Overview of Status of Analysis, Design, Fabrication, Tests, etc.
First version of 3D Printed/Custom PCB sensor package finished
Drop tests performed Friday (5/10)
data was not recorded due to malfunction in wiring
Accomplishments from Previous Week
Completed PCB design, ordered and received
3D printed first prototype of sensor housing
Soldered and assembled instrumentation package, performs as expected
Completed test dummy
Created Matlab script to verify proper I-beam loading in drop testing procedure
Performed several instrumented drop tests w/dummy on Fri. 5/10 (~10 ft)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Perform more/higher drop tests to continue accumulating data (All)
Perform Test Dummy modifications (Joe C./Kelvin)
Work on further revisions of housing/PCB (Joe M.)
Analyze drop test data, continue work on event detection (Jeff)
Continue website/report work (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor viewed dummy drop tests, was pleased with progress. Recommended dummy modifications and continue ironing out test procedure.
Sponsor was interested in investigating the possibility of dead reckoning position for the sensors in the package, further simulation needs to be done.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Concerns about report draft (5/6 Meeting). Worked on report, adding figures and ensuring metric units. Awaiting corrected draft to continue this work.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Working on perfecting test dummy drop procedure with Isaiah and Tom
Resources or Information Required but not Available
N/A
Schedule
Hope to perform more drop tests on Wed. 5/15
Dummy modifications and first drop test data analysis will be compete by this time.
Budget (list amount spent and amount remaining)
$1442.04 Spent and 57.96 Remaining
Progress on Report and Webpage
Will continue working on report, awaiting corrected draft from last week.