Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Preliminary designs are finished
Fabricating/Setting up Table
Accomplishments from Previous Week
· Presentation
· LaserCamm parts list
· Varnish Table
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Build secondary painting table for sponsor (Team or anyone with extra time)
Cad and fabricate new washing station (Greg)
Fabricate new carriage (Kent/Jay)
Make our own DXF file to works as a NC file. (Jon/Eric)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
No meeting but told us to varnish table which is completed and build secondary painting table which is in progress.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
There was no meeting because of presentation
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
· No special comments from students in class.
Risks and Areas of Concern
Same as last week (gcode language learning)
Resources or Information Required but not Available
We need to know if we will be able to use the same motors with the Linux machine system. They may require a minimum voltage that is higher than the motors used in the original drawing table.
Schedule
· Build new table
· Convert DXF to DMC and run a simulation on the computer using CutViewer
· Create interrupts for different home points (brushes, ink pots, etc)
Update Gantt chart.
Budget (list amount spent and amount remaining)
$692.62 = duplicate table w/o motors, gears, and timing belts
$384 = motor kit
(3) 425 oz-in stepping motors, NEMA 23
(3) KL-4030 Drivers (3.0Amp 24-40 Volts, 1-1/64 microstepping)
(1) 36VDC/ 9.7A Power Supply 110VAC/220VAC
(1)C10 Breakout board
(1) 5V power supply
Progress on Report and Webpage
Impact on Society has been uploaded
Weekly Progress Report 4 uploaded