Overview of Status of Analysis, Design, Fabrication, Tests, etc.
The new latching mechanism for the large bunny hop has been mounted and is ready for testing
High Speed Video has been taken of an ollie to analyze
The mini bunny hop is almost ready
Accomplishments from Previous Week
A mini bunny hop has been designed and is ready to be made
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Assemble the mini bunny hop
Mount the car jack so it is more safe
Test the new latching device for the large bunny hop
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
N/A
Instructor Comments from Last Meeting and Actions Taken to Address these CommentsÂ
N/A
Comments from Other Students in the Class
N/A
Risks and Areas of Concern
Making sure the skateboard does not topple over
Safety
Resources or Information Required but not Available
N/A
Schedule
Print out the parts with the lasercamm
Assemble the mini bunny hop model
Troubleshoot the new latching mechanism
Budget (list amount spent and amount remaining)
Spent: $730
Remaining: $270
Progress on Report and Webpage
Updated the budget on the website
In progress for the completion of the final report
In progress for the final poster
Updated the website