The Schematic Design Report (SDR) submission was sent to the MSBA on 12/17/21.
To view the complete submission, follow the link below:
https://clientportal.vertexeng.com/fl/7YcCabyJM6/Watertown_HS_-_MSBA_Schematic_Design_Submission_
____________________________________________________
The Design Subcommittee prepared a memo. dated 11/2/21 for the Project Team, and School Building Committee with feedback, concerns, and questions.
https://clientportal.vertexeng.com/dl/gqDz8BTsED/211102_WSBC_Arch_Subcommittee_Feedback-1.pdf_
____________________________________________________
The Preferred Schematic Report (PSR) submission was sent to the MSBA on 7/2/21.
To view the complete submission, follow the link below:
https://clientportal.vertexeng.com/dl/eXOLE9icAR/WatertownHS_PSR_Report_2021_07_02.pdf_
SBC Voted on 6/2/21 to Approve Option 1H as the Preferred Schematic Report to be Submitted to the MSBA.
Design progress on Option 1H can be followed in the folder below.
________________________________________________________
Both the School Building Committee and the School Committee voted in June 2021
to name the high school swing space to be temporarily located at
Moxley Field from Fall 2022 thru Spring 2026
in honor of PFC Richard Moxley.
More information about the other sites studied for swing space can be found below in the folder named "Swing Space at Moxley Field".
________________________________________________________
Summary of High School Options Studied, presented to the SBC on 5/26/21:
________________________________________________________
Summary of the Preliminary Design Program (PDP) Options
See the link below to view the entire report
__________________________________________
The Preliminary Design Program (PDP) submission was sent to the MSBA on 3/5/20.
To view the complete submission, follow the link below:
https://www.dropbox.com/s/9xkzip75ijmag9a/1.%20Entire%20PDP%20Document.pdf?dl=0