DESIGN

The Schematic Design Report (SDR) submission was sent to the MSBA on 12/17/21.

To view the complete submission, follow the link below:

https://clientportal.vertexeng.com/fl/7YcCabyJM6/Watertown_HS_-_MSBA_Schematic_Design_Submission_

____________________________________________________

The Design Subcommittee prepared a memo. dated 11/2/21 for the Project Team, and School Building Committee with feedback, concerns, and questions.

https://clientportal.vertexeng.com/dl/gqDz8BTsED/211102_WSBC_Arch_Subcommittee_Feedback-1.pdf_

____________________________________________________

The Preferred Schematic Report (PSR) submission was sent to the MSBA on 7/2/21.

To view the complete submission, follow the link below:

https://clientportal.vertexeng.com/dl/eXOLE9icAR/WatertownHS_PSR_Report_2021_07_02.pdf_

SBC Voted on 6/2/21 to Approve Option 1H as the Preferred Schematic Report to be Submitted to the MSBA.

Design progress on Option 1H can be followed in the folder below.

________________________________________________________

Both the School Building Committee and the School Committee voted in June 2021

to name the high school swing space to be temporarily located at

Moxley Field from Fall 2022 thru Spring 2026

in honor of PFC Richard Moxley.

More information about the other sites studied for swing space can be found below in the folder named "Swing Space at Moxley Field".

________________________________________________________

Summary of High School Options Studied, presented to the SBC on 5/26/21:

________________________________________________________

Summary of the Preliminary Design Program (PDP) Options

See the link below to view the entire report

__________________________________________

The Preliminary Design Program (PDP) submission was sent to the MSBA on 3/5/20.

To view the complete submission, follow the link below:

https://www.dropbox.com/s/9xkzip75ijmag9a/1.%20Entire%20PDP%20Document.pdf?dl=0