Welcome to the general Timeline. Here, all updates and events will be posted. Included must be date, description and source, if possible with a link. Timeline sections in any other articles (such as the SN articles) should only refer to this page.
Events and activities are assigned to the days according to local time.
This page should be kept in a manner that it is search-friendly (CTRL+F).
BN: Super heavy booster serial number (first stage of the rocket)
CH4: (Liquid) methane
COPV: Composite overwrapped pressure vessel (black helium tank for tank pressurisation)
FST: FutureSpaceTourist
GSE: Ground support equipment, including ground tanks
IT: Integration tower (for catching boosters and stacking starship)
LN2: Liquid nitrogen
LOX: Liquid oxygen
LR: Liebherr crane
NET: No earlier than [+date] (but very likely later)
NSF: NASASpaceflight
OLM: Orbital launch mount
OLS: Orbital launch site (the east part of the launch site)
PB: Power bay or comms building (at the far east of the OLS)
PPS: Propellant production site (prop prod site)
QD: Quick disconnect (arm)
RB: Raptor boost
RC: Road closure (prim and sec - primary and secondary)
RC: Raptor Center (same as raptor boost, but with gimballing capability)
RSN: Raptor engine serial number
RVac: Raptor vacuum engine
SH: Starhopper
SF: Static fire
SN: Starship serial number (upper stage of the rocket)
SoLS: Suborbital launch site
SPMT: Self propelled modular transporter
TFR: Temporary flight restriction (for flight tests, issued by FAA)
TPS: Thermal protection system heat shield tiles (hexagonal black tiles)
NET July/August 2022: Starship orbital test flight; FAA draft environmental review has closed its public phase; FAA deadline currently May 31[1].
Date
Description
Source
Link
11.06.2022
New building near production site: wall being added
B8 methane tank in high bay
B7 has all 33 engines installed according to Elon Musk
White mystery structure spotted in tent 1
High bay 2 work continued
Ballast loaded onto an SPMT
S24 in high bay 1
OLM Booster QD rear hood reinstalled
NSF
Nic
LabPadre
10.06.2022
B7.1 test tank stacked in high bay 1
I-beams deliverd to production site
Starfactory work continued [Why is there a wall towards the tents?]
S24 worked on in high bay 1
PPS plant worked on, antenna installed [?]
Earth work at PPS
S25 tank section in mid bay
Chopsticks worked on as well as OLM
Concrete work near SoLS pad A: Berm work to SoLS tank farm
Concrete broken up outside fence at launch site main entrance
EDOME test tank at launch site
S27 aft dome barrel section moved to tent 1 (quad)
Parts lifted into white mystery box (possibly a Starlink loader)
Chopsticks tested: lifted
NSF
Mary
Nic
LabPadre
09.06.2022
High bay 2/megabay cladding work; half of the roof seems to be installed
Starfactory work continued
S25 tank section moved to mid bay
Booster aft section moved around
Ground work for future expansion
S24 lifted off SoLS pad A by LR11000X, put on transport stand; moved back to production site, entered high bay 1
NSF
Mary
Nic
LabPadre
08.06.2022
Beams delivered to production site
Quad barrel sleeve moved between fence and tent 1; worked on near tent 1; moved into tent 1
B7.1 cmn dome section as booster fwd dome for a test tank
High bay 2 work continued
Starfactory work continued
New building near production site work continued
EDOME test tank moved to the launch site
LR11000X moved towards S24 at pad A, connected to it
SoLS pad B worked on, possibly installing a new QD
NSF
Mary
Nic
LabPadre
07.06.2022
SoLS tank farm LN2? delivery
OLS tank farm many deliveries of LOX/LN2
Boston dynamics dog ZEUS and APOLLO spotted
SoLS earth work continued
B7 in high bay 2: at least one of the chines have been removed
Mystery structure (black column with 4 feet) lifted onto a truck
B7.1 cmn section spotted, being used as a booster fwd dome of a new test tank; crews work on it; later moved
Raptor installation truck spotted
Booster load spreader moved at production site
Starfactory work continued
Stuctural test stand cap worked on (the one with a tank on top)
S24 cryo proof test #3 at SoLS Pad A, possibly with thrust ram tests; LOX tank fully frosted; CH4 only started later; huge depress vent before loading CH4 continued to top
OLM QD hood extension (rear part) moved back to launch site
-Roberts Road Complex:
--OLIT: No new sections built, but additional work on previous segments; segment 5 (third built, level of QD arm) gets hardware for QD arm; raceway installed on the columns that will be opposite the OLM [couldn't they also be rails for chopsticks??]
--Megabay: concrete poured over rebar; cross bracings seen near tents area
--Starfactory: More pile drilling work
--Elon Musk render: Megabay entrance will be to the north; starfactory will have two different roof hights
-Pad 29-A:
--OLM: all legs in place
--Crane base spotted for crane that will stack OLIT
--OLIT: Remaining concrete work appears to be done; work continues on future location for drawworks on opposite side of OLM
--GSE line covers spotted near the pad
--Octagonal pad work continued; purpose still unknown
NSF
Mary
Nic
LabPadre
06.06.2022
Mystery box moved in front of tent 3
S25? payload section / nc barrel in front of tents
HVAC systems delivered on a flatbet
Starfactory work continued, more beams added towards southwest
Old test tanks and SN16 aft section at PPS
White mystery box moved again; according to NSF it might be a Starlink V2 satellite loader
More beams delivered to production site
LR11000X moved away from pad A ahead of S24 test
S24 cryo proof test #2 at SoLS pad A, possibly including the thurst rams to simulate structural loads on aft dome during lift off (force by engines); LOX tank frosted up to half, followed by CH4 and second half of LOX tanks
NSF
Mary
Nic
LabPadre
05.06.2022
B8 LOX tank moved from high bay 1 to high bay 2
Video released by Elon Musk:
-B7 and S24 still planned to complete orbital flight test
-Starlink V2 will be deployed in pairs of 2 satellites each
-Picture of B7 engine section with Raptor 2 engines and shielding
-Renders of Starbase and Cape production facilities
S24 some TPS tiles replaced (those who fell off during first ambient test)
OLM worked on
SoLS pad B work continued
CH4 delivery to OLS tank farm
SoLS grass vent
New building structure work continued near production site
S25 cmn dome and mid LOX sections in high bay 1
NSF
Mary
LabPadre
04.06.2022
Nice sunrise
Pad A closed for S24 lifting operations at 07:40 am
S24 aft flaps folded; ship lifted by LR11000X onto SoLS pad A for thrust ram tests; work around aft section; later detached from crane
Starfactory and high bay 2 work continued
S25? Payload bay/nc barrel section spotted; no tiles yet
Work on new building structure continued facing hwy 4 at production site
S25 mid-LOX and common dome sections moved into high bay 1; common dome section stacked onto mid-LOX section
NSF
Mary
Nic
LabPadre
03.06.2022
Two ring flat dome sleeve lifted into mid bay and stacked onto EDOME section
B7 last grid fin installed Dome jig spotted in tent
S25 nosecone both fwd flaps installed
Booster QD hood extension at production site
New building structure beginning to be built at production site, columns lifted
OLM booster QD vented as crews were working near it
New booster transport stand work continued
High bay 2 work continued; 3 levels of side wall panneling still missing; roof work has progressed
S25 sections staged outside high bay 1
B8 LOX tank section rotated in high bay
LR11000X picked up a load spreader at SoLS
Ship barrel sleeves in front of tents with TPS tile attachment points
EDOME test tank worked on in mid bay
S24 disconnected from OLS cryo station QD; QD adapter installed [?]
S24 moved to SoLS pad A, attached to LR11000X load spreader
SoLS pad A: Last main Fill/Drain LOX and CH4 pipes attached to QD panel, now complete
Cape: All 6 legs of OLM at 39A now vertical, base completed (William Harwood)
B8 transport stand moved to the build site
B8 LOX tank moved inside high bay 1; placed on new booster transport stand [vid 04]
NSF
Mary
LabPadre
02.06.2022
Mystery stucture still in tent 1
Two Raptor 2 engines delivered
SN16 scrapping continued
S25 nosecone TPS tiles work continued; fwd flaps installed
Stage assembled for a meeting
Development double barrel sleeve spotted ("This is likely a development section for welding the new dome design")
B7 second grid fin installed, third later this day
OLM booster QD hood extension moved to production site storage area, unknown reason
OLMo work continued
SoLS pad A preparations continued
Starhopper meintenance work
S24 cryo proof test at OLS cryo station; CH4 tank frosted, followed by LOX tank, both tanks fully frosted, detanked, depressed; passed the test according to Elon Musk
FAA: Section 4f of the Environmental Assessment completed today as last big milestone; release still target for June 13
NSF
Mary
Nic
LabPadre
01.06.2022
Road closed at 17:24, pad cleared at 17:56 for potential testing; farm venting at 17:57; road opened at around 22:00
OLS tank farm: several deliveries of LOX/LN2 and CH4; work continued SoLS tank farm: LN2 delivered
OLM work continued; work on booster QD hood
S24 repair work continued and completed
High bay 2 work continued
B8 LOX tank stacked on engine section in high bay 1; after being stacked and destacked twice
SN16 disassembly continued; aft section rolled to scrap yard
Booster methane barrel section (triple) spotted
S25 nosecone TPS tiles work continued
Mystery box work continued
Ship transfer tube loaded onto a truck near gate B3
Starfactory work continued
B7 raptor engine installation continued; first grid fin installed
NSF
Mary
Nic
LabPadre
Date
Description
Source
Link
31.05.2022
S25 nosecone TPS tiles work in tent 3 continued
Mystery box worked on
SN16 worked on at top of tank section; scrapping
Fwd dome (flat design) moved into tent
Old booster header tank repurposed as some sort of horizontal storage tank [?]
Starfactory work continued
B8 engine section moved from tent to high bay (header tank visible)
S25 nosecone moved out of tent 3, tiles work continued
S24 pressurized, dents visibly disappeared
OLM work continued; inside of legs have received new shielding; work on booster QD and hood continued
SoLS Pad B upgrade work continued
S25? fwd dome section (sleeved) spotted
B7 disconnected from bridge crane in high bay 2 ahead of a potential roll out; engine installation continued
Standard TFR updated for June
Faa: Release of EA delayed; intended new date of issuing now June 13 (Christian Davenport)
NSF
Mary
Nic
LabPadre
30.05.2022
[No video]
S24 new pipe with expansion loops lifted into payload bay hatch; additional parts of raceway aerocover added
29.05.2022
OLM and booster QD work continued
S24: crews worked on raceway; reparations continued; fwd aerocover not yet installed at aft flap
SoLS Pad B old ship QD has been removed
Ship common dome spotted with TPS tiles installed
Ship flap aerocover spotted
Dome with new design spotted in front of tents next to a ship transfer tube (still wraped up)
S25 nosecone TPS tiles work continued in tent 3
LCH4 delivered to OLS tank farm
NSF
Mary
LabPadre
28.05.2022
High bay 2/Megabay roof contstruction continued
Booster aft dome section has been sleeved recently [?]
Mystery structure spotted in tent 1
S25? nosecone TPS tiles work in tent 3 continued
Raptor engines SN62 and SN77 delivered to production site
Booster fwd tank #2 spotted [B8/B9, barely readable]
S24 reparation works continued throughout the day on the section around the fwd at OLS cryo site
OLM work continued; modifications on QD hood
NSF
Nic
LabPadre
27.05.2022
QD arm rotated
OLS tank farm venting a lot
S25 nosecone in tent 3 work has progressed
EDOME barrel outside tents, hooked to crane
SN16 aft flap removed
Booster methane sump delivered at gate B3; also a ship thrust puck
High bay 2 roof work continued
S24 ambient proof test, tanks didn't frost up; OLS tank farm and OLM were venting; S24 lost several tiles from nosecone barrel during the test after a loud boom was heared; fwd dome and cmn dome depress vents (new venting locations compared to older ships; ullage vents)
S24 damaged pipe (bent) removed after the testing
Stand moved
Roadway kit for challenging terrain and SPMTs moved (SPMT on SPMT)
Ship QD (on QD arm) retraction test in the evening
NSF
Mary
LabPadre
26.05.2022
OLM booster QD hood backside removed during the night
S24 rolled from high bay 1 to the launch site on SpaceX's SPMTs
S24: three areas of TPS tiles around the stacking welds still missing; six unusual hexagonal tiles on nose's leeward side
S24 moved to OLS cryo station, attached to QD; first ever ambient venting at 16:26 CDT
LOX delivery to OLS tank farm
SoLS tank farm beam work continued
Earth work at the launch site main entrance (Gate D2)
SPMT moved to launch site
Temporary buildings from roof of OLS power bay/comms building relocated and installed near the SoLS tank farm and pads
Work on popellant production plant
Booster transfer pipe section spotted
Crane sections continued to leave the site
High bay 2 roof work continued
Raptor 2 engine SN70 moved into high bay 2/mega bay for installation on B7; R center or R boost equipment still missing
Everyday Astronaut: Release of the second part of Starbase tour (OLS):
-Orbital flight will follow same trajectory as originally released by FCC exhibit
-Booster has a 250t catch weight, goal is 200t; mach 0.5 at start of landing burn; chines will be facing perpendicular to catch arms
-HLS mostly digital work currently; focus is orbital test flight
-Starlink 2.0: 7m size, some allready on site, 1.25t weight, only fit in Starship, has higher throughput and useful bits
-Roberts Road:
--East end: Hangar X booster transporter empty
--Area for upcoming parking space cleared in the north of hangar X
--OLIT 2 segments: 5th and 6th segments (according to construction order which doesn't correspond levels) now structurally complete; 5th segment has an aditional floor; legs for 7th sement ready on concrete pad, together with some small beams; legs for 8th and 9th segments onsite
---Cryogenic pipes delivered to the tents area, being prepared for installation on OLIT segments ahead of stacking
---Segments numbered 1-2-5-3-4 (from oldest to newest)
--Mega bay foundations now complete; pile driller moved away
--Starfactory foundation work continued; slower than expected
--Trees and bushes removed
-Pad 39-A:
--OLM leg installation has started: 3 out of 6 already installed, no elbows yet
--OLIT base not progressed; likely teams are waiting for the concrete to cure before pouring the next level
NSF
Mary
Nic
LabPadre
25.05.2022
High bay 2 stair parts delivered
Stiffener ring rmoved from a stand
Edome barrel (triple) spotted for the first time, likely as part of a new test tank, near gate B3/tent 1; stiffeners and lead-ins
Ship fwd dome cleaned
Jackhammer broke up concrete at production site
B8 worked on in high bay 1, will still being connected to high bay bridge crane
Mystery box work continued
High bay 2 work continued; new kind of roof beams lifted
Starfactory work continued
In place machiening equipment set up in high tent next to high bay 2
More crane and SPMT parts left the site
S25 fwd dome lifted on sleeving stand; sleeved with corresponding triple with circular hole
Scrap coils of stainless steel left production site
OLS tank farm LN2 tank venting
CH4 deliveries to OLS tank farm continued
OLM: work on the QD hoood
Ship cryo station at OLS: QD work continued
NSF
Mary
Nic
LabPadre
24.05.2022
Methane deliveries to OLS tank farm; also LN2 and LOX delivered
OLS tank farm GSE plumbing work continued; strainer removed at CH4 site
OLM minor work continued
SoLS pad A: Work and access platform installed at the ship QD
S25 nosecone TPS tiles installation nearly complete in tent 3
B7 work in high bay 2/megabay continued
SN16 aft flaps moved in the wind outside the tents
Triple barrel section with a circular hole (ship fwd dome sleeve) moved into tent 1; moved out again
Raptor 2 engine SN74 delivered
Water pumped away after morning rain
Fagioli SPMT parts left starbase on trucks
NSF
Mary
Nic
LabPadre
23.05.2022
High bay 2 more roof beams lifted; looks finished now
PPS venting
Starfactory work continued
B8 LOX tank work continued in high bay 1
Crawler crane disassembly started at high bay 2
Mystery box white painting continued
Scrap ring moved
Aft cap transport stand loaded onto a truck
Construction work near the production site; work on a new concrete foundation
SPMT loaded onto a truck (Old red Fagioli)
Structural test stand work continued
Raptor installation platform for OLM is currently next to SoLS pad B
Chopstick work continued
OLM work continued; new black back part of the booster QD cover spotted earlier now installed
NSF
Mary
Nic
LabPadre
22.05.2022
High bay 2: installation of roof beams continued, soon to be finished
RC scheduled for Monday
Hardware "Tooling" column spotted at production site
New booster transfer stand work continued
OLM booster QD cover attached to crane and moved at launch site; but not yet installed
CH4 deliveries continued to OLS tank farm
NSF
Mary
LabPadre
21.05.2022
OLS tank farm venting as LN2 was delivered
OLS tank farm work continued
Mystery box that has been painted white recently attached to a crane
Office building looking like LC-39A's crew access arm spotted outside after years in Ground Fabrication building
High bay 2 construction continued
SPMTs moved at production site
NSF
Mary
Nic
LabPadre
20.05.2022
OLM work continued; OLS CH4 subcoolers and OLM venting [line cleaning?]
SoLS Pad A preparation work continued; ground work near the pad continued as well
LN2 delivered to SoLS tank farm ahead of possible S24 testing; suborbital tank farm worked on
Starfactory work continued, crews worked on roof beams
B8 still connected to bridge crane in high bay 1
Mystery box being painted white
High bay 2 work continued, eg on work platform installation near the top
New booster transport stand work continued
Tent 3: Ship nosecone TPS tiles work continued (possibly S25?)
