Machined half of extruder mount from aluminum (Kevin)
ElectronicsÂ
Finished Arduino protoboard (Armando)
Heater and motor work simultaneously (Armando)
First successful test of pushing PLA through extruder tip using heating element (Armando)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finalize and assemble all components together for working prototype (all members)
Start testing with the KUKA
Get familiar with milling software (Armando)
Ensure baseplate fits onto the mount and all components are secure (Nicholas, Anny)
Ensure extruder tip is stable on milling head, integrate tool into quick change rack (Kevin)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
2/5/2016 (email)
Sponsor updated on status of project
Will meet with sponsor on 2/16/2016 for KUKA access
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
After presentation on 2/4/2016 (in person)
Labels for pictures and figures
Possibly using more than one Arduino for each component
Use fan instead of compressed air for filament cooling
Mount Mosfets and voltage regulator on heat sinks
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
After presentation on 2/4/2016 (in person)
Use software to plan proto-board electronics (Paulie)
Risks and Areas of Concern
Need to test Y-connector housing once stepper motor is running
Need to test high-current motor driver
Resources or Information Required but not Available
N/A
Schedule
Complete first prototype
Gain access to lab by 2/16/2016
Budget (list amount spent and amount remaining)
Spent: $397.13
Remaining: $1,102.87
Progress on Report and Webpage
Completed and uploaded first draft of report