(3/4/12-3/9/12)
Overview of Status of Analysis, Design, Fabrication, Test, etc
Finished up with fabrication
Everything was assembled
Need to get some more screws
Got the motor working
Until it stopped working
Goals for next week
Get the motor working
Run the different sequence to meet the functional requirement
Home sensing fabrication
Prepare for the final presentation
Instructor comments from last meeting and actions taken
Focused on control system
Had the motor working after speaking to an engineer at Delta Design
Distribute fabrication
Thought of different option; however, we were able to finish it without outsourcing
Risks and areas of concern
Control system
Schedule
Motor
Inside first, then outside
Home sensing
Budget
Risk Reduction and scale model: $215.20
Steel Rod and Ball Bearings: $104.77
Materials: $843.47
Electronics: $500.00