NSF
Mary
LabPadre
19.05.2022
Deliveries to launch site
CH4 delivered to OLS tank farm
Chopsticks work continued
SoLS Pad A preparation work continued
Two new Raptor 2 engines delivered: SN63 identified
B8 methane transfer tube lifted into LOX tank
New stand parts delivered to production site
B7 work in high bay 2 continued
Starfactory work continued, more wall panels added
High bay 2 [megabay/widebay] work continued; work platform constructed near the top
NSF
Mary
Nic
LabPadre
18.05.2022
OLM, OLIT, chopsticks worked on a lot
LOX, CH4 deliveries to OLS tank farm; resumption of CH4 delivery might indicate static fire testing to start soon
Concrete work at LOX offload station at OLS tank farm
SoLS tank farm berm worked on
OLS ship cryo station QD work continued
LR11000X inspected
Ship transfer tube delivered to production site
Ship mid-LOX section spotted with installed TPS tiles
Raptor engine moved into high bay for installation on B7; antoher one moved from the high bay 2 to tent 1
High bay 2 construction work continued
Starfactory work continued; work on the roof
Intermodal container moved
High bay 1 bridge crane connected to B8 LOX tank section
Load spreader moved to production site
NSF
Mary
Nic
LabPadre
17.05.2022
High bay 2: roofing panels/beams lifted; wall work continued
Booster common dome lifted
SN16 tank section left high bay 2
S24 and B8 worked on in high bay 1
Starfactory work continued
Raptor 2 engines SN21, SN24, SN46, moved into high bay 2 for installation on B7
New parts for OLM delivered to launch site; booster QD-backside cover (covering the flexible cryo lines), other angular parts
OLIT and chopsticks work continued
OLS Cryo station ship QD worked on
NSF
Mary
Nic
LabPadre
16.05.2022
Chopsticks worked on
New SPMT delivered
Structural test stand work continued
Ship cryo station at OLS,work on QD
QD arm work continued
OLM work continued
Repair work at gate D2 (Launch site main entrance), concrete opened up
New gate installed at launch site (next to the tank farm wall and offloading station)
High bay 2 work continued
Rvac engine boxes spotted at the production site
SN16 flaps removed, quite ruggedly, nosecone scrapping continued; flaps loaded onto a flatbed
S24 aft flap installed
B7 worked on in high bay 2/mega bay
Raptor vacuum engine boxes left Boca Chica (one labelled SN 1)
Fuel storage tanks delivered (Enviro Cube)
High bay 1/mega bay: more roof beams lifted
Work on nosecones in tent 3, likely for S25 and S26 [vid 17]
NSF
Mary
Nic
LabPadre
15.05.2022
Raptor engines visible unter SN20/S20
S25 or S26 Mid-LOX section spotted
Stiffener ring removed from a 5-ring barrel section
S24 worked on in high bay 1
B8 LOX section (16 rings tall) moved into high bay 1, attached to bridge crane to resume stacking operations; stacked onto another 4-ring section (LOX tank now 20 out of 24 rings tall)
SN16 nosecone still sitting infront of bays
Counterweights removed from an SPMT
Chopsticks and OLM work continued
NSF
Mary
LabPadre
14.05.2022
B7 rolled back to the production site, entered gate B2 and then high bay 2 [filmed from gate B6], possibly for Raptor engine installation; later attached to bridge crane
SN16 nosecone sitting in front of bays, moved to the scrapyard
High bay 2 [megabay according to Musk/widebay] wall panelling work continued
Raptor 2 engines delivered from McGregor, SN66 identified
OLM worked on
Elon Musk Starbase tour with Everyday Astronaut, Part 1 released; key take aways:
-First orbital flight by B7 and S24, likely with Starlink satellites in an electrically actuated dispenser
-Ullage gas thrusters on both ship and booster
-Thrust to weight ratio of full stack will be around 1.5 at lift off
-Ship fwd flaps will need to be improved massively, possibly even removing them or moving them more to the leeward side
-No more suborbital flights
-B7 120 degrees chines layout make sense due to pressure [?]; B7 will have lighter grid fins
-Future boosters will have less grid fins, not more than 3
-Megabay [high bay 2] supports up to 12 work stations, is 30-40 ft taller than high bay 1 and has 4x usable area
NSF
Mary
Nic
LabPadre
13.05.2022
Booster QD on OLM is retracted
B7 lifted from OLM onto transport stand by LR11000X
SoLS Pad A: Ship QD added
SoLS tank farm vented slightly
SN16 tank section still in high bay 2
Starfactory wall installation continued
New booster transport stand work continued
S25 flaps spotted
Booster load spreader picked up by high bay 2 bridge crane for first time
NSF
Mary
LabPadre
12.05.2022
Chopsticks work continued
OLM/B7 work on "engine" section
B7 inspection
LN2 delivery to OLS tank farm
Structural test stand worked on
SoLS Pad A preparation work continued
Ground work at SoLS
LR11000X moved to OLS, OLM, connected to B7 via loadspreader
OLM booster QD hood painted black
SN20/S20 has replaced SN16 at the rocket garden
Work on mystery structure at production site
Stafactory siding installation continued, move beams added
S24 worked on in high bay 1
High bay 2 work continued, small roof beams installation began (roof frames)
Raptor 2 delivered (unknown serial number)
Delivery, packed in white sheets and labelled "UTF 12CCJ/F/E", to production site
Booster transport stand moved to OLM
SN16 nosecone has been removed from rest in high bay 2, sits now in front of tent [vid 13]
NSF
Mary
Nic
LabPadre
11.05.2022
SN20/S20 rolled back from launch site to production site, to rocket garden; lifting eyes have been removed last night
S21 aft section scrapped, parts cut off
Starfactory work continued, wall panels installation continued
S24 has been unhooked from bridge crane in high bay 1, scaffolding for payload bay stacking has been removed, work continued
High bay 2 work continued, more wall panels installed, back side now fully covered; rooftop beams installed (for the upper roof, lower roof has been fully installed)
SN16 attached to high bay 2 bridge crane, while its stand rolled back to rocket garden through gate A3
Delivery in black boxes (labelled with SN4 and SN1 ?) to production site
S26 aft dome spotted in front of tents; S26 quad for payload bay/nosecone barrel section spotted (it's still a quad, extra ring will be welded on top inside the high bay), moved into high bay 1; S26 aft dome sleeve (4-ring) spotted outside the tents, flipped
Nosecone in tent 3 TPS tile installation picking up pace
S26 aft dome lifted onto sleeving stand
Ground work at PPS continued
B7/OLM QD reconnected after it has been disconnected
B7 cryo proof test on OLM, both tanks fully frosted up; first ever booster/OLM QD retraction test under cryogenic conditions
-Roberts road:
--Hangar X: New B1064 Falcon heavy rocket side booster spotted; fairing delivered for refurbishment; new parking area norht of it; concrete pathways construction started on the east side, indicating no further extension of the building
--Starfactory: Two new tents assembled to support construction; concrete spread footings nearly completed
--High bays: Pile drillers began to work on the foundations, rebar already being added
--OLIT: Fifth section assembly began, three columns added; sixth section starting soon with feet placed, seventh section might start soon as well
--Entrance road completed
Pad 39A:
--Second tent now completed
--OLIT base is being expanded with walls coming out to the west and away from the OLM, possibly for draw works, however, the design is certainly different to Starbase where the extension is made of steel beams instead of concrete walls
--OLM: Rebars coming out of ground for the legs, the six legs have been spotted north of it
--Octagonal clearing of a new foundation spotted west of the OLIT and OLM, unknown purpose
NSF
Mary
Nic
LabPadre
10.05.2022
B7 LOX hatch reopened, worked inside tank; work on OLM/booster QD
Chopsticks work continued
OLIT plumbing lifted and installed
SoLS Pad A preparation work continued (likely
for S24 test campaign)
Work on booster transport stand
Starfactory first two side covering panels installed
SN16 moved to high bay 2 [NSF called it megabay] by two SPMTs after lifting eyes have been installed last night; potentially for som testing; later connected to bridge crane
B8 LOX tank worked on
S24 still hooked to bridge crane in high bay 1; welding work continued
High bay work continued on top levels
New nosecone in tent 3: Thermal blankets applied
Black boxes delivered to production site
Elon Musk: hopes for first orbital attempt in the summer and an uncrewed mission to Mars in 3 to 5 years
NSF
Mary
Nic
LabPadre
09.05.2022
Construction work at PPS near rocket garden, with excavators
B8 aft tank worked on the outside
S24 worked on in high bay 1, rotated for welding; payload door visible
Starfactory work continued
High bay 2: work continued, more wall panels added at the back side
Ship leg skirt section with can cursher cap on top of it spotted at PPS
SPMTs moved under SN16 at rocket garden
B5 stand worked on
Raptor installation platform near the OLM
B7 cryo proof test on OLM; both tank fully frosted up befor detanking
NSF
Mary
Nic
LabPadre
08.05.2022
B7 work on OLM continued through LOX tank access hole; work on a raceway
QD arm work continued
B8 LOX tank section still waiting outside bay area
Nosecone and barrel section worked on in tent 3
S24 tank section worked on in high bay, Nosecone (with barrel section and fwd dome section) stacked onto tank section
FCC approval for communication for orbital test renewed (May 21 - November 21)
Raptor installation platform moved to OLM [vid 09]
NSF
Mary
LabPadre
07.05.2022
S24 tank section moved from mid bay into high bay 1 [enough space now as B7 has left]
B7 worked on at OLM; work through LOX access hatch while still hooked to LR11000X; OLM QD hood opened, extended, QD connected; later crane disconnected from B7 (16:30)
Pump truck worked at SoLS [vacuum truck, "hydroexcavation" truck, normally used to remove loose dirt, gravel... according to Graves/Pearson]
LR11000X moved away from OLS
S24 tank section lifted in high bay 1; moved around
Starfactory construction work continued
Part of a nosecone spotted outside tent 3
NSF
Nic
LabPadre
06.05.2022
B7 moved out high bay 1, prepared for roll out (delayed a bit due to lighning); rolled back shortly
SoLS preparation work continued
Starfactory work continued
S24 nosecone (stacked on barrel section) seen high bay 1
High bay 2 construction work continued
B7 rolled out to the launch site for the second time [despite speculation after transfer tube failure] (no grid fins installed yet)
B7 lifted onto OLM by LR11000X, after chopsticks moved out of the way
FAA: Section 106 review completed today
Florida: All six legs for OLM delivered to pad, assembly of 5th OLIT section began, new concrete base under construction at LC39-A (Stranger)
NSF
Mary
Nic
LabPadre
05.05.2022
High bay 2 construction continued, more beams lifted and installed
Stairs production behind high bay 1 continued
B7 rebair work in high bay 1 continued
New flat dome design shown
Booster aft cap assembly lifted and moved into tent 1
New booster transport stand work continued
Front end loader worked at PPS
Drone flight at rocket garden/ PPS (inspections/drone test?)
Starfactory work continued, more roof beams installed
S24 tank section still waiting in mid bay
Mystery box (the rusty one near Gate B4) attached to crane and lifted
Counterweights moved to production site by SPMT, possibly for B7 roll out in the near future
LR11000X moved with load spreader, likely for future B7 lift
Booster QD on OLM worked on
Chopsticks worked on
Unknown item lifted over launch site wall at SoLS
OLM vented, possibly Raptor QD vents [?]
NSF
Mary
Nic
LabPadre
04.05.2022
OLM work continued; work with a special load spreader
Ship QD arm work continued
SoLS Pad A: all 6 thrust rams have been installed
SoLS concrete work continued
Wide bay 2 work continued
Mystery box work continued; another mystery box shown as well
Starfactory work continued
Air conditioner unit delivered
SPMTs being rearranged
NSF
Mary
Nic
LabPadre
03.05.2022
Work at the top of high bay 2 during night
B7 work in high bay 1 continued
High bay 2: wall panels missing on two levels at the back and north side, 5 levels missing on the south side; work continued
Starfactory work continued
New booster transport stand work continued, securing clamps being added
OLM work continued
Rvac thrust rams/simulators installation on SoLS pad A
LN2 delivery to OLS tank farm
Structural test stand work continued
US Fish & Wildlife Service documents sent to CNBC via FOIA request, biological and conference opinion based on the review of the effects of the proposed Starship program
NSF
Mary
Nic
LabPadre
02.05.2022
SoLS Pad A work continued to prepare it for testing; concrete work near it
New Ship QD plate added to the new QD stand at Starship cryo station next to OLIT
Structural test stand welding work
GSE plumbing cleaned
Excavator working at SoLS
GSE plumbing moved on flatbed at launch site
Ship QD arm work continued
New GSE hoses delivered to launch site
Starfactroy construction work continued, more beams added
Faro vantage laser tracker for precise construction spotted
More Appleton crane parts moved to PPS
Delivery of new unknown structure to production site
New scissor lifts spotted at production site
NSF
Mary
Nic
LabPadre
01.05.2022
Chopsticks worked on
Helium containers are at the OLS tank farm
S24 and B7 worked on in high bay 1
Appleton Marine crane parts moved to PPS; possibly to leave Starbase
LN2 and LOX deliveries to OLS tank farm
OLM work continued
NSF
Mary
LabPadre
Date
Description
Source
Link
30.04.2022
Ship QD arm work continued after the new QD has been installed
S24 still attached to high bay bridge crane
Booster aft cap assembly shown
High bay 2 [ex widebay] work continued
S21 scrapping continued
Starfactory work continued
NSF
Nic
LabPadre
29.04.2022
QD arm, new ship QD installation continued; detached from LR11000X
B7 work in high bay 1 continued
S24 stacking preparations continued
Starfactory work continued
Large hardware delivered to production site near the new tent
Astro pak machine (for metal surface treatment) delivered
Transport stand moved on SPMT
Rvac thrust simulators have now been assembled
OLS tank farm venting from LN2 tank
Air conditioners delivered to production site
Road closed at 17:14 for unknown reason, opened at 17:52
Chopsticks: diagonal braces at the stabilisation extensions added again
First OLM water deluge system test at 09:00:33 pm [vid 30]
NSF
Mary
LabPadre
Starship Gazer
28,04.2022
Ship Raptor vacuum thrust rams preparation work at launch site
Ship QD with updated design arrived at luanch site; installation on QD arm
Workers on beam sculpture at PPS
High bay 2 [ex wide bay] work continued
S24 nosecone attached to bridge crane in high bay 1
Starfactory work continued
S21 scrapped section at PPS
Booster aft cap assembly
Dome parts delivered
Raptor 2 engine SN45 delivered
NSF
Mary
Nic
LabPadre
27.04.2022
Tent 3: several nosecones worked on; polished
High bay 2 [ex wide bay] work continued, more beams lifted; bridge crane shown
B7 work continued in high bay 1
Starfactory work continued
S21 remains moved to PPS
Road work next to rocket garden continued
Mystery box work continued
New booster transport stand work continued
Field machining equipment arrived at production site "In-Place Machining"
Stairs and other parts delivered
SoLS Pad A work continued, eg on additional structure
B4 with old Raptor 1 engines shown
QD arm overhaul continued; LR11000X moved to it, parts lifted onto it
OLM work continued
NSF
Mary
Nic
LabPadre
26.04.2022
SoLS Pad A installation of thrust simulation equipment continued; Rvac thrust simulators and stands near it
OLS tank farm: more plumbing being installed at the CH4 pump site; LOX and LN2 deliveries
Raptor van arrived at Starbase, delivered one new lego themed engine, two trucked away, one missing its head
High bay 2 [wide bay] work continued
S24 fwd dome section (fully tiled) moved from tent 3 to high bay for future stacking; lifted [likely placed on a new stand]
Smooth fwd dome outside dome
B8 fwd section seen in mid bay
High bay 2 [wide bay]; stairs lifted into it
NSF
Mary
Nic
LabPadre
25.04.2022
OLM and chopsticks worked on
SoLS Pad A work continued
Structural test stand worked on
OLS tank farm plumbing work continued at pumping area
CH4 deliveries to OLS tank farm
High bay 2 (wide bay) work continued, work platform removed
Starfactory work continued, more beams added
Curved stand parts delivered
B7 disconnected from bridge crane in high bay; moved into the corner
B8 LOX tank worked outside
Groundwork near the Rocket Garden
High bay 1: Work on some supporting beams
S24 nosecone spotted in high bay
NSF
Mary
Nic
LabPadre
24.04.2022
SoLS Pad A work continued for preparing testing
QD arm work continued
OLS tank farm work continued, plumbing installed
New transfer tubes for booster spotted
B7 worked on at high bay; transfer tube possibly being repaired; hydraulic power unit shown
Mystery box at production site
Deliveries to production site, unknown parts, dome segments
Work on new booster stand
NSF
Mary
Nic LabPadre
23.04.2022
B7 worked on in high bay; leaked picture from inside LOX tank shows transfer tube scrunched
New transfer tube for unknown booster delivered
Old cargo door prototype shown
Work on new ship nosecone in tent 3
OLM work continued
SoLS pad A work continued, brown metal part lifted and installed
Chopsticks tested, raised and lowered [vid 24]
NSF
Nic
LabPadre
22.04.2022
Two smooth? nosecones in tent 3
Scrap dome in front of tents
Booster aft section (sleeved) prepared to flip; later flipped; great views from the inside of aft section with plumbing
New transport stand [again not much shown]
B7 in high bay: chine has been opened up
Road work in front of prdouction site
StarFactory work continued
Wide bay: Work platform lowered
Black Mystery box spotted at production site, connected to a crane
S24 tank section worked on in mid bay
Load spreader disconnected from S24 nosecone
SoLS concrete work
OLS: Work continued on GSE piping
Bystronic laser cutter delivered to production site
Parts for a new stand? delivered
NSF
Mary
LabPadre
21.04.2022
Three new Raptor 2 engines delivered, legp themed; RSN51 identified
FCC document: Wide bay called "High Bay 2"
Booster common dome sleeve moved
Ship load spreader moved at production site
Booster transport stand work continued at launch? site
Concrete work at production site entrance (Gate B2)
S21 at scrap yard; TPS tiles and white blanket torn off
Work on new stand continued
Starfactory production building work continued [name has been confirmed by label spotted on beams]
Grey turbine like parts delivered
SPMT moved weights to productioin site
Three Rvac thrust simulators moved to launch site, offloaded near SoLS Pad A and installed in the pad
SoLS: Berm under construction!
OLM work continued
OLIT: Work on Chopsticks rail
NSF
Mary
Nic
LabPadre
20.04.2022
LN2 tanker trucks at PPS, venting
Ground fabrication building shown
Smooth nosecone spotted in tent
B7 worked on in high bay
Starship factory starfactory girders installed
Old cargo door prototype still around at production site
Starship thrust simulator moved to SoLS; fit checks on Pad A; removed again
Grove GMK 1550 boom element delivered
New booster thrust puck delivered
Ship thrust simulator lifted again into Pad A [vid 21]
-Roberts road:
--Hangar X: New Fence splitting the offload area into two parts, one likely for fairing half delivery/refurbishment/roll out; More material for interior
--Road to north paved for increase in activity
--4 OLIT segments prepared, 3rd and 4th segment received parts for central elevator truss; feet for 5th segment prepared; more feet ready
--Starfactory: Construction starting, cut-outs for concretes spread footings visible
--Clearing for high bays continued, access road construction started between bay area and starfactory area
--Retention pond being filled
-Pad 39A:
--Cocnrete work on OLIT base continued, first stage complete; work on the two back walls, that will hold the draw work system; panels removed
--Foundations for the six OLM legs appear to being built up to ground level after earth work last week
--New white tent added in the south; frame for a second tent next to it
--Work on upgrading hydrogen sphere continued
NSF
Nic
LabPadre
19.04.2022
B7 worked on in high bay, especially aft section
Wide bay work continued [according to new official documents called wide bay 2]
New production tent work continued
Starfactory work continued, first horizontal beam installed
Raptor V2 engine SN42 delivered
Structural test stand QD worked on
OLIT new plumbing lifted by LR11000X
NSF
Mary
Nic
LabPadre
18.04.2022
B7 prepared for lifting, transport stand prepared, lifted by LR11000X and placed onto transport stand (alignment pin not used); load spreader and crane disconnected from B7; rolled back to production site (reason yet unknown)
B8 moved within high bay by bridge crane; then moved out of high bay, likely to make place for B7
Construction of new factory building that will replace the production tents (often referred to as "Starfactory") continued with first beams being placed
Dismantling of a container back wall at production site near gate B3
Wide bay work continued
New production tent work continued; first awnings added
B7 moved into high bay
NSF
Mary
Nic
LabPadre
17.04.2022
OLM raceway covers installation continued
B7 umbilical disconnected ahead of possibly lifting it off the structural test stand
New mystery structure [spotted yesterday] now delivered to launch site
Nosecone in tent 3 has alignment jig attached [S25?]
B8 aft #4 tank section (4-ring, part of LOX tank) prepared for lifting in front of high bay; lifted and placed on a stand; LOX tank moved within high bay, lifted by bridge crane and stacked onto aft #4 section (LOX tank now 16 rings tall)
NSF
Mary
LabPadre
16.04.2022
Crane counterweighs transported by SPMT
S21 scrapping continued
New tent construction continued
B7 connected to LR11000X
Tank trucks deliveries to OLS tank farm
Rusty mystery structure delivered
Ground work for possible future starfactory shown
Old methane theader tank design for booster spotted at PPS
Nosecone in tent 3 being prepared for aerosurfaces
NSF
Nic
Mary
LabPadre
15.04.2022
B8 LOX tank stacked: cmn dome and aft #2 sections stacked onto aft #3 section
New booster stand workded on
Wide bay work during the night (welding?)
