Progress Report (4/15-4/21)
Progress:
Completed client handoff plan
Completed documentation plan
Met with client to show final changes for approval
Fixed all remaining bugs and tested branches
Merged branches into main branch in repo
Plans:
Final tests on main branch
Create video demos for client
Deliver documentation and videos to client
Finalize website materials
Record final demo video
Problems:
None
Progress Report (4/8-4/14)
Progress:
Finalized location selector fixes
Finalized tech talk and delivered presentation in class
Met with coach to discuss upcoming deliverables and finalization of code
Completed test plan assignment
Plans:
Complete client handoff plan
Complete documentation plan
Finalize code changes
Merge branches into main branch in repo
Meet with client to show final changes
Fix bugs in location selector
Problems:
None
Progress Report (4/1-4/7)
Progress:
Met with coach to review progress and receive feedback and suggestions for future improvements
Met with client to review progress and discuss coach-recommended changes
Worked on location selector bugs and sidebar selector
Worked on tech talk presentation
Plans:
Meet with client to show progress
Finalize location selector fixes
Merge feature branches into main branch in repo
Continue tech talk presentation development and practice
Complete test plan assignment
Problems:
None
Progress Report (3/24-3/31)
Progress:
Worked on implementing client's proposed UI changes
Got feedback from client on UI design
Began preparing content for tech talk
Met as a team to plan remaining tasks and timeline for the rest of the semester
Plans:
Continue implementing client-requested changes in the project repo
Create slides and finalize content for tech talk presentation
Begin practicing tech talk presentation
Problems:
None
Progress Report (3/3–3/9)
Progress:
Delivered midterm presentation
Met with client and reviewed UI redesign
Confirmed client approval of UI change suggestions
Discussed tech talk topic as a team and brainstormed key points to include
Added previous assignments on GitHub project board with attributions
Added planned goals to GitHub project board
Plans:
Begin implementation of UI changes in the project repository
Start coding the target metric selector
Continue planning tech talk content and structure
Problems / Challenges:
Need to wait for client to confirm the location selector change after discussing it with supervisor before implementing that portion of the UI redesign
Progress Report (2/24-3/2)
Progress:
Met with TA during coach meeting and reviewed missing assignments + next steps
Completed architecture diagram
Finalized platform selection documentation
Met as a team to outline and organize midterm presentation
Created and refined midterm slides
Prepared and practiced for midterm presentation
Plans:
Begin implementation phase based on finalized architecture
Incorporate feedback from midterm presentation
Meet with client to confirm UI and begin working in forked repo
Update GitHub project board with new and previous assignments
Problems / Challenges:
Needed to catch up on previously incomplete assignments