Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Existing technologies researched
Contacted manufacturer of existing technology for composite printers
Designed basic concept of printing head
Accomplishments from Previous Week
Redefined project to meet MAE 156B standards
Bill of Materials created for first prototype (All members)
CAD of Prototype (Armando)
Contacted manufacturer of existing technology for composite printers
Set weekly meeting time with sponsor
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Check with Chris Cassidy for existing components
Order all components from Bill of Materials for first prototype (Nick)
Manufacture custom extruder mount and spool mount
Manufacture desktop testing mount for access to quick testing
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Meeting on 1/15/2016 to approve new project definition (changing from fiber winding to 3D printing)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Changed project definition (addressed issue)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Not relevant until 1/14/2016, after Design Proposal Presentation
Risks and Areas of Concern
Carbon fiber filament or continuous carbon fiber
Write custom path planning software
Implement cooling system to create self-supporting structures
Use of heating printing
Separate controllers for feeding filament and controlling arm movements
Use of a cutter
Resources or Information Required but not Available
N/A
Schedule
Start manufacturing testing platform
Purchase parts for prototype
Once parts arrive, build and manufacture hot end adapter
Create another Bill of Materials for actual purchased items
Budget (list amount spent and amount remaining)
Projected parts cost: $150 (for major components)
Remaining (projected): $850
Progress on Report and Webpage
Finish first report draft 1/15/2016, as specified