S21 tank section finally being scrapped
Coil of stainless steel delivered
Work on new tent behind wide bay continued
LR11000X moved to B7, load spreader still attached
B4 transport stand worked on
B7 aft section worked on with an unknown orange part of equipment
NSF
Mary
LabPadre
14.04.2022
PPS earth and concrete work near entrance to rocket garden
B5 stand and aft section worked on
Unknown part transported by SPMT
Wide bay work continued
B8 common dome and aft #2 section otuside high bay (8 rings tall stack)
Old COPV aerocover seen at production site
S24 tank section worked on in mid bay
New flat dome placed on sleeving stand (the third one made overall, according to NSF still a pathfinder); 2-ring sleeve sleeved on dome
New tent going up at production site
Coil of stainless steel moved
B7 work on QD area
B7 transport stand (with alignment pins) placed on two SPMTs
B7 cryo proof test on structural test stand, possibly also hydraulic thrust test; ice formed on both tanks; in the second round, LOX tank got fully frosty
NSF
Nic
LabPadre
13.04.2022
Nosecone in tent 3 shown
Workers on high bay bar balcony
High bay construction elevator dismantling continued
Beams delivered to production site, as well as other parts, possibly for wide bay
Original cargo door pathfinder (5-ring nc barrel) shown
Mystery parts (curved boxes with SpaceX logo and windows) delivered to production site, unknown purpose, interior yet to be finished
Tanker trucks deliveries to OLS tank farm, some ventings
B7 some sort of white felt near its aft section
Chopsticks worked on, especially on the stabilisation pin arms
B7 ambient proof test (pneumatic test) on structural test stand late night [vid 14]
NSF
Mary
LabPadre
12.04.2022
Tanker truck deliveries to OLS tank farm
B5 worked on at PPS, especially near stand and aft section plumbing
S25 5-ring nosecone barrel section spotted in frotn of tent
New flat dome got rectangular section cut out [pahtfinder?], then moved away (for scrapping); according to NSF it was the second flat dome that was built
New structure beginning to be assembled (rings on pistons?) at build site, unknown purpose
S25 nosecone barrel stiffener removed, then moved into wind break (low bay)
Old cargo door pathfinder (5-ring nosecone barrel) with cut in dispenser hole seen at high bay
S24 nosecone still attached to crane in high bay
Third flat dome shown in front tent
S25 aft section spotted in tent
Wide bay work continued, more beams lifted into place on top level
High bay elevator removal work continued
Hwy 4 work next to production stie continued
Delieveries to production site
Wall building work at production site next to cate B3 continued
B7 ambient pressure test, (inspected by bird), tank farm active; pressure release through all vents at common and fwd dome
NSF
Mary
LabPadre
11.04.2022
OLM work continued, parts lifted onto it
B7 work around QD as preparation for testing
OLS tank farm deliveries by tanker trucks
B4 transport stand worked on
Earth work at SoLS pad B near SN20/S20
Hwy 4 road work next to production site contined
Wide bay work continued
Wall building work continued at production! site with sun pannel installation
-Roberts road
--Hangar X: exterior walls to extensions completed, concrete work progressed; northern wall now completely pannelled with glass; delivery area complete with large concrete pad; door possibly for fairing halves
--OLIT progression: third and fourth sections being built [deep dive into this by Zack Golden], concrete foundations for four more sections nearly complete
--Starship Factory: Pile drilling operations likely complete; ground clearing underway for possible high/wide bay
--Retention pond excavations continued on western side
-Pad 39 A:
--Concrete work on OLIT base has begun, still some rebar seen
--Work on old hydrogen storage sphere, possibly for use with LCH4, subcoolers have been installed next to it [2 out of 4!!]
--LOX subcoolers spotted on the opposite side of the complex (where previous starship OLM was planned and partially built in 2019 and removed in October 2020)
NSF
Mary
LabPadre
10.04.2022
Tank trucker deliveries to OLS tank farm
B7 testing preparation work contiuned via work platform and access hole, GSE lines connected to QD plate
Booster methane transfer tube delivered, unloaded
Wide bay work continued
New smaller dome spotted
NSF
Mary
LabPadre
09.04.2022
S24 nosecone attached to high bay bridge crane, stacked onto payload section [nc barrel section]
B7 preparations for testing on structural test stand, hooked up to GSE; work platform erected near it
NSF
Mary
LabPadre
see below
08.04.2022
S24 lifted in high bay by bridge crane [stacking?], later tank section left high bay
S24 nosecone detached from crane in front of ten 3, later moved to high bay
Booster load spreader attached to LR11000X
B7 attached to LR11000X, QD retracted, destacked from OLM and placed onto structural test stand [ex can crusher]
Tracking station tracked the Ax-1 mission [Axiom]
High bay construction elevator removed as a permanent elevator has been installed inside the high bay
S24 worked on in mid bay; payload section [nosecone barrel section] moved to high bay via hwy 4
NSF
Mary
LabPadre
07.04.2022
OLM work continued, new lines added
Hydraulic gantry assembled over structural test stand at OLS to lift it
Launch site wall work continued, new wall panels added
S24 nosecone work continued
Ship transfer tube spotted at launch site
New crane tracks delivered to production site/PPS, old ones moved away
Domes moved to scrap yard [one with new design?]
Wide bay construction work continued
QD arm retracted and chopsticks lifted during a test, rotated at the top
SN20/S20 moved next to SoLS pad B, reason unknown
NSF
Mary
LabPadre
06.04.2022
S24 sections stacked and welded together in high bay [which?]
B7/OLM worked on; LOX tank hatch installed on B7
S20 worked on [small aerocovers removed]
Deliveries to launch site
[B7] Booster transport stand work continued, especially on alignment pin
Launch site wall work continued, see through panels and some beams removed
GSE plumbing removed and lowered from OLIT, new GSE plumbing delivered and lifted on OLIT
Hydraulig gantry parts delivered to launch site [what for?]
Booster header tank loaded onto a truck
Ship thrust puck hoisted (pipes already installed)
Robotic wielder spotted in high bay
Wide bay work continued, more beams lifted, roof construction has started (not on the very top)
Hwy 4 road work next to starbase sign
Ship QD arm disconnect moved back to the launch site, close up showing the details of pins, connections, and cameras on the QD plate
Foundation work at rocket garden
S24 nosecone TPS tiles work continued
Tent 3 S24 fwd dome section
NSF
Mary
Nic
LabPadre
05.04.2022
S24 aft section removed from B8 aft section after fit check of stage separation system
Fwd dome section spotted in tent 3, likely for S24 [??]
Raptor engine delivered to production site
S24 LOX tank section moved from mid bay to high bay, attached to crane
Wide bay construction work continued, more beams lifted into place
Booster header tank domes spotted at production site
Booster aft dome sleeve moved out of tent 1; flipped
Booster aft dome with cap moved onto sleeving stand
[B7] transport stand worked on, especially on the alignment pins
Ship QD arm: Ship QD plate and piping attached to LR11000X and removed
Launch site wall building work continued
Chopsticks worked on
NSF
Mary
Nic
LabPadre
04.04.2020
Ship aft section moved into tent 3 by a crane (likely S25 aft section)
B7 has been disconnected form LR11000X; briefly hooked to it again and unhooked shortly after; B7 connected to booster QD on OLM
SoLS tank farm LN2 deliveries [Can we expect testing at SoLS to restart soon?]
OLS tank farm: subcoolers active
Alignment pins from B4 transport stand removed and installed on B7 transport stand
LR11000X moved away from OLM and B7
B7 vented from fwd dome vents ahead of cryo proof test
B7 first cryo proof test, both tanks fully frosted up at the nearly same pace (CH4 tank frost reaching the top faster); during the filling process, the cmn dome vents constantly vented for short periods; venting stopped for ~1min, then LOX tank filling continued and reached top after some time; detanking started soon after that; later in the night, RCS cmn dome vents and fwd dome vents depress vented and frost/condensation started to reappear shortly after decreasing fully and final full depress vents
Wide bay construction work continued, more beams lifted; second bridge crane has been installed as well
S24 aft section moved to high bay, and stacked onto B8 fwd section
SPMT rolled down hwy 4
Starship methane transfer tube delivered (with anti-vortex device)
Booster header tank domes delivered to production site
NSF
Mary
Nic
LabPadre
03.04.2022
OLS tank farm: GSE piping worked on at CH4 site, LN2 tank vented; heat exchanger moved
Common dome section (Scrap, see vid 04) spotted on a transport stand in front of tent 1
S24 nosecone moved out of tent 3; two-three nosecone barrel sections being worked on in tent 3 with TPS tiles being installed [S25, S26... ?]
Booster header tank spotted in tents
B8 work in high bay continued, weld cleaned while the tank got rotated
Wide bay: Bridge crane lifted into place and installed on girders
NSF
Mary
LabPadre
02.04.2022
Wide bay: Work continued; bridge crane part (white) moved; first bridge crane girder lifted and installed; second bridge crane girder lifted onto the rail and installed, followed by third, SpaceX custom design; fourth girder lifted
B8 common dome section moved in front of high bay, LOX tank vents seen; lifted onto aft #2 section (LOX tank now 8 rings tall)
Raptor engine nr 59 spotted in storage
B7 attached to LR11000X, QD hood on OLM closed, B7 lifted onto OLM by LR11000X (not by chopstics as some have expected, and not on structural test stand as others expected), a lot of engine attachment point hardware visible; chopsticks slightly rotated towards booster
NSF
Mary
Nic
LabPadre
01.04.2022
OLIT work continued
Wide bay: More beams lifted into place for roof level; wall work on level 6&7 continued
S24 nosecone TPS tile installation nearing completion
B8 aft tank #2 section (4-ring, no lead-ins) attached to crane and moved into high bay
OLS tank farm LN2 loudspeaker tank vented
B7 work on aft section/transport stand; detached from LR11000X and load spreader (reason unknown)
LR11000X rolled away from B7 towards OLM, Chopsticks turned out of the way
NSF
Mary
LabPadre
Date
Description
Source
Link
31.03.2022
OLS tank farm deliveries (propellant / LN2)
OLM work continued
B7 rolled out from high bay to launch site during early morning road closure, followed by a flood light car; later attached to LR11000X
B7 work continued around aft section/transport stand ahead of possible lift; according to NSF, the "chines are aerodynamic surfaces that increase the Booster's crossrange when returning to the launch site", they also cover COPVs
SPMT returned to production site
B8 CH4 tank stacking continued in high bay
Part of a new booster transport stand delivered to production site
S24 nosecone TPS tiles work continued
Common dome section placed on sleeving stand (already sleeved with a 1.5 ring sleeve!)
Building work next to high bay continued
NSF update on design changes as part of the continues iterative approach on Starship:
-S20 (first complete heat shield) is functionally out of date as it can only be launched on B4 and possibly B5
-B4 first booster with 29 engines, engine shields, aerocovers, grid fins...; but out of date as well
-Naming conventions for barrel sections: Quint, Quad, Triple, Double, Single (according to number of rings, each 6ft tall)
-Starship (old/new layout): 20 rings + nosecone; aft section (5/4), mid LOX section (4/4), cmn some section (3/4), fwd dome section (4/3), nc barrel section (4/5)
--Aft: ship QD moved from second to third ring, possibly for shorter plumbing or more space for 3 additional Rvac engines; nobs and holes for booster/ship integration reversed: since S22 and B7, holes are on booster (negative side) and nobs on ship (positive side); new aft domes with redesigned thrust puck for Raptor V2
--Mid LOX: same but sits one ring lower
--Common dome section: Methane header tank removed (to nosecone); new main LOX tank vents to be the same as ullage thruster vents on booster, possibly also for attitude control and possibly nosecone RCS thruster
--Fwd dome section: Shortened, giving one ring to nosecone [tank sizes remain the same, as dome is now welded higher]
--Nc barrel: now quint, possibly to facilitate cargo door manufacturing, first one seen on S24, including dispenser mechanism
--Nosecone: 4 to 2 rows of panels; methane header tank to be included; S24 nosecone under construction has two header tank vents and no RCS thrusters
--Domes with flatter design
--Not yet seen but anounced: Fwd flap design, streched tank section, increased raptor engine numbers
-Booster: improvements in order to optimize the dry mass, as well as reduction of landing propellant amount
--Thrust section: B3, B4, B5 had three standard 1.8m/6ft ring; B7 thrust section has four 1.4m/4.5ft rings, stringers now extended all the way down; B7+ will support Raptor 2 engines (vs B4 V1.5 engines)
--Header tanks: B5 had a long tube tank on the side of the LOX tank; B7 has new design that is located in the middle and encloses the transfer tube (coaxial tank); new transfer tubes with plate that has three holes (likely for providing landing LOX for center 3 engines)
--Pressurization lines: B4, B5 had 4 lines for each tank; B7 only two per tank
--Aerosurfaces: B7 has new COPVs arrangement (2 vertical columns instead of horizontal ring); covered by "nominal" sections, forming chines (dual purpose: protect COPVs, additional cross sectional surface area - additional cross range, extra drag and reduced approach velocity
NSF
Mary
Nic
LabPadre
30.03.2022
OLS tank farm work continued; wall work continued
Three Raptor V2 engines delivered and moved into a production tent
OLS: work on the new fence building continued
OLM work on booster QD
New nosecone barrel section (5-ring) spotted outside tents
Haas VM-6-High-Performance VMC delivered ("This can be used to machine metal parts on site")
3-ring barrel section moved in front of tent 1
NSF
Mary
Nic
LabPadre
29.03.2022
B7 moved inside high bay, now at its entrance
OLM work continued, also on booster QD
OLS tank farm: LOX delivery; work on new tank farm wall continued rapidly, top covers added at the western segment
SPMT power back transported at launch site
Structural test stand (can cursher) work continued at launch site, more parts added
B7 work continued around aft section
S24 payload bay section / nc barrel section near the entrance of tent 3
S24 nosecone work continued on TPS tiles
PPS work on propellant production plant
NSF
Mary
Nic
LabPadre
28.03.2022
Ship QD panel worked on on QD arm
OLS tank farm: work behind the wall
Structural test stand worked on at launch site
Zeus (boston dynamics spot dog robot) spotted at launch site
B7 work at fwd dome, as well as around COPV cover
Wide bay work continued
Tent 3: work on a nosecone barrel section
S24 tank section waiting in mid bay; nc barrel section TPS tile installation continued
Construction work outside production site between tent 1 and hwy 4
PPS: Crane counterweight tray and weights loaded onto an SPMT
NSF
Mary
Nic
see below
27.03.2022
OLS tank farm: LOX delivered
NSF
Mary
Nic
LabPadre
26.03.2022
Wide bay construction work continued, first additional wall panel for level 7 has been added (likely yesterday)
S24 nosecone TPS tiles got tape around flap
OLS tank farm: loudspeeker tank venting
Launch site fence section got removed (the one at the main entrance with Gate D2 sign)
Yellow and red crane parts transported away from launch site
NSF
Nic
LabPadre
25.03.2022
OLS tank farm: wall construction progressed rapidly
B4 transport stand alignment pins not engaged
New booster QD plate delivered and unloaded at launch site for booster QD; B7's QD design is different from B4
Structural test stand worked on at launch site
LR11000X moved away from OLM
B7 disconnected from high bay crane, moved out of high bay and rolled back in later, moved out again
B8 fwd tank section #4 moved into high bay (4-ring)
B7 moved back into high bay again
Wide bay work continued, wall panels on level 6 being added
Chopstick rotated south and lowered
NSF
Mary
Nic
LabPadre
24.03.2022
B4 lifted off OLM by LR11000X and placed onto transport stand
Wide bay: wall panels installation continued on level 6
S24 nc barrel TPS installation progress shown including cut out for potential cargo door, lifted by a crane and moved; work on nosecone
B4 disconnected from LR11000X crane and moved away towards Landing pad / SoLS [vid 25]
NSF
Mary
Nic
LabPadre
23.03.2022
B4 attached to LR11000X ahead of possible lift from OLM; transport stand being prepared; booster QD retracted slowly
OLM: new steel side parts welded to a leg, likely for future plumbing covers
Chopsticks worked on
Launch site: flexible pipes being worked on
S24 nosecone barrel section TPS work contineud, as well as on nosecone in tent 3
Wide bay work continued, construction elevator in use inside wide bay
Air conditioning unit lifted into place at PPS
Dome segments (new design) outside tents on a cart
New booster thrust puck at production site (delivered recently)
NSF
Mary
Nic
LabPadre
22.03.2022
S24 nosecone barrel: TPS blankets and its black net covering being workded on, first TPS tiles being added
Booster fwd dome lifted onto sleeving stand [B9/B10/B11?, same as on March 20?], sleeved with flipped fwd dome sleeve (likely the one from March 20, 3-ring) after it rolled out of tent 1 again
B7.1 barrel sleeve "Aft dome barrel assy" (4-ring) moved towards sleeving stand, apparently for a new test tank
Production site concrete work
Wide bay: level 5 and 6 wall panel work continued
Thrust puck for future booster delivered
Booster test stand with hydraulics moved to launch site by two SPMTs (lower part of can crusher), possibly for B4 testing
Booster load spreader bar attached to LR11000X, possibly to lift B4 off OLM; crane moved towards B4
OLS tank farm: new plumbing prepared
Booster transport stand worked on and prepared at launch site (the one with the alignment pins), moved to OLS next to B4 by new SpaceX SPMTs
Chopsticks opened
NSF
Mary
Nic
LabPadre
21.03.2022
B7 grid fins infront of S25 mid-LOX barrel section
S24 in mid bay
Booster aft section with header tank spotted in tents [B?]
B7: crew work on platform at cmn dome, chine moved
B4 propellant load test with CH4
NSF
Nic
LabPadre
20.03.2022
B7: chines installed: aerocovers for the vertical COPVs
New booster fwd dome spotted in tent [B9/B10?]
New ship common dome infront of tents [new desing]
New booster comn dome section moved out of tent 1 (4-ring, sleeved), ullage vents preinstalled [B8/B9?]; attached to flipping jig, flipped
Wide bay: more beams lifted onto top level (roof level), second half of the roof structure beginning to be built
S20 moved away from chopsticks
OLS tank farm: LOX deliveries
New booster fwd dome [B9/B10?] lifted onto sleeving stand
New booster fwd dome sleeve [B9/B10?] moved outside tent 1, prepared for flipping
NSF
Mary
LabPadre
19.03.2022
OLM work continued
OLS tank farm: LOX and LN2 deliveries; GSE piping work continued at landing pad loading area; wall construction continued westwards
Production sit consturction
S24? nosecone barrel section with payload dispenser: white thermal blankets being installed
Scrap ship common dome infront tent 1
Booster header tank lifted [B8/B9?] and moved into tent 2?
QD arm: ship QD retracted from SN20/S20, then arm retracted away from ship ahead of destacking
Starship 4/20: S20 destacked from B4 by chopsticks, road remained open for the first time
NSF
Mary
Nic
LabPadre
18.03.2022
Booster header tank still outside tents (for LOX) [B8/B9?]
