Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Machining of table components in progress
Controller electronics and software in prototype stage
Accomplishments from Previous Week
Received two Trespa sheets
Purchased and picked up aluminium t-slot extrusions and aluminium corner brackets from F&L Industrial Solutions
Purchased and picked up cylindrical Delrin stock from ePlastics
Controller four button push button system working.
Programmed Arduino to communicate with in-room controller and LabVIEW
Ordered leveling casters and Type 316 stainless steel bolts from McMaster-Carr
Machine nuts for fastening t-slot aluminium
Working to order fiber optic components from Industrial Fiber Optics (there was some purchasing trouble)
Working to finalize order of PCBs
Ordered thrust bearings from Igus
Completed newer, more detailed CAD model of table, positioning system, and associated components
Completed Report Draft 1
Created v1 of team website
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Add fifth button to in-room controller. Have it operational by end of Week 6
Complete machining Delrin stock and aluminium stock into lead nut and lead screws respectively
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
No major comments. Meeting was a general status check
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Dr. Delson advised us to check the tolerances on our linear bearings.
Upon receiving our linear bearings, we fastened aluminum extrusions to them and observed minor free play between the bearing wall and the extrusion. However, the bearings shipped with thin spacers (~5 thousandths of an inch) to further tighten the tolerance.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A this week
Risks and Areas of Concern
Thrust bearing will take 1.5 weeks to arrive, which is later than we'd like.
Will be purchasing a new arduino for our controller and must make sure it is compatible with our current setup (small concern)
Resources or Information Required but not Available
N/A
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$1150 spent of $1500 total
Progress on Report and Webpage
Draft 1 of Report completed