156B Week 8

Overview of Status of Analysis, Design, Fabrication, Tests, etc.

After conducting a cost analysis, it would cost less for the air source of the wind tunnel to be the fan rather than shop air. The team is still working on building the RTD circuit board for the new temperature range. The team has begun machining the exhaust box and mesh screen mounts. The majority of the wind tunnel will be fabricated by the end of the week.

Accomplishments from Previous Week

Goals for Next Week (list names after each item). Use specific and measurable objectives.

Sponsor Comments from Last Meeting and Actions Taken to Address these Comments

Instructor Comments from Last Meeting and Actions Taken to Address these Comments

Risks and Areas of Concern

Resources or Information Required but not Available

Schedule

Budget

Progress on Report and Webpage