Wide bay construction work continued: level 5 walls, top level beams
4-ring nosecone barrel section in front of tent 3 as well
Booster COPV aerocover at production site
Starship 4/20 [B4/S20] propellant load testing; OLS tank fram active; unlike a cryo proof test, wher only LN2 is used, here the tanks got filled with propellant (CH4/LOX); B4 LOX and CH4 tanks got frosty, followed by S20 tanks, only partially filled (0.5-2 rings); drone observed the test
SPMT moved around rocket garden / PPS
NSF
Mary
LabPadre
17.03.2022
Starship 4/20 cryo proof test continued
OLS tank farm: some venting from vent stack; work on plumbing infront 5 CH4 tanks; LN2 delivery
Work on one of the tracking dishes near Gate C2
OLM work continued, new metal part has been added on top of the coverings, welding work
Booster header tank outside tents [B8/B9?]
Entrance building work continued behind high bay and Stargate [?]
SpaceX SPMTs being assembled
Booster fwd dome sleeve in a tent
SN8 forward flap spotted at Brownsville Airport being displayed
NSF
Mary
Nic
LabPAdre
16.03.2022
Crane moved into tent 1
Ship aft section flipped (4-ring) [inside visible, new design], moved into tent 2
New flatter down design visiblea again
Wide bay: more preassembled roof beams lifted and installed; z-beams lifted as well
Tracking station: dishes lowered
S22: red tape added on TPS tiles around aft flap
Work on structural test stand at PPS
Launch site: hydraulic rams moved
Cargo door prototype and S24 nosecone still outside tent 3
Ship QD/SN20/S20 work on QD arm
OLM and OLIT work continued
Starship 4/20 [B4, S20] cryo test [with liquid nitrogen], much venting from OLS tank farm (all areas), OLIT vent indicating cryo flow through OLIT, OLM vent, frost on B4 tanks and S20 condensation, first time ship QD active with cryo [vid 17]
NSF
Mary
Nic
LabPadre
15.03.2022
SN20/S20 prepared for lifting between chopsticks
OLM work continued, wooden parts removed
Ship QD lines being cleaned
OLS tank farm: work on GSE piping around new CH4 tanks
Red crane parts delivered earlier this month now identified as Liebherr LTM 1300-6.2, at gate A2
Wide bay: New beams for roof level lifted and installed, wall levels being installed up to level 5 (of 11)
New dome design outside tents
SN20/S20 lifted by chopsticks onto B4 for second time, much faster than previously; third full stack; Ship QD arm extended to S20 [cont. vid 16]
-Roberts Road:
--Hangar X: Extension roof complete, side walls worked on, loading ramp along the wall under construction (facing parking location); expansion seems to have reached its limit; east side: wall painted black, large door entrance; Falcon 9 transporter spotted
--Water tower: Hooked up to ground pipes and closed off
--Berm being built to separate the Starship yard and the rest of the facility
--Retention pond began to be constructed at the west end of facility
--OLIT: First segment being constructed, 3 columns are up on construction stand, cross beams added; 5th beam ready for second segment; 5th foundation for segment now complete [add: NSF speculation that this would be enough turned out to be incorrect]
--Starship yard/factory: Progress on ground work, especially on pile drilling (holes filled with rebar and concrete); 6 east to west rows of piles (12 per row) have already been completed on northern side; half way done with seventh row; concrete yet missing
-Pad 39 A:
--OLIT base: concrete poured around the base of four support pillars; large crane next to it
--Two propellant tanks (spotted on NSF fleet cam on March 7) now placed at new fuel farm next to the Falcon ramp (old 2019 Starship foundation)
--Hydrogene sphere work continued; potentially for CH4 storage (usable storage capacity: 3218m3, compared to 2395m3 full stack Starship CH4 volume)
NSF
Mary
Nic
LabPadre
14.03.2022
SN20/S20 now at chopsticks, chopsticks closed in later
Ship QD extended (although SN20/S20 not yet stacked)
Launch site weather station work continued
Wide bay construction continued: first level 11 beams preassembled and lifted by LR11000 (for final roof level, no wall panels installed yet); followed by second one; more beams added on lower levels for outside support structure
Booster barrel section (3-ring) moved
Deliveries to production site
Production site: Concrete work
New black SPMTs delivered!
S24 nosecone now outside tent!
NSF
Mary
Nic
LabPadre
13.03.2022
Chopsticks raised early morning, lowered afterwards
Ship common dome scrap, booster aft section prepared for flipping
Booster aft section (4-ring) flipped; header tank part visible (with three-engine pipe outlets!) [B8/B9?]
OLM work contineud
LN2 delivered to OLS tank farm
GSE piping delivered to OLS tank farm
New booster transport stand shown at launch site
Crew worked on a weather station
SN20/S20 moved away from cryo pad and OLIT
SPMT counterweights adjusted
SN20/S20 moved to chopsticks [vid 14]
NSF
Mary
LabPadre
12.03.2022
B8 stacking started: fwd dome section lifted and stacked on another 3-ring section (LCH4 tank now 6/13 rings)
B4 one grid fin has moved/turned a bit
New building work along launch site wall continued, more beams installed
LR11000X moved towards OLS
QD arm, more parts removed by LR11000X; crane moved away from OLS after that
Unknown parts spotted at launch site
Starship factory: Foundation work next to tent 3 continued, concrete being poured
S24 Nosecone tent 3: TPS tiles installation nearly complete
NSF
Mary
Nic
LabPadre
11.03.2022
QD arm: parts of second claw uninstalled as well and lowered by LR11000X
B8 fwd section moved into high bay to start with stacking
B7 work through access hole near the weld
Wide bay: construction continued, wall panels being fixed, some level 5 panels have been installed
S24 still in mid bay
S24 nosecone barrel with payload dispenser: work continued on TPS blanket
LR11000X moved at OLS
Chopsticks connector bar delivered to OLS
Booster transport stand (new one) moved to launch site, concrete pad next to the circular tank; OLIT two beams erected and cross beams installed; new tower pads nearly complete; HangarX building extension towards pond nearly covered; Starship factory foundation work continued
LabPadre Florida update: Water storage near completion at Roberts road
NASA document: Artemis HLS mission plan updted, new images; depot Starship is shown to be 6 rings longer than regular tanker Starship (687m3 extra volume)
NSF
Mary
LabPadre
Scuba
10.03.2022
B7 CH4 tank section stacked onto LOX section at 12:47 am; grid fins still missing
S25 aft dome spotted, lifted onto sleeving stand; sleeved with 4-ring sleeve [flipped yesterday]; lifted of stand
Wide bay: Staircase consturction behind high bay continued; bracing installed (connection above the future entrance)
Payload bay pathfinder (not same as S24 nosecone barrel section?!)
B9 common dome sleeve (4-ring, RCS/ullage vents upside down) moved out of tent
S24 nosecone barrel section: TPS tile blankets added; another 5-ring section behind it
B9 common dome lifted onto sleeving stand, sleeved with common dome sleeve, lifted off sleeving stand and moved back into tent
Transfer tubes moved to scrapyard
Hwy4 road work continued
OLS, OLIT: rails inspected on movable work platform
QD arm work, one of the claws (stabilization arm) removed and lowered by LR11000X
Beam structure has been erected next to launch site entrance (behind the new entrance building)
SN20/S20 work through access hole, fan used
Work on loudspeaker tank at OLS tank farm
NSF
Mary
Nic
LabPadre
09.03.2022
Chopsticks work continued
QD arm work continued
SpaceX LR11000X fitted with new rigging, connected to one of the QD stabilization arms
Booster transport stand (old) moved towards production site
S25 aft dome sleeve prepared for flipping (4-ring), flipped
B4 vented (fwd dome depress vents)
McGregor: Raptor Vac engine test on horizontal test stand for about 0m02s?; first time with water deluge system
NSF
Nic
LabPadre
08.03.2022
Chopsticks tested (went to the top, opened, closed, moved, went down again, accompanied by drone)
B8 common dome section (4-ring) at scrap yard
LOX truck to lunch site
More red Liebherr crane parts delivered
Wide bay work continued on lower levels, wall panels being added, elevator installation continued, stair construction continued behind high bay
Dome sleeving stand modifications continued: New and differently shaped alignment jigs, possibly for differently shaped domes
B6? header tank scrapped
Booster fwd dome worked on at production site outside tents
New booster transport stand underwent testing (pins lifted and lowered by hydraulics)
OLS, OLIT: tower rails being worked on
Road work on hwy4 infront of OLS
Ship common dome section spotted in a tent
New nosecone spotted in tent 3
NSF
Mary
Nic
LabPadre
07.03.2022
B7 rotated in high bay
OLM work continued
Road work on hwy4 continued
Potential payload dispenser installed in nosecone barrel section believed to be S24
OLS tank farm: work around CH4 tanks
QD arm moved (retracted away from B4)
Wide bay: stair section lifted into it
B7 in high bay: arrangement of COPVs has changed from a ring around aft section to two vertical columns
Absorbtion columns that left Sanchez 2 weeks ago have arrived at Port Canaveral at 9:42am EST
NSF
Mary
Nic
LabPadre
WLAnimal
06.03.2022
S24 noseceone, fwd dome section, thrust section in tent; S25 common dome section/segment and another nosecone spotted in same tent
5-ring nosecone barrel section work continued
S22 work continued at PPS
Red crane parts delivered to production site
Work on new booster transport stand; old booster transport stand moved outside bay area by SPMT
B8 fwd tank #2 (3-ring) spotted ("goes directly underneath the forward dome section")
Dome cap delivered to production site
Wide bay work continued; installation of a construction lift
B8? fwd dome section spotted
LCH4 delivered to OLS tank farm, as well as LOX
OLM work continued
Deimos oil rig arrived at Port Pascagoula, Mississippi
NSF
Mary
LabPadre
05.03.2022
Booster fwd section spotted near other sections, another one in a tent
B7 aft section with a new design spotted at tent entrance: different QD plate and addition of a header tank!!, rolled out and moved towards high bay
Counterweights moved by SPTM
New booster transport stand still at PPS
Utility work next to Starbase sign / hwy4
S25? common dome section in tent
B7 tank section (which one?) lifted and moved in high bay; LOX section stacked onto thrust section, both tanks now fully stacked
OLM work continued; work on booster QD
NSF
Mary
Nic
LabPadre
04.03.2022
Ship cmn and aft dome, booster fwd and cmn dome lying around outside tents
Parts for structural test stand lifted into place
Wide bay: construction continued, more z-beams lifted into place
Dome sleeving stand being modified
B7 grid fins spotted, not painted black (yet?)
Work on GSE7 outside cable
OLM work
SN20/S20 work through access hole
Flexible pipe near methane offloading site at OLS tank farm; CH4 delivery
Parts delivered to OLS
B7 work in high bay
Damaged CH4 tank (truck) towed away (Stabilis)
Florida: First section for OLM at 39-a at KSC spotted![97]
Elon Musk: "SpaceX reprioritized to cyber defense & overcoming signal jamming. Will cause slight delays in Starship & Starlink V2."[98]
McGregor: Raptor 2 engine test on horizontal test stand for about 0m33s?; multiple very bright flashes at the end
NSF
Mary
LabPadre
03.03.2022
Tracking station: one dish used for Starlink 4-9
S22 single TPS tile attached
Wide bay: Work continued (more beams lifted)
LR11000 (Buckner) modifications continued, has now a double jib mast
Ship aft dome with new design spotted along with booster fwd and common dome
Stainless steel tube (possibly methane transfer) spotted
OLS tank farm: work around CH4 site continued; LOX deliveries
LR11000 lifted its boom and jib partially; followed by complete lift later
Masey's Gun Range: First structure (a tent) began construction
SN20/S20 cryo proof test, LOX tank fully filled, followed by CH4 tank (likely fully as well)
NSF
Nic
LabPadre
02.03.2022
B4 cryo test continued, LOX tank fully filled, CH4 partially, huge depress vents; loudspeaker vertical LN2 vent continued long in the morning; OLIT vented again
Chopsticks lowered
SoLS pad A upgrading work
Booster aft dome sleeve (4-ring) in front of tents, aft dome on sleeving stand, workers wrap up extending pipes for engines with plastic bags; aft dome sleeved [B8/B9?]
S24 nosecone TPS tiles work continued
S22 work at rocket garden/PPS continued around aft flaps
Wide bay work continued (wall panels being added on level 3&4)
Buckner LR11000 upgrade work continued
Ship wfd dome moved away from tents, ship aft dome moved into tents
Booster fwd section near high bay [B8?]
SPMT transported ballast from PPS
LR11000X laid down at 11:25 and gone back up later, reason unknown
Star Factory at Boca Chica: Foundatiion work looking very far in progress; building is expected to be over 300'ooo sq ft by 60' tall and will replace all the large production tents [RGV]
-Roberts road: Expansion continued, including the area for possible new Starship construction yard; two rusted feet spotted for building and transporting the OLIT segments, first pillar already delivered, toghether with some cross beams; ground pipes built that end near the tower construction area, ending in three concret squares (similar to PPS for data connections); large white tank, possibly for water, added onto circular gravel pad next to tower construction pad; hangar X work continued, roof beams in place, roof beginning to be added, parking space complete; levelling and drilling of holes for future Starship production buildings
-LC39A: Earth work continued near OLIT area, different lines being worked on
McGregor: Raptor 2 engine tests:
-on tripod test stand for about 0m07?s;
-on horizontal test stand for about 0m30s
-on horizontal test stand for about 0m01s
NSF
Mary
Nic
LabPadre
RGV
01.03.2022
OLS tank farm: LOX delivery
Booster aft dome, ship common dome and booster fwd dome at tent area
S22 aft flap work continued
Wide bay work continued, more beams lifted to top levels
LR11000 main boom reassembled
Chopsticks moved
B4 cryo test, both tanks frosted up, whole OLS tank farm active; OLIT was venting as well (although ship QD not active) [cont. vid 02]
NSF
Mary
Nic
LabPadre
Date
Description
Source
Link
28.02.2022
S24 tank section [complete?] in high bay; moved to mid bay early morning
Wide bay: level 2-4 wall segments completion continued; more beams lifted into place at the top
LR11000 parts delivered; derrick installed; counterweights loaded onto a SPMT, moved to production site
Booster fwd dome section spotted in a tent
S22 work through fwd hatch continued at PPS
Load spreader that has been used for lifting wide bay segments loaded onto truck for departure
Dirt work outside production site
Ship aft flap waiting to be offloaded at production sit
Booster fwd section moved out of tent
Pedestals delivered
OLM work continued
OLS tank farm: CH4 wall work continued; concrete pumped into forms
Deimos left port of Brownsville for Pascagoula, Mississippi, possibly for transformation work
Florida KSC: First OLIT parts (columns) spotted to be delivered
McGregor: Raptor 2 engine test on horizontal test stand for about 0m10s [captured live as well]
NSF
Mary
Nic
LabPadre
Trevor Mahlmann
27.02.2022
Buckner LR11000 modification work underway; complete boom reconfigured
B8 common dome seen
OLS tank farm: Wall work completion continued; CH4 truck waited at production site for delivery
New booster transport stand spotted at PPS; new guiding pins have been installed on both sides
SoLS: compressed nitrogen truck; LN2 delivery
NSF
Mary
LabPadre
26.02.2022
S22 work through access hole
Wide bay: more beams being added
LR11000 boom lowered, possibly for extension, new crane parts moved to production site
OLS tank farm: work at CH4 recondenser, concrete work at the brick and concrete wall that surrounds the CH4 site
NSF
Nic
LabPadre
25.02.2022
Crane mats removed from under LR11000X
OLS tank farm: Wall work around CH4 tanks continued (briks); LN2 delivery
OLM work continued
Crane parts delivered for LR11000 which is likely to get an upgrade
Wide bay work continued on level 2 and level 3 wall panels
Build rig, likely for domes, delivered
CH4 truck at production site
S24 common dome section stacked and welded on LOX section in high bay
NSF
Mary
LabPadre
24.02.2022
OLS tank farm: Methane tanks delivered yesterday now lifted into place next to the other larger two; third smaller (fifth in total) white horizontal tank moved to OLS tank farm by SPMT, followed by fourth and fifth (total seven); all five smaller CH4 tanks lfted into place
QD arm rapid retractio test at 15:04:30 More new LR11000 parts delivered
Wide bay: fourth corner segment lifted to level 9&10
-Roberts road: 67 acres large site; Hangar X expansion continued, second expansion started towards ponds; circular pad poured and filled with gravel next to OLIT construction foundations, purpose unclear; six new pad foundations for OLIT construction being worked on, and rusty steel parts spotted for building the segments; large rectangular pad now levelled for proposed 32000 ft2 facility for Starship construction (192000 ft2 expansion also proposed in phase 2), piles prepared for foundation
-LC39A: 4 large propellant tanks delivered for Starship pad, last week they were at the turn basin; no work on mobile service tower yet for Falcon payload integration; possible cut-outs in liquid hydrogen sphere; some earth work near future OLM pad
-LC49: No work yet, environmental review in progress
NSF
Mary
LabPadre
23.02.2022
S22 wor continued (especially TPS tiles) during the night
OLS tank farm work continued (eg. around new CH4 foundations, concrete work beginning at 02:28 am); LN2 and CH4 deliveries
LR11000X crane moved towards OLS; parts delivered; Two long white horizontal methane (CH4) tanks moved from PPS to OLS
OLIT and chopsticks work continued; as well as on OLM
S24? nosecone TPS tiles work continued in tent 3
Wide bay: Fourth and last segment of level 9&10(5) connected to LR11000, disconnected again; more beams lifted
SN15, S22 and SN16 at rocket garden
NSF
Mary
Nic
LabPadre
22.02.2022
Booster transport stand moved to build site on SPMT
LN2 delivery to OLS tank farm
OLS tank farm: wall construction work continued around CH4 tanks
OLS, IT (OLIT): work on movable platforms
Wide bay: more beams and parts delivered
New crane parts for LR11000 (Buckner owned crane, possibly reconfiguration)
S22 TPS tile work on aft flap at PPS, received aft aerocaps
New ship fwd flap delivered to production site
Ship nosecone barrel section assembled in high bay
S24 nosecone TPS tile work continued in tent 3
Bridge crane hook blocks mixed with some LR11000 parts
SN20/S20 and OLS tank farm cryo proof test, CH4 heat exchangers frosty, as well as LOX and partly CH4 tanks on Ship
McGregor: Two Raptor 2 engine tests on tripod test stand for about 0m09s and one for about 0m2.5s
NSF
Mary
Nic
LabPadre
21.02.2022
LOX deliveries continued
S24 nosecone work continued, especially on TPS tiles
B6 test tank disconnected
Transport stand moved at PPS by SPMT
Nosecone barrel section moved outside tent 3, possibly for a new cargo door prototype
4-ring section outside high bay; moved into high bay
Booster methane transfer tube delivered; new transfer tube design than previously seen on other boosters
Pedestals delivered to build site
Wide bay work on lower levels; LR11000 rstill attached to third top level segment; new beams delivered
S24 nosecone in tent 3 TPS tile work continued; a ship thrust section next to it
OLS: earth work continued for CH4 extension
NSF
Mary
Nic
LabPadre
20.02.2022
Wide bay: Second corner segment of level 9/10 lifted by LR11000 and installed, rigging uninstalled; connected to third segment, lifted
S22 outside high bay; moved to rocket garden (PPS)
LCH4 deliveries to OLS tank farm
OLM work continued
B8 common doem section moved out of high bay (destacked, likely to be scrapped [see: [111]])
NSF
Mary
LabPadre
19.02.2022
Chopstick test continued; lowered later that day
B8 common dome section lifted in high bay and stacked
OLS tank farm work continued; concrete work next to CH4 tanks (completing new foundations for new CH4 tanks); vertical cryogenic process pump installed at LOX side of OLS tank farm, more have been delivered
LN2 deliveries to OLS tank farm
Ship flap deliviered to build site
S22 moved out of high bay; flap installed; moved into high bay and out again
B6 test tank lifted at PPS
Wide bay: Staircase construction continued behind high bay
LNG (Liquid natural gas) purification stack removed from Boca Chica
Entrance building behind high bay construction continued, roof added
Booster aft caps spotted on a stand
Absorbtion column (second one) left Starbase at 09:02
NSF
Mary
Nic
LabPadre
18.02.2022
B4 cryo proof testing on OLM, LOX tank fully filled (frosty); methane subcoolers frosted up
B8 stacking began in high bay; 4-ring section lifted by bridge crane; aft tank #2 (4-ring section) moved into high bay, lifted and stacked; B8 common dome section (4-ring with ullage vents below stringers) outside high bay
Wide bay: second level 9/10(5) corner segment attached to LR11000; more beams delivered
LCH4 deliveries continued
First of several smaller LCH4 tanks moved from PPS to OLS tank farm [looks like half]
QD arm moved away from B4 (retracted)
First absorbtion column left Starbase at 9:35am
Chopsticks raised to the top of OLIT
McGregor: Raptor 2 engine test on horizontal test stand for about 1m42s
McGregor: Raptor 2 engine test on tripod test stand, duration unknown, only picture available
NSF
Mary
LabPadre
17.02.2022
OLS tank farm: LCH4 (liquid methane) deliveries; venting
OLM work continued; most of the gap covers have been painted grey as well
Ship section (4-ring) test fit with a booster fwd section, possibly B8 and S24; then removed again; another fit check followed
Wide bay: First segment of level 9/10(5) lifted by LR11000 and installed, there's no outside supporting structure on level 10 as this is going to be the top level; crane detached from segment; second segment attached to LR11000
B8 aft #2 section (4-ring) spotted outside high bay; being cleaned
Ship load spreader moved at production site
S22 has been disconnected from high bay bridge crane
SN20/S20 cryo proof test at OLS cryo pad; full frost on LOX tank; venting from engine chill vents
Vertical LN2 tank near bunker now called heat exchanger by NSF [the loudspeaker tank]; vented
S24 nosecone TPS tiles installation continued in tent 3 [nosecone shown previous vids also S24!]
