Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Manufacturing all components
Aluminum plate done
Frame in progress
Wooden in progress
Impact heads/aluminum tubes in progress
Testing will be Monday 6/1 at 9:00 AM (ATA will come here to test)
Accomplishments from Previous Week
All components/parts/materials have been ordered
Manufacturing began/plate completed
Testing date and presentation date finalized with ATA
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Successfully test machine with ATA (aka hit all 3 profiles) on Monday 6/1- all
Make a 45 minute presentation to be done at ATA on Friday 6/5- all
Work on poster/report/web page- all
Impact tip/mass manufacturing- Roy
Wooden slider/frame assembly- Leighy & Troy
Mitered tubes/aluminum tubes- Sam
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Belleville washers were too expensive, so we got wave springs instead (ATA said this was fine)
Discuss the analysis of the bolt shear/impact head
They were satisfied with the final design of all components
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Show more calculations (which we have, we just did not put them in the presentation so that it would not be too long)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Some students were concerned with consistency of results after reassembly of the machine
Based on calculations/interchangeable impact heads/designated assembly holes (and each tube will be marked so that it will be put together exactly the same every time), we should have consistent results
Risks and Areas of Concern
Time crunch
We will have testing time on Monday, but more testing time is always desirable. Due to our manufacturing schedule + ATA's busy schedule, setting up an agreeing time is difficult
Machine shop hours are short and space is crowded
Resources or Information Required but not Available
All resources/info has been easily available thanks to ATA
Schedule
Complete ALL manufacturing by weekend
Do some dry runs of the completely manufactured machine over the weekend to prepare for testing on Monday with ATA
Update Gantt chart.
Prepare presentation for ATA for Friday 6/5
Do poster by this Friday
Work on report/webpage
Budget (list amount spent and amount remaining)
Spent $1881.43
Remaining $318.57
Progress on Report and Webpage
Will read student feedback on both report/webpage and make corrections we find helpful