350000 sft | floor area
8.00 core bdt | project cost
240 days | project duration
Civil, Plumbing, Interior & Exterior Decoration | provided service
Total office solution
REGENCY GARMENTS LIMITED, CEPZ, CHITTAGONG
42000 sft sft | floor area
4.05 core bdt | project cost
160 days | project duration
fit-out | provided service
Total office solution.
EXECUTIVE GREENTEX LTD, MAONA, GAZIPUR
33000 sft | Working area
6.5 core bdt | project cost
12 months | project duration
Internal Civil Construction and fit-out | provided service
Total office solution.
PROGRESS APPARELS (BD) LTD, AEPZ, NARAYANGANJ
10500 sft | Working area
1.92 core bdt | project cost
06 months | project duration
Interior Decoration and fit-out | provided service
Total office solution.
COMTEXTILE (HK) LTD, DHAKA.
350000 sft | floor area
2.18 core bdt | project cost
120 days | project duration
Interior Decoration & Fit Out | provided service
Total office solution
ANANTA HUAXIANG LTD
9500 sft | floor area
2.21 core bdt | project cost
120 days | project duration
Design and fit-out | provided service
Total office solution
TEX ZIPPER, AEPZ
7000 sft | floor area
0.35 core bdt | project cost
40 days | project duration
Design and fit-out | provided service
Total office solution
ANANTA APPARELS LTD OF ANANTA GROUP, AEPZ
350000 sft I floor area
2.18 core bdt I project cost
120 days I project duration
Interior Decoration & Fit Out I provided service
Total office solution
UHM LIMITED, AEPZ
15000 sft | floor area
.70 core bdt | project cost
60 days | project duration
Design and fit-out | provided service
Total office solution
UNIVERSAL MENSWEAR, AEPZ
13000 sft | floor area
1.23 core bdt | project cost
120 days | project duration
Design and fit-out | provided service
Total office solution
JAY JAY MILLS BD LTD, CEPZ
5500 sft I floor area
.35 core bdt I project cost
30 days I project duration
Work Station & Furniture I provided service
Total office solution