Entry building next to high bay: Sidings installed
Mid bay: Maintenance work on roof
NSF
Mary
Nic
LabPadre
16.02.2022
SN20/S20: transport stand QD connected to S20; cryo proof test on OLS cryo pad, frost on both tanks, engine chill vents inside flaps; possibly testing the full OLS tank farm system including LCH4 side
S22 welding work continued, still connected to high bay crane
Wide bay construction work continued, wall panels added to level 9/10(5) segments; first connected to LR11000
B7 [?] aft section (4-ring) spotted [possibly the number is B9, difficult to read]
B2.1 and BN2.1 next to each other at PPS
Foundation work next to S16 possibly for another display/storage pad [add: for S22]
Nosecone in tent 3: TPS tiles applied; booster fwd dome section outside the tent
S24 thrust section hooked to crane inside tent 3
S25 common dome section spotted
FCC: approved SpaceX for vehicle communications for orbital test flight
McGregor: Raptor 2 engine test on horizontal test stand for about 0m10s; loud sonic-like boom at the start
NSF
Mary
Nic
LabPadre
15.02.2022
SN20/S20 moved away from chopsticks to its cryo stand at south of the OLS tank farm
OLS tank farm: LCH4 (red label) deliveries continued, as well as LN2 (blue/green) and LOX (yellow)
S22 nosecone (ex S21) welded to its tank section
QD arm plumbing work continued
Wathervane and anemometer (wind speed measurement) on Starhopper
LR11000 lowered near wide bay for jib extension (for lifting final wide bay segments); raised again
S21 tanks section work remains paused
Wide bay level 9/10 segements preassembly continued, first wall panels being added; last parts of two wide bay bridge cranes have been spotted
S25 nosecone barrel section spotted (5-ring)
B8 aft #2 and aft #3 sections spotted (4-ring)
Unknown parts spotted at production site (small diameter tubes?)
B2.1 and B6 test tanks, as well as cargo door pathfinder shown
S24 mid LOX section (4-rings with tiles) and common dome section (with tiles) and an unknown 4-ring sleeve (untiled) seen infront tents
Entrance building next to (behind) high bay work continued
"Nominal segments" delivered, yet unknown purpose
Ship QD arm venting spotted at 19:47:10
Cape Update NSF #1 [NSF planning weekly updates from now on, covering not only SpaceX]:
-Roberts Road Operations Area: Hangar X used for storage and refurbishment of Falcon 9 boosters; Hangar X is currently undergoing an extension; large amount of land being cleared as well as foundations prepared - likely for a new Starship build site 320'000 ft2 or 29'728 m2 building proposed; loading dock construction, as well as a circular structure with 9m diameter, possibly a foundation; 12 square concrete pads with the same layout at PPS for launch tower segments construction (3 segments at a time); road extension north towards Schwartz Rd, possibly for Falcon/Starship transportation
-Kennedy Space Center, LC-39A: Holes visible in an old spherical liquid hydrogen tank, possibly for LCH4; 4 horizontal LCH4 tanks visible below it (bought in 2019); yellow piling crane dismantled, foundation work for Starship launch pad possibly complete
-Cidco Road Facility: Today likely part of heat shield production process (not to be confused with bakery)
NSF
Mary
Nic
LabPadre
Starship Gazer
14.02.2022
Polaris program news: Jared Isaacman scheduled two flights on Crew Dragon but also one on Crewed Starship
OLS tank farm: First time venting from "mystery brown tank" at methane side
Starship 4/22: SN20/S20 destacked from B4 by chopsticks during road closure (RC 10:27am, pad cleared 10:52am, road opened 2:01pm, QD arm back into position at 2:15 8:09pm detached from chopsticks); some OLS tank farm ventig ahead of destacking and ship transport stand moved into position; ship QD arm retracted for operation S21 and S22: S22 tank section moved to high bay; S21 nosecone reassigned to S22; nosecone lifted and stacked onto S22 tank section in high bay
Wide bay: Work on level 9/10(5) segments (all) continued
S25 fwd dome sleeve outside tents (3-ring)
FAA: New target date for issuing final PEA is March 28
McGregor: Raptor 2 engine test on tripod test stand for about 0m05s; smooth quieter sound
NSF
Mary
Nic
LabPadre
FAA
13.02.2022
OLM work, some scaffolding reinstalled after presentation
OLS tank farm: First methane (LCH4, red truck sign) delivery! In total three trucks via landing pad
Controlled access area sign: Pre requirements: "FR clothing, 4-Gas monitor, hard hat, safety glasses, safety work shoes. Pad site work permit is required for all work in orbital tank farm"
Ship common dome [S24?] flipped (4-ring, access hole at top ring), moved into tent 1
Deliveries to production site (wrapped up)
B7 methane section moved from high by into mid bay, LOX section moved inside high bay, relocated
4-ring section moved into tent 2
NSF
Mary
LabPadre
12.02.2022
Workers on QD arm
OLM/B4 work on QD
Booster transport stand next to SoLS pad B
Jared Isaacman's Alpha Jet flew over Boca Chica
NSF
Nic
LabPadre
11.02.2022
Nosecone, ship fwd dome and nc barel section seen in tent 3
Wide bay: Wall panels continued to being added; level 3&4 nearly complete, some still missing on level 2; more beams added [add: z-girder according to RGV]; assembly of two level 9&10/5 corner segments continued (other two begun as well [vid 12]); more staircase assembly work behind high bay
Bigge LR1300 crane lowered in front wide bay
S22 tank section: work platform added at fwd dome section ahead of potential nosecone stacking
New building at the side/behind high bay work continued, taking form; likely to be some sort of entrance building from parking space
Chopsticks closed and lifted towards SN20/S20 lifting points; not yet attached
Jared Isaacman's Alpha Jet flew over starbase Boca Chica
OLS tank farm: Cryo proof test [see SN20 for timeline]
McGregor: Three Raptor 2 engine tests:
-horizontal test stand, duration unknown
-tripod test stand, for about 0m05s
-tripod test stand, for about 0m04s?
NSF
Mary
Nic
Jack
LabPadre
10.02.2022
SN20/S20 stacking operations by chopsticks; second full starship stack
Ship QD extended and attached to SN20/S20
Work around S20/B4 interface; chopsticks stabilization arms removed from S20
Landing pad: Workers prepared stage and equipment for Elon Musk's Starship presentation
Chopsticks disconnected from SN20/S20 and opened up [seen in vid 11]
Elon Musk Starship presentation
NSF
Mary
Nic
Jack
LabPadre
09.02.2022
Intermittent RC for today from 1am to 9:30am
SN20/S20 has moved between the chopsticks; chopsticks moved up to lifting points, later lowered again; S20 opened aft flaps (fwd flaps already opened)
QD arm work continued
OLS tank farm vertical LN2 tank venting
SoLS tank farm unusual venting from black tanks
RSN27 (Raptor 1) and RSN88 (Raptor 1.5) in tents
B9 comm dome (4-rings with ullage vents, stringers (less than one ring high) spotted outside tents
Wide bay work continued
Smooth nosecone (the one outside tent 3) being scrapped
SN20/S20 stacking operations by chopsticks [vid 10]
McGregor: Raptor 2 engine test on tripod test stand for about 0m51s; smooth sound
NSF
Mary
Nic
LabPadre
08.02.2022
LR11000X crane rotated
QD arm: curved part lowered down by LR11000X; preparation work continued
OLIT scaffolding being removed, so chopsticks could move
B4 grabbed by QD arm claws; work on the claws connectors
SN20/S20 work on QD; took them very long to disconnect the ship from the stand QD
Chopsticks: Scaffolding being removed
Excavator trying to remove water from landing pad near entrance
B6 test tank moved at PPS by SPMT
B2.1 test tank moved at PPS
Wide bay: LR11000 still connected to last level 7&8 segment, work on several areas continued
S22 work continued in mid bay; aft flap aerocover moved into mid bay
New tent spotted in tent 3
Berm tunnel on landing pad painted black, likely to prepare for presentation
SN20/S20 moved into position for stacking
NSF
Mary
Nic
LabPadre
07.02.2022
B4 disconnected from LR11000X load spreader 2:54 am
SPMT Coupler lifted; one of the two SPMTs moved away from under the B4 transport stand; stand moved away
New launch site fence painting work continued
QD arm work continued
OLIT work continued on movable work platforms
OLM/B4: booster QD work
Wide bay: last level 2 wall panels being installed; beams delivered
Ship transfer tube with anti-vortex device delivered ("The anti-vortex device prevents methane from cavitating and damaging Raptor engines")
5-ring nosecone barrel section scrapped
Long pipe lifted inside the high bay
Coil of stainless steel delivered
COPVs and potential vehicle parts delivered
OLS tank farm: work platforms erected around the the two horizontal large CH4 tanks, possibly for building a wall; insulated GSE pipe moved on landing pad
McGregor: Raptor 2 engine test on tripod test stand for about 1m18s; Mach Diamonds visible, started with yellow and green exhaust
NSF
Mary
Nic
LabPadre
06.02.2022
B4 work inside LOX tank; hatch closed at 5:30am
Wide bay: Fourth corner section of level 7&8/4 lifted at 8:20 am and installed
B4 prepared for lifting (ropes attached), lifted off transport stand and onto OLM for the fourth time, by LR11000X without the help of the chopsticks; transport stand removed
B4 secured on OLM, booster QD connected [great closeup]
Ship QD arm work continued; rotated away from B4 after stacking
Bridge crane girder delivered to production site, possibly for new wide bay
NSF
Mary
Nic
LabPadre
05.02.2022
B4 unhooked from LR11000X at 9:56am
Earth work between OLS tank farm and landing pad continued
OLM work continued
LR11000X moved towards OLS, load spreader lowered and unhooked
Crane load test bag storage boxes shown
Road work on hwy 4 near launch site continued
GSE4 scrapping continued
B4 moved slightly with transport stand
Two jets owned by Jared Isaacman (from Inspiration 4) flew over starbase several times
Wide bay: more beams lifted into place; more beams, likely for final level 9&10 (5), delivered; stair assembly continued next to high bay
Ship aft section flipped (4-ring)
Smooth nosecone with lifting jigs outside tent 3
B7 work on fwd section (still attached to bridge crane)
Chopsticks raised and lowered again; moved out of the way
B4 moved to OLS after LR11000X on an SPMT (the one from yesterday); attached
OLIT: work on rails via movable work platforms "window washers"
NSF
Mary
Nic
LabPadre
04.02.2022
Testing at OLS tank farm (possibly vertical CH4 tanks): road closure: road closed at around 6:52am; dish has been lowered; pad clear 1:37 pm; at the end a bit venting from the small vertical LN2 tank (with loudspeakers); road opened at 4:01pm
Power outages at shipyard in the morning
Nosecone moved in tent 3
B8 LCH4 sump next to transfer tube
Work on the building like structure (with redish beams) next to high bay continued
High bay: workers using the high bay balcony
Crane load test bag storage boxes shown
OLS tank farm: LN2 deliveries
Wide bay beams delivered
SPMT delivered ballast to launch site, possibly for B4 transport
NSF
Mary
LabPadre
03.02.2022
B3 methane manifold lying around at launch site
GSE4 stand moved to production site by SPMT
Wide bay third segment of level 7&8 still attached to LR11000
PPS: Ship leg skirt with can crusher top shown close up; work on the bottom part of the structural test stand; trench work near booster 5
B8 LCH4 tank sump [connecting the main LCH4 tank with the transfer tube/downcomer] delivered to production site
High bay load spreader connected to B7 methane tank section (no grid fins installed yet to fwd section)
Beams assembled next to high bay forming the framework of a small building
SpaceX cat spotted
B5 at PPS: hydraulic power unit removed
Elon Musk announced Starship presentation with full stack on Thursday, February 10th, 8pm CT (2am UTC)
NSF
Mary
Nic
LabPadre
02.02.2022
Can crusher top (top of structural test stand) put on aft skirt at PPS
OLM work continued; gaps between the shieldings covered
LR11000X moved to B4, load spreader picked up, hooked up
B4 engine bells have been painted grey [not today]
OLS tank farm work at the vertical CH4 tanks; earth work continued; consumables delivered
GSE4 remains (aft dome) removed from stand, scrapping continued
Starhopper maintenace work
Wide bay work on lower levels continued; some small wall panels installed
PPS: Earth work next to SN15 and SN16
S22 tank section work in mid bay continued, raceway has been installed, some of the TPS tile covering visible; work through acces hole
Tiles applied on a barrel section in a tent
B7 methane section has moved in high bay
NSF
Mary
Nic
LabPadre
01.02.2022
S22 raceway (preassembled) lifted into mid bay for installation, installed; work through access hole
Wide bay construction continued; LR11000 detached from second level 7&8 segment, attached to third segment, lifted at 2:35pm and installed; workers climbing on beams
Old ship leg skirt (2-ring) lifted onto a transport stand at PPS
B7: jig has been installed on its side
Domes cut up at scrapyard
Sleeving stand worked on
Dirt work continued at launch site
B4 grid fins unstrapped
FAA: EA is now at 2 out of 5, endangered species act consultation was finished on 31 January 2022 [cms.permits]
Roberts road update: OLIT assembly fixture pieces spotted, along with new foundations for assembling the OLIT sections
NSF
Mary
Nic
LabPadre
The Denks, Farrielle
Date
Description
Source
Link
31.01.2022
Chopsticks: water bags removed
B3 some remnants still lying around
OLM work continued
Crane ballast and counterweight cradle moved by SPMT
B8? fwd dome section/segment spotted in tent
S24? noseceone (smooth) spotted in tent 3; fwd flap mounting jig attached
S22 flap attachment jigs installed
Wide bay: installation of small vertical cross beams
B4 raptor nozzles have been painted grey [RGV]
RC for today canceled
New RCs for February 3-7 (10am-10pm), February 4 (6am-4pm)
NSF
Mary
Nic
LabPadre
30.01.2022
Ship aft section from yesterday removed from sleeving stand
Cargo door prototype still next to smooth nosecone
High bay bar looking finished from outside; work platforms being removed
Ship aft skirt (2-ring) spotted
OLM work continued
Crane water bags loaded onto chopsticks via cross bar
Chopsticks load testing: raised slightly, bags filled water, chopsticks lifted about 1/3 of tower and lowered again
NSF
Mary
LabPadre
29.01.2022
B4 work on an aerocover
B8 common dome section flipped at 10:57am Launch site wall construction work continued
OLM: Booster QD work continued
OLS tank farm: LN2 deliveries
Crane ballast bags for chopsticks moved at launch site
Wide bay: First section of level 7&8 (4) lifted by LR11000 at 10:00am and installed, work platforms have been installed on top of level 6; LR11000 attached to second segment, lifted at 3:27pm and installled
Ship aft barrel [S22, S24?] spotted outside tents, ship QD panel has moved upwards by one ring
Crane prepared for flipping rig
NSF
Mary
Nic
LabPadre
28.01.2022
S21 production appearing to have paused
LR11000 attached to first segment of level 7&8(4) of wide bay
Crane detached from nosecone infront of tent 3
Tracking site: one dish pointed towards launch site
OLS tank farm venting: both subcooler areas, near SN20/S20 stand, south berm; OLM vented for a long time (vent below QD lines); subcoolers frosted up after testing
McGregor: Raptor 2 engine test on vertical tripod test stand for the first time, for about 0m40s; mach diamonds visible
NSF
Mary
LabPadre
27.01.2022
OLS: Excavators work around SN20/S20 base
OLS: GSE piping readied on carts, laid out before being buried; OLM work continued
SoLS: concrete work around pad B
OLS tank farm: cryo deliveries; work on horizontal LCH4 tanks
Ship QD work continued, lines and cables being installed, work on the QD plate and lines
Chopsticks work on the downward extensions
OLS, IT: welding work, work on platform that moves up and down column
B7 moved moved around in the high bay
Nosecone hooked to crane outside tent 3
High bay rooftop bar work continued
13 engine booster aft cap aka "thrust puck" infront of tents
Odd shaped tank spotted in an earlier video speculated to potentially be a new booster header tank design (dome with smalle top ring)
Booster fwd section in production tent
S21 outside mid bay
Wide bay: stair section (produced next to high bay) lowered into it
New RCs for January 31 - February 2 (10am-10pm)
S22 disconnected from crane in mid bay at 20:03
NASA Aerospace Saety Advisory Panel: SpaceX provided the agency with "an integrated master schedule" on HLS Starship development this month. Also gave a "good understanding of some of the challenges" the company is having with Raptor engine production. NASA conducted some site visits to Boca Chica and Hawthorne. Landing technologies accuracy /stability / hazard avoicance identified as top risk to HLS Starship; mitigations include the fact that there will be uncrewed test landings [Sheetz]
McGregor: Raptor 2 engine test on horizontal test stand for about 0m25s; multiple very bright flashes at the end
McGregor: Raptor 2 engine test on vertical test stand for about 0m09s; green flash at the end; similar to test on January 14th
NSF
Mary
Nic
LabPadre
26,01.2022
Smooth nosecone attached to crane outside tents, next to cargo door prototype
Booster fwd dome lifted onto sleeving stand; dome cleaned [?]; 3-ring sleeve with 2-ring stringers moved out of tent
Wide bay work continued; preassembly of level 7&8 under way
S22 tank section in mid bay (now full height, 16 rings)
Booster [B8] fwd dome sleeve rolled out of tent 1 again after being rolled back in; attached to crane, lifted and flipped; attached to another crane, sleeved
OLM work continued
OLS tank farm: klemm drill rig used again
OLS, IT; Ship QD arm's claw tested
SN20/S20 work around and on quick disconnect
Chopsticks work continued, white part has been added to lower extensions
Standard TFR renewed for February
RC for January 27-28 canceled
McGregor: Raptor 2 engine test on horizontal test stand for about 2m05s
McGregor: Raptor 2 engine test on horizontal test stand for about 1m45s
NSF
Mary
Nic
LabPadre
25.01.2022
OLS IT, OLM and Chopsticks worked on; IT with scaffolding on rail columns, working on rails
B4 work continued
Earth work on SoLS, near pad
B3 remains cut into smaller sections
PPS: Work on destillery tower
B2.1 connected to crane for lifting; lifted from structural test stand (lower part of can crusher)
Wide bay: more beams added
Unusual tank structure (dome-like with a small top ring) spotted in tents
Booster common dome and its sleeve next to sleeving stand
S22 thrust section (5-ring with lead-ins) spotted in mid bay
RC for tomorrow canceled
McGregor: Raptor 2 engine test on horizontal test stand for about 2m25s; longest yet
NSF
Mary
Nic
LabPadre
24.01.2022
McGregor: Raptor 2 engine test on horizontal test stand for about 1m54s; dense fog, very loud
Ship and booster stabilization arms folded and extended from 11:36pm to midnight
LabPadre
no
23.01.2022
OLM work continued
OLS IT work continued
SN20/S20 rigging and LR11000X disconnected; moved next to OLM
B7 CH4 section being welded by a robotic welder in high bay
Raptor 2 sighted for first time; testing started [139]
RC for January 24-25 canceled
NSF
Mary
LabPadre
22.01.2022
Wide bay construction work continued, beams added
S22 thrust section moved from high bay into mid bay (moved in and out several times)
B7 aft tank section #4 moved near high bay [?]
B7 LCH4 section stacked on another 4-ring section at 1:30am, now 13 out of 13 rings tall
Crane rigging from LR11000X detached and reattached from/to SN20/S20
SN20/S20 disconnected (8:19am) and reconnected to LR11000X at 10:31am, lifted from pad B on to transport stand with QD at 11:42-57am
OLS IT work continued
Ship QD worked on
NSF
Nic
LabPadre
21.01.2022
McGregor: Raptor 2 engine test at ?:?? pm on horizontal test stand for about 1m58s
McGregor: Raptor 2 engine test at ?:?? pm on vertical test stand for about 1m10s
no
20.01.2022
LOX deliveries to OLS tank farm
SN20/S20 still hooked to LR11000X on Pad B; transport stand next to it
GSE4 remains still laying around
Berm removal continued
Ship nosecone barrel section in high bay
S21 tank section still outside mid bay
Oilfield workers and equipment from FESCO arrived at Boca Chica
B2.1 work on outside
Earth and concrete work behind high bay and wide bay looks like foundation for some new building/construction
New RCs for January 26-27 (10am-10pm) and 28 (6am-4pm)
NSF
Mary
LabPadre
19.01.2022
Ship QD transport stand positioned next to S20/SN20 at 9:37am
Production tent moving continued
High bay rooftop bar work continued
Single 3.6mm ring moved into high bay
Smooth nosecones in tent 3; first one with TPS pins [Randolph]
Ship common dome spotted
Booster fwd dome moved
High bay: ship nosecone barrel section attached to crane (3.6mm!)
Smooth nosecone moved out of tent 3, next to S22 nc barrel section (cargo door prototype)
Wide bay work continued on all current levels; assembly of level 7&8 has begun
GSE4 remains at launch site
OLM work continued
Chopsticks worked on
Concrete forms constructed at launch site
Perimeter fence being welded at launch site
Cryogenic deliveries to OLS tank farm
RCs for January 20 and 21 canceled
Elon Musk catching simulation video on Twitter
McGregor: Raptor 2 engine test at ?:?? pm on horizontal test stand for about 1m46s; throttling of engine
NSF
Mary
Nic
LabPadre
18.01.2022
Chopsticks worked on
Commodities delivered to OLS tank farm
GSE4 test tank cryo proof tested to failure (popping)
Wide bay construction work continued on lower levels; concrete work behind wide bay
S22 nosecone barrel section (5-ring) as payload door prototype closeup; work continued, more of the door has been cut
High bay rooftop bar work continued
B7 CH4 section stacked on a 3-ring section; now 9 of 13 rings tall
RC for tomorrow canceled
NSF
Mary
LabPadre
Randolph
17.01.2022
LR11000X moved towards SN20/S20
SN20/S20 lifting squid attached; work on QD area on Pad B (disconnected from GSE connections); connected to LR11000X
OLS, IT: Roof installation has begun
OLM: Painting work
B4 work on QD area; aerocover for QD panel installed
Concrete mixer moved by crane at OLS tank farm
Wide bay construction work continued; cross beams added for level 5&6
Concrete work behind wide bay
B7 fwd section #3 (3-ring) in high bay; stacked, now 6/13 rings tall
S21 tank section moved out of mid bay once again
Nosecone scrapping work continued
Tent moved at production site (again?)
NSF
Mary
Nic
LabPadre
16,01.2022
B7 Ch4 tank sections ready for stacking
OLS tank farm work, parts lifted
NSF
Mary
LabPadre
15.01.2022
Wide bay: 4th corner segment of level 5&6 has been lifted
LR11000X turned
OLS tank farm: Klemm KR702-2R Drill rig in action
B7 3-ring CH4 tank section (with lead-ins) and fwd dome section moved into high bay
OLM QD: several full speed hood tests (05:21am
NSF
Mary
Nic
LabPadre
14.01.2022
OLS tank farm: Large number of trucks delivered LOX/LN2; some venting
Ship QD work continued
Berm removal continue
B4 work on engine section (work on aerocovers): engines have received side covers; three aerocovers are now installed
B7 fwd dome section (sleeved) spotted outside highbay
Wide bay: work continued; level 7&8 preassembly has begun; LR11000 disconnected from segment; fourth section lifted at 3:15pm and installed
Load spreader moved away from production site
Crane connected to a 2-ring leg skirt
Crane with huge load spreader (delivered on January 09) relocating a tent at production site (the one next to tent 3)
McGregor: Raptor 2 engine test at ?:?? pm on vertical test stand for about 0m26s; green flash at shut off
NSF
Mary
Nic
LabPadre
13.01.2022
B2.1 work through access hole
SoLS Pad A: Booster adaptor removed Wide bay: third level 5&6 (3) segment attached to crane and lifted; more beams added
Unused nosecone attached to crane, scrapped, cut in half
Groundwork behind high and wide bays continued
B4 work continued; first aerocovers finally being added
B3 engine section removed from Pad A
Chopsticks: Beam and water bags remvoed
RC for tomorrow canceled
NSF
Mary
Nic
LabPadre
12.01.2022
Wide bay: Preassembly of remaining level 5&6 segments continued
LR11000 ("Buucky") lifted and lowereed again; raised again
Parts for a construction elevator delivered
B2.1 test stand cap removed
Mobile offices delivered to production site
Choptsticks: worked on; ballast bags filled with water (canflex crane test water bags for 100 tons); tested (moved upwards a bit; sideways as well)
Berm removal continued
LN2 and LOX deliveries to OLS tank farm
B3 scrapping continued
B4 covers worked on
B7 downcomer installed into LOX section beginning at around 19:55
RC for tomorrow canceled
New RCs for January 18-20 (10am-10pm)
McGregor: Raptor 2 engine test at 8:43 pm on vertical test stand for about 1m20s
NSF
Mary
Nic
LabPadre
11.01.2022
Wide bay: ramaining two level 5&6 segments preassembly continued; cross beams added on level 5&6
Hydraulic rams loaded onto truck
Booster fwd dome sleeve and dome infront of tents
B3 scrapping continued
B2.1 hatch opened by force
Ship aft flap with tiles waitung for installation
LR11000 lowered boom at production site
PPS: new structure (black stand?) spotted
Chopsticks: Cross bar with ballast bags (re-)attached; moved to the top (not filled, fastest yet); drone inspected; moved down
OLS, IT (OLIT): workers started adding roof tiles
Tank farm/launch pad berm continued to be removed
Ship QD: grab arms moved; full arm moved
B4 work continued around QD area
GSE4 test tank worked on
SN20/S20 work continued
RC for tomorrow canceled
NSF
Mary
Nic
LabPadre
10.01.2022
Wide bay: LR11000 still connected to corner segment; work other two segments of level 5&6
Crane work at production site
Ship stand with disconnect moved to launch site
OLS tank farm/landing pad berm continued to be removed
LN2 and LOX deliveries to OLS tank farm
B3 scrapping continued
Chopsticks tested: fastes move yet (stayed relatively low)
NSF
Mary
Nic
LabPadre
09.01.2022
Crane weights transported on SPMT
Mystery column still at production site
Leg skirt barrel segment spotted in tent
S22 5-ring nosecone barrel; possibly payload door prototype
S24 common dome (4-ring, with new types of lead-ins) spotted
Load spreader delivered
OLM work continued; raptor disconnect vent [?] tested twice
Chopsticks work continued; bar lifted onto it to connect both arms, installed; chopsticks tested; rose very slowly to the top; arm movement on the top; slowly lowered down again
Ship QD arm work continued; tested (extended and retracted)
B3 scrapping continued
SN20/S20 worked on
McGregor: Raptor 2 engine test at 2:00 pm on horizontal test stand for about 0m40s
NSF
Mary
Nic
LabPadre
08.01.2022
Ship QD and chopsticks being tested [see below]
OLS/landing pad earth work continued
Nilgai spotted
Wide bay work continued
B2.1 test tank: Ropes continued to being disconnected from structural test stand
B3 LOX section scrapping began on pad A; tank section cut off from aft section an lifted away; scrapping of tank section continued
OLM: Work on booster QD
Booster fwd dome outside tents
B7 rotated in tent
NSF
Mary
Nic
LabPadre
07.01.2022
OLM work continued with last shieldings continued to being added
Power bay: Stair added
OLS/landing pad berm continued to be removed
Ship transport stand and ballast transported to production site
Earth work behind high and wide bay continued (levelling)
Wide bay: New beams delivered; beams added between corner sections of level 5&6, preassembly of level 5&6, as well as of 7&8 continued
B7 aft LOX tank segment #5 (4-ring) moved into high bay
B2.1 test tank: ropes have been detached from lower attachment points; crews removing one of the ropes
OLS tank farm testing with activity from CH4 subcoolers and LN2 tanks; green blinking lights spotted [vid 08]
LR11000X moved towards B3 and attached to it [vid 08]
Chopsticks extensively tested, especially horizontal arm movement; observed by a SpaceX drone [vid 08]
Ship QD arm movement tested [vid 08]
B7 LOX tank section lifted in high bay; stacked onto another LOX tank section (now 20 out of 23 rings tall) [vid 08]
B3 attached to LR11000X at 8:53pm
McGregor: Raptor 2 engine test at 7:19 pm on horizontal test stand for about 0m34sec
NSF
Mary
Nic
LabPadre
06.01.2022
New RCs for January 12 (10am-8pm), 13-14 (6am-4pm)
B4 attached to LR11000X
OLS/landing pad berm earth continued to be removed
Wall construction between landing pad and hwy 4 continued
SoLS: Ground repair work began near pad B
OLM: Awning/shieldings added
Chopsticks work continued Wide bay: Second corner segment of level 5&6 lifted by LR11000 and installed
Work on ship QD: New panels added, some curved (soft?) plates added (bumpers)
LOX and LN2 deliveries to OLS tank farm
SN20/S20 work on fwd flaps
B4 work through acces hole
Construction elevator moved away from launch site
Wide bay: Work continued, second corner segment for level 5&6 lifted by LR11000 and installled
Foundation work next to stargate building
High bay rooftop bar work continued
S24 mid LOX section has tiles attached
New ship section spotted outside tents (4-ring, no lead-ins)
New RCs for January 12 (10am-10pm) and 13-14 (6am-4pm)
McGregor: Raptor 2 engine test at ?:?? pm on vertical test stand for about 1m00sec
NSF
Mary
Nic
LabPadre
05.01.2022
Fast booster QD retraction test at 12:55 am, another one, fastest yet, at 4:16 pm
Chopsticks work continued
Wide bay: First segment of level 5&6 lifted slowly, put down again, LR11000 moved forward into the bay, lifted and installed; work on finishing level 2 continued
Earth work south-west of wide bay
SN2 lifted from concrete stand at production site, lowered onto transport stand, moved to PPS
5-ring nosecone barrel section at scrap yard; scrapped flaps spotted
Rotating fabrication mount from tent 2 moved ("These spin a barrel section so a robotic welder can access the seam between two rings")
B4 work continued
OLM awning installation continued, one has a hole; some other work
GSE4 worked on
OLS tank farm venting next to horizontal CH4 tanks and CH4 subcoolers
NSF
Mary
Nic LabPadre
04.01.2022
Wide bay construction work continued with cross beams and wall plates being added; more beams delivered;
Chopsticks (Mechazilla) tested
Possible cargo door pathfinder shown
B4 work continued on several areas
Fence with semi-transparent plates being added between landing pad and hwy 4
LN2 delivery to OLS tank farm
OLS bearm towards landing pad being removed
OLM work continued, first three awnings installed to protect pipes equipment on the side of the OLT
Chopsticks work; testesd very slowly: risen up several meters, right arm opened up, left arm tested, moved down, rose again, arms tested in several angles, moved down to original position [per part vid 05]
PLS, IT scaffolding continued to be removed
McGregor: Raptor 2 engine test at 8:53 pm on horizontal test stand for about 1m32sec
NSF
Mary
Nic
LabPadre
03.01.2022
LOX and LN2 deliveres to launch site
SN20/S20 Tiles being removed again at the nosecone lift points after the static fire
OLS, IT: Scaffold continued to being removed
OLS berm: earth work continued; some earth being removed
Booster QD on OLM: Insulation being wrapped around main QD pipes
"Dog house" covers have been painted grey
Wide bay: LR11000 connected to first level 5&6 corner segment; work on lower levels continued
S24 common dome sleeve waiting to be sleeved; load spreader attached to S24 common dome, lifted onto sleeving stand; no header tank installed, Elon Musk confirmed that CH4 header tank would be moved to nosecone [!]; load spreader connected to common dome sleeve, sleeved on dome
Stair construction near high bay continued
Deliveries (bround half rings, McDonough machine)
Chopsticks work continued
LR11000X moved to landing pad and attached to B4 via loadspreader
Elon Musk: "Raptor 2 now operates routinely at 300 bar main chamber pressure"
SN20/S20 Liftting points reinstalled
NSF
Mary
LabPadre
02.01.2022
Ship QD arm still waiting for its completion
B4 on landing pad
Minor work began again
Wind damage at Tent 1 (roll-up door)
Chopsticks short move upwards
NSF
Mary
LabPadre
01.01.2022
Date
Description
Source
Link
31.12.2021
Scaffolding continued being removed from OLS, IT
Standard TFR up to 10000 feet renewed for January 2022
30.12.2021
OLM work continued
B4 prepared for lifting; QD disconnected (retracted and hatch closed); lifted by LR11000X and lowered onto a transport stand (engines spotted: RB28, RB29, RB30, RB 31, RB32, RB13, RB16, RB12, ... RB33, RB14, RB4, RB20, RB5, RB7, RB??, RB28); secured on stand
Wide bay construction work continued
Nosecone at production site with orange line markings
S24 common dome spotted
Unknown covers/"dog house" structures painted grey at production site
Load spreader and LR11000X disconnected from B4; B4 moved towards landing pad
OLS, IT: Scaffolding being removed
New RCs for January 4-6 (10am-6pm)
NSF
Mary
LabPadre
29.12.2021
SN20/S20 venting early morning
B4 hooked to LR11000X
OLM work
SN20/S20 flaps tested
SN20/S20 Static fire #4 and scrubbed attempt
RC for today extendet until 8pm
S21 tank section moved into mid bay (again)
NSF
Mary
LabPadre
28.12.2021
SN20/S20 Scrubbed static fire attempt
S21 nosecone still being worked on, S22 nc barrel section (5-rings) infront of it
Wide bay construction continued
LN2 deliveries to SoLS tank farm
Tent 3 nosecone work continued
Fabrication stand moved
S21 tank section still waiting outside mid bay
Stair assembly next to high bay continued
B7 fwd tank #3 section (3-ring) spotted; cmn dome barrel without dome
Two unknown "dog houses" or covers still at production site
OLM work continued
B4/OLM igniter test #5?
Alert notice issued for SN20/S20 static fire attempt
FAA: PEA issuing delayed until February 28
NSF
Mary
LabPadre
27.12.2021
B7 aft #4 ring barrel (4-ring with lead-ins) lifted into high bay and stacked with LOX section; now 16 out of 23 rings tall
Wide bay: Parts and beams delivered; construction work continued (preassembly of level 5&6 uner way)
Coil of stainless steel delivered
Ship mid-LOX tank section spotted in tent
LR11000X moved towards B4/OLM
OLM work continued
LN2 delivered to OLS tank farm
Alert notice and NOTMAR issued for SN20/S20 static fire attempt
B4/OLM two ignitor tests [vid 28]
NSF
Mary
LabPadre
26.12.2021
25.12.2021
24.12.2021
23.12.2021
Work on nosecones in tent 3 continued (one with old design, one with new design)
S21 tank section still waiting outside high bay, possibly being scrapped
Wide bay: Level 5&6 preassembly continued
B7 in high bay 12 rings tall [B7 according to NSF]
OLM work continued
SN20/S20 TPS tiles placed over the crane attach points "this could be for a full up test of the heat shield during a static fire" [NSF]
LN2 delivery to OLS tank farm
Stair assembly continued next to high bay (not clear if for high bay)
S22 nosecone barrel section (5-ring) [cf. Dec 19] in windbreak "It looks like this could be repurposed for another cargo door pathfinder"
B4/OLM igniter tests at 19:49 and 22:27
NSF
Mary
LabPadre
22.12.2021
B4 cryo proof test #3
[B7/B8?] fwd section lifted off sleeving stand, moved into tent 1
Coil of stainless steel delivered
Highbay stair assembly continued
Wide bay: level 5&6 first corner section preassembly on its way
Deliveries to production site: beams and flexible pipes
[B7/B8?] section lifted into high bay for stacking (4-ring with lead-ins)
[B7/B8?] 8-ring tank section (LOX and cmn dome) lifted by bridge crane; stacked onto the 4-ring section [add: B7]
S21 tank section moved out of mid bay once again; crane attached, lifted off transport stand near high bay
Stand moved to production site by SPMT
Nosecone [pathfinder] with new design now being scrapped
S21 nosecone moved out of high bay, tank section unhooked from crane after being placed on a shorter stand
NSF
Mary
Nic
LabPadre
21.12.2021
Piling work has already begun at Pad 39, pad and earth work [WAI]
Roberts Road (Florida based facility used in 2020, together with cidco rd): more area cleared, work on building extension work continued; LC49 proposed according to NASA [WAI]
B4 cryo proof test #2
Chopsticks work
B7/B8 stacking in high bay began [add: B7]
Work outside high bay: Staircase construction
Wide bay work continued
B2.1 test tank in structural test stand: closeup
Ship fwd section moved (3-ring, sleeved)
B7/B8 aft dome section sleeved (4-ring segement, 2 rings stiffeners; smaller rings [???]; 33 engines) and lifted from sleeving stand; 3-ring booster fwd dome sleeve with 2-rings stiffeners infront of it
Booster fwd dome attached to crane, lifted onto sleeving stand [likely B7/B8], sleeved with the 3-ring booster fwd dome sleeve
The new booster thrust puck stored outside tents
RC extended until 8pm
NSF
Mary
Nic
LabPadre
20.12.2021
B4 scrubbed testing
B2.1 all ropes connected to hydraulic pistons at the structural test stand
Booster common dome moved into mid bay (4-ring with lead-ins and stiffeners)
High bay: construction work outside, beams erected, possibly for an elevator [?]
S21 nosecone in
Ship nosecone barrel section (5-rings!!) [S22/S23/S24?]
Wide bay construction continued; level 2 wall covers continued to be added; work on completing beam structure on level 3&4
LN2 storage tank lifted and positioned at PPS
33 Raptor thrust/aft dome lifted onto sleeving stand [B7/B8] [add: B7]
LN2 delivery to OLS tank farm
OLS tank farm work continued: red and orange parts lifted into place
OLM work continued
Chopsticks work continued
Work and painting on a fence at landing pad
Booster dommon dome section spotted in high bay [add B7]
NSF
Mary
Nic
LabPadre
Below
19.12.2021
S21 tank section moved into high bay; moved back into mid bay later that day [???]
NSF
Mary
Nic
LabPadre
18.12.2021
Black pillars still at production site
Wide bay: Fourth level 3&4 corner segment attached an lifted by LR11000 and installed
Booster fwd section in front tents
Ship section spotted in high bay (nc barrel sectoin from yesterday?)
B2.1 work continued
Delivery if metal parts to launch site [SL-04, LN-2]
SN20/S20 work at engine section
Drilling rig working at the OLS tank farm
Chopsticks work continued
Purging of CH4 buffer tank
Raptor 2.0 engine test in McGregor on a horizontal test stand [Adam Cuker, confirmed by Elon Musk]
S21 moved into high bay at around 7pm
B2.1 stress tested; Remedios road closed
NSF
Mary
Nic
LabPadre
17.12.2021
Rocket garden at PPS: B5, BN2.1, B2.1, SN15, B6, SN16
B2.1 work continued
Sheriff at Remedios ave
B4 cryo proof test on OLM
PBI crane lowered and rose again near wide bay
Wide bay work continued; beams added between the newly added segments, finishing work on fourth corner segment of level 3&4 on ground
Nosecone barrel section in high bay
Booster methane sump delivered
S21 rolled out of mid bay; tiles not completely added, some broken or missing; aft flap mounting rig not yet installed; work platfrm on top has been removed some time ago
S22 inside mid bay at least 10 rings tall
SN15 aft flap inner skin has been removed
SN20/S20 work in engine section
Todays RC extdended until 5pm
Elon Musk tweets; video of B4 gimbal test (center engines)
McGregor: Raptor 2 engine test at 5:33 pm on horizontal test stand for about 2m24sec
NSF
Mary
Nic
LabPadre
16.12.2021
Wide bay: second corner segment of level 3&4 lifted by LR11000 and installed and later disconnected; beams added between the two corner segments; third corner segment attached to LR11000 and lifted later
Nosecone cage (max Q test rig) moved by two SPMTs
SN15 work on one aft flap
B2.1 work continued; ropes lowered ("These are likely to be used to pull down the cap while the tank is filled and pressurized")
B6 work continued
Tall black stand? (column/pole) spotted at the production site
LR11000X lifted load spreader
SN20/S20 work on engine section, parts added [heat shields for Raptors?]
B4 remained connected to QD; work on a cover attached to aft section
QD arm work continued
Booster thrust puck accidentally delivered to launch site (third one for 13 inner engines), possibly for B9?; developed since first one spotted in early October (recesses bigger, [171]structural weaving increased - less weight) [WAI]
MaxQ testing cage moved to PPS/Sanchez site
Todays RC canceled
New RCs for Dec 23, 27-30 (10am-6pm)
NSF
Mary
Nic
LabPadre
15.12.2021
McGregor: Raptor engine test at 8:43 pm
Starhopper (SH) marine radar removed, new antenna mounted
Chopsticks work continued, cables attached near the hydraulic piston; later the green cables and piston has been removed; wires fed into the chopsticks
OLS tank farm: vertical LN2 tank venting, venting from a GSE equipment between GSE2 and GSE7
SN20/S20 work at the ex attach points
B4 still attached to LR11000X; OLM and B4 work continued; later detached from crane
Concrete work between launch site and hwy 4 continued; I beams added, likely for a new wall
Wide bay: level 3&4 section moved by LR11000
Single ring moved to scrapyard
B6 test tank moved to PPS, moved next to SN15, SN16, B5
Lines installed on the structural test stand (for B2.1)
NASA is preparing to conduct environmental assessments to develop a proposed new launch site, LC49, at Kennedy Space Center [NASA]
NSF
Mary
Nic
LabPadre
14.12.2021
LR11000 disconnected from wide bay segment that has been installed yesterday; hooked to another corner segemtn of level 3&4 that has been finished; screws tightened; new beams delivered
S21 nosecone work continued infront of high bay, some tape has been removed
Structural test stand cap lifted onto B2.1 test tank (the one with the tank like top, has some heavy orange ropes on it, "can crusher cap")
Grinders used on one of SN15s aft flap
S24 common dome spotted (4-ring! instead of 3-ring!!)
OLM work continued, booster QD hood closed; later opened and likely connected to B4, work around QD
B4 work on OLM continued; ship QD arm likely to hold on booster
SN20/S20 some tiles are brown; cable attached on lower section onto TPS tiles; attach points being removed!; work at engine section
OLS tank farm LN2 tank venting (GSE1), some venting from detanked CH4 buffer tanks; LN2 deliveries
NSF
Mary
Nic
LabPadre
13.12.2021
OLM: welding work
B4 work on aft section (QD plate) ahead of lifting
B4 lifted onto OLM by LR11000X and installed carefully (engines spotted: RB28, RB29, RB30, RB31, RB32, RB13, RB16, RB12, RB18, RB15, RB17, RB3, RB6 RB33, RB14, RB4, RB20, RB5, RB7); all holddown clamps extended one by one manually; RB engine disconnect spotted
Booster stand moved away
Concrete forms prepared at launch site north of landing pad
SN20/S20 two red/orange boxes installed
Work on a funny looking structure at production site
S21 nosecone section moved towards high bay, tiles work continued
Wide bay: finished corner segment of level 3&4 lifted by LR11000 and installed
NSF
Mary
Nic
LabPadre
Marcus House
12.12.2021
Ship fwd dome lifted on sleeving stand
Booster aft dome sleeve in front tents
B6 test tank worked on in high bay
B2.1 work continued: strenghtening? ring added around the lower part of the test tank
OLM: Scaffolding staircase removed as the fix staircase has been finished (the top part is a spiral staircase); much work
Hydraulic piston still hanging loose from Chopstick extension
Compressed nitrogen trailer at landing pad
OLS a lot of venting south of tank farm berm
LR11000X moved towards OLM
B4 moved towards OLM, likely to be lifted soon
OLS tank farm: testing [?], some venting from around the LOX subcoolers
B4 connected to LR11000X late in the night
NSF
Mary
LabPadre
11.12.2021
Pad work infront of OLS tank farm continued: concrete poured
B4 unhooked from load spreader (without having moved), LR11000X moved
OLM: Booster QD work continued
OLS, IT: Ship QD work continued
SN20/S20 Work on a cover above QD; nosecone hatch closed
S21 nosecone work continued, horizontal beam added between nc and nc barrel section
Work on the two LN2 storage tanks at PPS
SoLS pad Ship QD at PPS
Wide bay level 3&4 work continued
B2.1 work continued at PPS
Nosecone with TPS attachment point in tents 3
Ship aft aerocover moved
Hwy4 roadwork between launch and production site continued (since several weeks major work)
NSF
Mary
Nic
LabPadre
10.12.2021
OLS, IT: More pipes lifted into place
OLS tank farm: Earth and concrete work continued
B4 still hooked to LR11000X, not moved yet
Transport stand parts delivered moved from launch site
SPMT with heavy counterweights moved to launch site
Barrel section infront of tent 3 (the one hooked to crane) is S22 thrust section
B6 test tank moved into high bay
B2.1 work continued
Wide bay construction work continued
New RCs for December 15-16 (10am-6pm) and 17 (8am-2pm)
OLM: New lights have been installed; QD tested (hood retracted, QD moved foreward)
NSF
Mary
LabPadre
09.12.2021
OLS tank farm: venting from horizontal CH4 buffer tank and vertical LN2 tank; work on the LN2 tank; work on concrete pad; multistage pump prepared and lifted into place near LOX subcoolers (into the ground?); LN2 delivery
Chopsticks work continued, new part (hydraulics?) added at the downward facing stabilisation extension
SN20/S20 work on engine section and through access hole
OLM work continued
S21 nosecone TPS tiles work continued
Barrel section with lead-ins (the same from yesterday) still hooked to crane outside tent 3
SN23 (S23) nosecone hooked to crane outside tents [not the same as the scrap nosecone from previous days?]
Booster aerocover spotted at production site
Wide bay construction work continued
B6 test tank work continued
RC for december 13 canceled
Ship QD (likely for suborbital pad) spotted near the starbase sign (RGV)
FCC application for radio communications with Ship and Booster for the orbital flight test granted for the requested window from 20 December 2021 until 1 March 2021; Purpose: "Experimental orbital demo and recovery test of the Starship test vehicle..."
NSF
Mary
Nic
LabPadre
08.12.2021
Ship aft section out of tents (hooked to crane), as well as scrap dome
B6 test tank work near wide bay construction site
Wide bay work continued; panels being installed on level 3&4 (preassembly)
S21 nosecone TPS tiles work continued
B5 unhooked from bridge crane; B5 moved out of high bay to the booster display stand recently constructed (located at PPS next to SN15 and SN16; engine production is confirmed to be slower than booster productin, so either B5 is being retired or on a waiting position)
B2.1 work at PPS
Scrap nosecone (the one with fewer panels) again spotted outside tent 3
OLM work continued
B4 connected to load spreader [not two days ago?], work on COPVs
SN20/S20 flaps still remained open
LN2 delivered to SoLS
RC for December 10 canceled
NSF
Mary
Nic
LabPadre
07.12.2021
Booster QD hood lifted onto OLM and installation began
OLM work continued
OLS, IT work continued
Earth work infront of OLS tank farm
B4 work continued
Delivery of some part wrapped in blue cover
SN20/S20 work through access hole
LN2 delivered to SoLS tank farm
Wide bay work continued
Dome delivered to production site
B2.1 is back at PPS
S21 tank section work in mid bay through access hole
S21 nosecone TPS tiles work continued
B6 common dome section with lead-ins hooked to crane; booster fwd dome section spotted near it, also attached to crane; both later detached from crane; fwd dome attachedto another crane, stacked onto B6 common dome; B6 apparently now a test tank with B6 common dome and a booster forward dome
RC for December 8 and 9 canceled
New intermittent RC for December 8 (9.30am-11.30am)
NSF
Mary
Nic
LabPadre
06.12.2021
Wide bay construction work continued: panels added on level 1, level 3&4 cross wall segments nearly fully added
Liquid nitrogen tank delivered to the PPS
S22 fwd dome section lifted into mid bay
Wide bay beams and parts delivered
Electrical equipment delivered (ABB)
B2.1 prepared for rolling back, then rolled back to production site
OLS tank farm GSE1 venting again
OLM construction work continued, especially on QD
LR11000X moved
OLS, IT work continued
SN20/S20 work on engine section
Booster QD hood has been delivered to launch site last night
B4 connected to LR11000X
RC for December 7 canceled; as well as todays
New RCs for December 10 (8am-2pm) and 13, 14 (10am-6pm)
NSF
Mary
Nic
LabPadre
05.12.2021
OLM work continued, especially on booster QD and lower exterior pipes
Chopsticks work continued
OLS tank farm work on pipe insulation
B2.1 prepared to move, SPMT moved towards test tank
Outriggers removed from LR11000X, moved to the production site
Ship leg skirt and fwd dome seen infront tents
Booster fwd dome section infront of tents, as well as barrel sections
NSF
Mary
LabPadre
04.12.2021
B5 hooked to bridge crane again; has all the aft section hardware installed already, but no covers yet installed
Nosecone with old design spotted in tent 3 with flap attachment rig installed
Booster barrel section moved into tent
S22 fwd dome section moved into tent
Earthwork at the PPS
Wide bay level 3&4 preassembly work as well as level 1&2 panels continued to be added
SN20/S20 work on extended flaps; fuelling adapter closeup; engine section worked on
B4 work on aft section continued
Concrete work at west side of the OLS tank farm
OLM work continued (NSF calls it OLP) as well as work on chopsticks
Booster load spreader moved to launch site, unloaded by LR11000X (LabPadre name: Marvin) (first job since crane was built)
NSF
Mary
Nic
LabPadre
03.12.2021
SN20/S20 fwd and aft flaps have been opened (Starship Gazer)
Work on a steel cable roll near SN16; thrust rams for Rvac engine thrust simulation spotted at PPS
Platform raised at PPS, Grove crane moved Panels being added to wide bay (RGV); level 3&4 work continued (preassembly); more beams delivered
Nosecone test stand (cage/rig) moved to scrapyard on two SPMTs
Delivery of a red/black structure to production site "343 ton cap"
S21 Nosecone TPS tiles work contineud
S22 fwd dome section shown outside tents
B2.1 Cryo Proof Test
GSE1/Shell5 venting; as well as GSE on OLS tank farm
LN2 delivery to OLS tank farm
OLS, IT: Ship QD work continued; also from the new offloading area at the old landing pad
Insulated pipe moved around near GSE5 at launch site
LC-39A at Cape Canaveral Kennedy Space Center: Work has begun with the Starship mount being dismantled (spotted on satellite pic by Harry Stranger); Elon Musk confirmed that "Construction of Starship orbital launch pad at the Cape has begun"[185] and that it "Will have similar, but improved, ground systems & tower to Starbase"[186].
B5 rolled out of highbay for a few minutes before rolling back in again
B4: Aerocovers for both hydraulic power units were installed
NSF
LabPadre
02.12.2021
SN20/S20 fwd and aft flaps tested and opened at 12:40
RC for today extended until 10pm
Unfinished domes spotted outside the tents
S22 fwd dome section spotted infront of tents
Wide bay construction work continued
S21 nosecone TPS tiles work continued
Work on a new structure infront of tents (looks like a hood; for Ship QD?)
Wide bay beams delivered to PPS/Production site
B2.1 cryo proof test
B5 unhooked from gantry crane in high bay
B4 raceway cover continued to be added (Kevin Randolph)
NSF
Mary
LabPadre
01.12.2021
OLS: South berm work continued; work on chopsticks
LOX delivered to the OLS tank farm
B4 COPV covers being installed
GSE4 test tank moved south
Wide bay work continued (level 1&2 vertical beams, level 3&4 preassembly)
S21 nosecone TPS tiles, red tape added
High bay rooftop bar work continued
Scrap smooth nosecone shown
Booster cmn dome section/sleeve shown in a tent
SN20/S20 aborted static fire attempt
SN20/S20 header tank test
B2.1 cryo proof test, possibly also puck shucking; the first time OLS tank farm was used for testing
New RCs for December 7-9 (10am-6pm)
NSF
Mary
Nic
LabPadre
Date
Description
Source
Link
30.11.2021
S21 LOX header tank downcomer lifted into mid bay for installation in S21 (the_denks)
RC for today canceled
OLM: Insulation added to pipes, meaning that they have been certified and ready to use
Prototype nosecone made with fewer panels now for scrap Wide bay beams assembly for level 3&4 continued; level 1&2 installation of small vertical beams continued; progress after some sort of a pause
Dome moved to scrapyard
SN20/S20 work on TPS tiles; all tiles have been replaced or repaired except those near the header tank vent; work on the engine section
S21 nosecone TPS tiles work continued
Chopsticks work continued
OLS tank farm work con GSE piping continued
B4 work near COPVs, raceway covers continued to be installed
SN20/S20 aft section work continued
GSE4 test tank moved southwards on landing pad (Starship Gazer)
Booster display stand under construction next to SN15 and SN16 at PPS (to the south west, RGV)
S23 nosecone (next generation) spotted by Starship Gazer
Alert notice for SN20/S20 static fire attempt isssued to residents; as well as NOTMAR posted
NSF
Mary
Nic
LabPadre
29.11.2021
RC for today canceled
New RCs for December 2, 6 (10am-6pm) and December 3 (6am-12pm)
OLM and chopsticks work continued OLS, IT; NE upper column now also with scaffolding installed
SPMT moved to SoLS; parts moved to landing pad near GSE4; then went to production site
Earth work at landing pad
LN2 delivery to SoLS
Wide bay construction continued; small vertical beam installation began
S21 tank section work in mid bay continued
S21 nosecone TPS tiles: new tapes added
Booster common dome section (sleeve?) spotted in a tent
S22 fwd dome section (sleeve?) spotted
NSF
Mary
Nic
LabPadre
28.11.2021
Launch site: pipes delivered, likely to OLS tank farm
B4 work near the COPVs
LN2 delivery to OLS tank farm; cone-like shaped item delivered
S21 nosecone TPS tiles work continued
Booster QD hood work continued at production site
Scrap fwd dome spotted
SN20/S20 work near aft flaps
OLS, IT: NW upper column scaffolding installed
Chopsticks work continued
Ship fwd dome spotted infront of tents
B6 common dome section hooked to flipping jig and flipped; methane transfer pipe appears to be plugged [?]
NSF
Mary
LabPadre
27.11.2021
SN20/S20 work continued through access hatch and on engine section
OLS tank farm work on pipe insulation
OLM work continued
B4 work continued
OLS, IT: upper SE column part fully covered with scaffolding
S21 aft flap alignment jig fully installed on one side (other side not visible)
Booster quick disconnect (QD) hood at launch site painted black
S21 nosecone TPS tiles work continued, especially around flap; label spotted: "Attention do not move flap"
Flip rig attached to a crane infornt of production tents
Booster common dome section flipped [likely B7?]
Standard TFR renewed for December (still 10000ft)
NSF
Mary
Nic
LabPadre
26.11.2021
Fwd dome spotted outside tents
OLM venting spotted again; announced on loudspeakers
Barrel section moved
LN2 delivered to OLS tank farm
OLS tank farm work continued on GSE pipes
Helium delivered
NSF
Mary
LabPadre
25.11.2021
Thanksgiving in US - not much work
24.11.2021
S24 common dome sleeve? spotted
OLM work continued
Concrete work between OLS tank farm and hwy 4
OLS tank farm: GSE plumbing being insulated, berm work continued
B4 work on engines, raceway cover and aft section continued
S21 nosecone TPS tiles work continued; some tape removed
S21 tank section in mid bay worked on
Raptor gimbal joints spotted
S22 stacking has begun in mid bay; cmn dome section identified; next to S21
Ship flap delivered; aft flap aerocovers spotted at the production site
NSF
Mary
Nic
LabPadre
23.11.2021
Ship fwd dome still outside tent; new jig next to it [S23?]
S21 nosecone TPS tiles work continued; many tapes around the flap
Wide bay work continued; Bigge crane has been lowered, now lifted again; several beam parts being assembled on ground; many more beams delivered
Ship [S22?] fwd dome section with many TPS tiles worked on
S21 tank section work in mid bay continued
Ship QD mechanism (star-shaped adapter and pipes) installed onto the QD arm
Chopsticks work continued
B4 work on some areocovers
Concrete torn up at OLS; earth work; rebar tied for new pad
OLS tank farm: inspection?
NSF
Mary
Nic
LabPadre
22.11.2021
OLM work continued; Booster QD extended; welding on circumfering pipe
Chopsticks worked on
Landing pad: parts relocated
LN2 deliveries to OLS tank farm and SoLS tank farm
SN20/S20 work on cables leading to raceway continued as well as on engine section
Wide bay work continued (third level installation hasn't begun yet); beams on ground being worked on
Rebar laid near high bay [?]
Work on booster QD hood at production site
S21 tank section worked on in mid bay
NSF
Mary
Nic
LabPadre
21.11.2021
OLM work continued; gas vented (likely Nitrogen used to purge GSE plumbing)
Earth work near landing pad
SN20/S20 work on engine section continue
S21 nosecone work on TPS tiles continue, more tapes added
Booster common dome sleeved [B6?]; second booster common dome sleeve moved near it
B5 work continued
Booster quick disconnect (QD) hood for OLM spotted, which will shield the booster QD from the exhaust plume
Ship quick disconnect (QD) spotted
NSF
Mary
LabPadre
20.11.2021
LN2 delivered to OLS tank farm
OLS tank farm: Work on connection the new horizontal CH4 tanks to tank farm continued
SN20/S20 and B4 (inspection) work
OLM work continued
Wide bay work continued; some beams being preassembled before lifting
Nosecone moved inside tent 3; nosecone barrel section with therman blankets spotted
S21 nosecone work continued, more tapes added
Booster common dome now on sleeving stand
B5 welding of the two sections
New Starship segment [S22?] spotted next to S21
NSF
Mary
Nic
LabPadre
19.11.2021
Ship fwd dome and booster cmn dome in front of tents
S21 nosecone TPS tiles inspected
Aerocovers staged for installation on S21; some tiles on it
B5 LOX tank lifted onto a transport stand
SN20/S20 work around cabling on aft section
LOX delivered to SoLS tank farm
OLS, IT: winch jutty received side walls for protection
OLM and IT work continued (also on chopsticks)
Road work at the entrance to the OLS tank farm
OLS tank farm: New black boxes installed near the orange and red pistons
Deliveries to production site
S21 nosecone green tape affixed; aft section prepared for aft fin installation
B5 methane tank section load spreader attached lifted by bridge crane and stacked onto LOX section (final stacking)
Wide bay construction work continued
SN20/S20 fwd and aft flaps tested
New RCs for 29 November - 1 December (10am-6pm)
NSF
Mary
LabPadre
18.11.2021
OLM work continued; work on a new circumfering pipe
LOX delivery to OLS tank farm
Wide bay beams accidentally delivered to launch site
QD arm work continued
SN20/S20 aft section work continued
B4 preparation work around aft section continued
LN2 delivered to SoLS tank farm
Concrete torn up between OLS tank farm tanks and Hwy4
B5 methane section moved in high bay
More wide bay beams delivered to production site
Scrap stainless steel sheets shown
S21 tank section worked on in mid bay
S22 cmn dome lifted into mid bay
NSF
Mary
Nic
LabPadre
17.11.2021
Elon Musk Presentation
S21 nosecone construction and TPS tiles work continued
S22 cmn dome work continued; extra vent with strange nozzle added (Potentially for a new thruster configuration?)
Wide bay construction work continued; more beams delivered
S21 work in mid bay continued
Fwd dome caps spotted
Deliveries to production site (some sort of pistons, new I-beams for wide bay)
OLM work continued
B4 inspection work
SN20/S20 work at engine area
Earth work at the launch site continued
OLS, IT: Some scaffolding removed
Elon Musk announced significant update for engine, basically a new engine: "A complete design overhaul is necessary for the engine that can actually make life multiplanetary. It won't be called Raptor."
RCs for November 18-19 canceled
Elon Musk presentation [see article]
NSF
Mary
Nic
LabPadre
16.11.2021
RC for November 17 canceled
OLM work continued
Chopsticks work continued
LOX deliveries to OLS tank farm continued
Section of flexible pipe spotted at OLS tank farm
Landing pad has received piping from OLS tank farm, possibly for more fuelling truck adapters
Landing pad/hwy4 berm removal continued
LN2 delivered to SoLS tank farm
Wide bay construction continued
Work on high bay construction elevator
S22 cmn dome section shown (3-ring, TPS tiles, lead-ins)
S21 nosecone TPS tiles worked on
Booster methane manifold spotted
Parts inventory at the production site shown
Unknown tubular part still at the production site, first spotted on September 19
Dome knuckle panels spotted
NSF
Mary
Nic
LabPadre
15.11.2021
FAA estimate: Environmental Review and permitting process would be completed by December 31; Transcripts from public hearings posted
COPVs loaded onto a flatbed
Wide bay construction work continued
Small pipes and rebar delivered to production site; as well as several trucks with beams [possibly for wide bay]
B5 scaffolding installed at the top of LOX section in prepartion of stacking; transport stand moved into high bay
SPMTs moved crane mats away from launch site
Chopsticks worked on
OLM work continued in several areas (plumbing, wiring, QD, stairs)
Berm between landing pad and hwy 4 began to be removed
SN20/S20 aft flaps tested
NSF
Mary
Nic
LabPadre
14.11.2021
OLS, IT: Work continued (rails, piping on QD arm)
Wide bay: work on LR11000 boom top
S21: new black plate spotted on the hull, just left above the QD area
Nosecones with the new design (single segments) spotted in tent 3
B7 "fwd dome stiffened barrel" 3-ring sleeve spotted
COPV aerocover moved
Booster aerocover (for COPV's) frame spotted
OLM: Work on new permanent staircase began (behind one pillar)
NSF
Mary
LabPadre
13.11.2021
B6 aft section (sleeved?) shown, work on it
Booster aft tank #5 spotted [Label looks like B7]
S21 nosecone work continued
-Y FWD aero cover delivered (-Y is the ship's starboard side)
Stair sections being stacked in high bay
Grove GRT8100 moved
Ship fwd dome sleeve with thermal blankets spotted in tent
SN20/S20 work in engine area
OLS tank farm: Daily LOX deliveries continued
Chopsticks work continued
NSF
Mary
Nic
LabPadre
12.11.2021
SN20/S20 Perburner test and Static Fire #3 (first one with all six engines, more tiles lost)
B2.1 on structural test stand ("cancrusher", closeup of thrust test setup) and GSE4 moved from PPS to launch site
NSF introduced new channelcam
S21 nosecone TPS tiles worked on
RCs for November 15-16 canceled
New RCs for November 17-18, 22-23 (10am-6pm) and November 19 (6am-12pm)
NSF
Mary
Nic
LabPadre
11.11.2021
S21 nosecone work continued
S23 aft dome sleeve (3-ring) spotted
B6 fwd dome sleeve hooked to crane, lifted and sleeved with fwd dome
S21 in mid bay: preparation work for aft fin installation
LR11000-P1300: according to NSF, both the boom and the jib have been extended by 6 meters
BN2.1, GSE4, B2.1 and SN15 shown at PPS; workers prepared concrete forms at PPS near them
OLS tank farm: Berm extension work continued
QD arm work continued
Cable supply reel for chopsticks not yet unspooled fully
Wide bay work continued; LR11000 is inside it
Alert notice delivered to residence for possible SN20/S20 static fire on 12 November
"Elon Musk will give a 30mins Starship presentation to the 1st Space Studies Board / Board on Physics and Astronomy" on 17 November 2021, 6pm EST
NSF
Mary
Nic
LabPadre
10.11.2021
OLS work continued at several areas (as always)
OLS tank farm: new equipment delivered
B4 COPV Covers installation finally began
Berry crane, Grove GMK 6350L, left launch site, drove to production site
SoLS tank farm venting
LOX deliveries to OLS tank farm continued
OLM work on booster QD
OLS, IT: work on QD arm
Ship aft dome sleeve (3-rings, lead-ins, TPS tile attachment points) moved at production site
Wide bay work continued
B2.1 work continued
B5 work in high bay continued
S21 nosecone TPS tiles worked on
RC for November 11 canceled
RC for today canceled
New RCs for November 16-18 (10am-6pm)
New RC for November 12 (6am-2pm)
NSF
Mary
Nic
LabPadre
09.11.2021
B5 thrust section lifted in high bay
S21 nosecone disconnected from crane; work continued
Two forward domes and a booster fwd sleeve (B6, yesterday) at the production site: as well as a Ship common dome and a aft sleeve and two pipes for methane transfer tube
LR11000 (Buckner) assembly at production site near wide bay
Grove GJMK7550 crane moved
Grey crane part delivered to production site as an addition to the old LR11000 crane (extension of the jib)
Grove, Manitowoc RT 9130E-2 crane drove to PPS
Wide bay construction work continued
LR11000 lifted its boom at the production site
Main cable reeving for chopsticks continued; reached draw works but spool has not yet been unwound completely
B4 work at the fwd section
SN20/S20 work at aft section
Apollo robot dog from Boston Dynamics spotted; new arm and SpaceX themed paint
OLS berm werk continued
OLS, IT plumbing lifted
B5 LOX section stacked on thrust/aft section
NOTMAR posted for November 10, Alert notice issued for potential SN20/S20 static fire
NSF
Mary
Nic
LabPadre
08.11.2021
Main steel cable installation began (unloading from the spool, pulled through the system by the pulling cable)
LR11000 with disassembled boom and counterweights moved to production site
LR11000-X moved; lifted other crane parts on truck (likely for the other LR11000)
OLS Tank farm: hose removed from a shell
Container wall construction at the production site
B5 work in high bay continued
B6 fwd sleeve shown (3-rings, vertical stiffeners, holes for grid fins)
Wide bay construction work continued; first two levels nearing completion
S21 nosecone welding work; nosecone still attached to crane
New robot arm delivered
Crew dragon Endeavour reentry visible over Starbase
RC for November 9 canceled
NSF
Mary
Nic
LabPadre
07.11.2021
LR11000 disassembly continued; parts moved to production site
S21 in mid bay now 16 rings tall; stacking of tank section complete
Fwd dome sleeve with TPS mounts spotted inside tent 3 (4-rings with lead-ins)
S21 nosecone stacked on nosecone barrel section; TPS tile rows on nosecone are labelled
OLM work continued
Chopsticks: Cable reeving began. Small help cable pulls up the pilote rope that will then pull the main cable through the system.
NSF
Mary
Nic
LabPadre
06.11.2021
Two Raptor engines with Spongebob drawings delivered to launch site RC78, RC79?
Wide bay construction work continued
S21 nosecone prepared for lifting, attached to crane
LR11000-X moved
SN20/S20 aft section work continued
OLS, IT: Work continued on the rails for the catch arms; Chopsticks work continued
LR11000 boom lowered, disassembly began, counterweights removed
LR11350 disassembly continued
Unknown Raptor engine delivered to launch site
NSF
Mary
Nic
LabPadre
05.11.2021
SN20/S20 equalized pressure by venting ambient air; work on it continued
LR11000-X assembly finished; counterweights added; boom and jib lifted
Raptor engines delivered to launch site (unknown number)
OLM elevator completely removed Wide bay construction work continued
Stair sections lifted in high bay
S21 engine section (5-rings, with lead-ins) moved to mid bay; lifted into mid bay
New RCs for November 11, 15 (10am-6pm), 12 (6am-12pm)
LR111350 disassembly continued; cabin and engine sections left launch site
RC58 delivered to launch site
NOTMAR issued for November 09
NSF
Mary
Nic
LabPadre
04.11.2021
Windy, rainy weather
LN2 and LOX deliveries to OLS tank farm
LR11000-X assembly continued
B4 aft section work continued
Dump trucks off LBJ boulevard
S22 nosecone barrel section; 5 rings tall and 3.6 mm steel according to label!!
Blue Origin lost lawsuit against NASA over HLS lunar lander contract with SpaceX
NSF
Mary
Nic
LabPadre
03.11.2021
B7? fwd tank #2 spotted
Wide bay construction work continued; more vertical beams (likely for wall attachment) added; first outwards facing beams for (similar to high bay) added
Black booster stand (the one with triangles) shown off Rocket Rd
B2.1 work continued near gate A3 (NSF confirms the other one to be BN2.1)
LR11000-X more parts delivered; assembly continued
RC74 delivered to launch site and unloaded; prepared for installation on B4
LR11350 more parts left launch site
SN20/S20 work on TPS tiles near aft flap
Chopsticks: More conducts installed
QD arm: piece lowered onto it
OLM elevator disassembly began, work looking to slowly conclude
Container wass construction at launch site
B4 work on fwd section
RC for November 04 canceled
NSF
Mary
Nic
LabPadre
02.11.2021
Crane moved back to production site
LR11000-X more parts (counterweights, boom and jib sections) delivered to launch site and unloaded; stacking continued
B4 fwd section worked on
OLS, IT and chopsticks work continued
PPS: More sidings added to staircase segment: two segments moved from PPS to high bay area by SPMT
Starship aft flap aerocover spotted
Booster fwd section outside the tents
Wide bay construction: More beams added
B2.1 testing preparations continued
S21 work in mid bay continued; work platform erected
Raptor engine spotted in scrapyard (unknown SN)
S22 mid-LOX section still outside tents, no TPS tiles attached yet
RC for November 03 canceled
NSF
Mary
Nic
LabPadre
01.11.2021
RC for today canceled
B2.1 preparation work for testing continued at PPS
Wide bay construction work continued; more beams delivered
PPS: Staircase work continued
S22 common dome section (sleeved, with methane header tank and lead-ins) spotted
S22 mid-LOX section (4-rings): thermal blanketing attached
Chopsticks work continued; linear actuators visible
OLS, IT: Work on chopstick rails
OLM work continued; control panel "COPV load" shown
LR11350 disassembly continued
LR11000 cleaned
FAA environmental review public comment phase now closed
RC for November 02 canceled
New RCs for November 2-4 (10am-6pm) and November 8-10 (10am-6pm)
NSF
Mary
Nic
LabPadre
Date
Description
Source
Link
31.10.2021
LR11350 disassembly continued
B4 work continued
Chopsticks work continued
More pipes lifted and installed on OLS, IT
LOX deliveries to OLS tank farm; 50th delivery truck of LOX
Launch site delivery turned around and unloaded at PPS "Atlas Copco"
SN20/S20 work continued, especially in engine area
B2.1 work continued at PPS, work through access hole
NSF
Mary
LabPadre
30.10.2021
LR11000-X more parts delivered to launch site, ballast unloaded from a truck; assembly continued
Common dome outside tents
S21 nosecone work continued
Unknown Raptor engine moved into tent
S22 mid LOX section spotted outside tent 1
B2.1 work on booster test stand continued
LR11350 "Frankencrane/Kong" disassembly of boom
B4 work on Raptor engines shield (TPS) looks complete [?]
Chopsticks work continued
QD arm work continued
SN20/S20 work around engines continued; all engines have been installed (RVac5, RVac6, RVac7, RC81, RC?, RC?)
S22? aft dome section flipped
R57 delivered to launch site
NSF
Mary
Nic
LabPadre
29.10.2021
New LR11000 parts in SpaceX custom design delivered to the launch site [to be called LR11000-X on this wiki or some suggested the community name BBC for "big black crane"]
Assembly of LR11000-X began
OLM work continued
Chopsticks work continued, downward facing extension on both arms added
Perlite expansion furnaces shown
Plumbing work on horizontal CH4 tanks at OLS tank farm continued
B4 aft section work continued
SN20/S20 Rvac6 installed, Rvac7 waiting for installation; later Rvac7 installed as well
Wide bay construction picking up the pace, more beams lifted into place
B2.1 work on test stand continued
Booster fwd sleeve and fwd dome infront of tents
NSF
Mary
LabPadre
28.10.2021
Chopsticks have swung for the first time after the actuators have been installed
Wide bay beams unloaded; at least 5 beams now errected
Nosecone in the scrapyard sliced into pieces
Chopsticks work continued
B4 work continued near common and forward dome, as well as on aft section
SN20/S20 work at engine section continued
Booster test stand has raptor gimbal joints which will attach to B2.1 on each of its RC mounting point
Work on a tent entrance
Hwy4 repair work at production site
Crane mats delivered to production site
B2.1 moved towards booster test stand at PPS by SPMT, lifted and removed from transport stand, lowered onto booster test stand
4-ring barrel section moved to scrap yard
Wide bay construction: more beams lifted, cross-beams began to be added
Rvac6 (label: "SN6")and Rvac7 (label: RV7") moved form production site to SN20/S20 at the launch site; Rvac6 lifted into aft section for first fit check, lowered again
RC for October 29 canceled
NSF
Mary
Nic
LabPadre
27.10.2021
OLM and OLS, IT work continued
Perlite sacks at OLS tank farm for further insulation
RB33 delivered to launch site [for B4]
B4 Raptor heat shield work continued, the big aerocovers now next to it [RGV]
S21 work continued in mid bay
Booster fwd dome section outside tents [sleeved?]
B5 work in high bay continued
LR11350 ballast lowered; boom lowered later, potentially for the last time
Raptor gimbal joints lifted into booster test stand; these are mounted to hydraulic cylinders which simulate Raptor engine thrust
Wide bay beams continued to be delivered
Standard TFR renewed for November, still 10000ft
NSF
Mary
Nic
LabPadre
26.10.2021
RC for today canceled
Booster fwd section spotted outside tents [label B4/B6 fwd dome??] PPS staircase assembly continued
B2.1 test tank work continued
"Dump truck pulls stuck truck carrying crane parts free"
Ship thrust simulator: parts removed
Booster test stand work at PPS
S21 in mid bay at least 7-8 rings tall, work through hatch; mass simulator plate installed
Wide bay construction work continued, new parts (beams) delivered
Crane parts stored at the PPS, some crane parts loaded onto a truck and left boca chica
LN2 truck at PPS
S21 nosecone TPS tiles work continued
Many flatbed trucks waited at Starbase sign
SN20/S20 has now 3 SL and one Rvac engine installed
Chopstick hydraulic actuator lifted for a fit check and lowered back down later
OLS, IT work continued; some crews working at the top of the tower
B4: Insulating foam added around the COPVs and QD plate; work on raptor heat shield (TPS) continued; work con raceway
Crane parts and chopstick stand structure left launch site
OLS tank farm: LOX heat exchangers tested, first venting
RC for October 28 canceled
NSF
Mary
Nic
LabPadre
25.10.2021
OLS tank farm: LOX deliveries (some from Sanchez site/PPS); Perlite expansion furnaces and hoppers shown in video for first time
SN20/S20 work in engine area continued
B4 work continued
OLS, IT work continued in several areas; cable track (the travelling cable for chopsticks) attache to upper right carriage arm
B6 aft dome on sleeving stand, ready for sleeving
Methane transfer tube for booster moved
Crane rigged for wide bay beams (yellow bigge crane)
Wide bay: more beams lifted
Ship [S22/23?] leg skirt spotted in tent 3, a cutout is visible for the quick disconnect plate
B2.1: parts added to grid fin cutouts
S21 work in mid bay
Chopsticks support structure moved away from launch site
New RCs for October 28 (10am-6pm), 29 (6am-12pm), November 1 (10am-6pm)
NSF
Mary
Nic
LabPadre
24.10.2021
Booster aft dome lowered onto sleeving stand [B6/B7?]
B2.1 work continued
Chopsticks/Carriage: Large pulley attached (diameter at least as big as a human)
LOX delivered to OLS tank farm
OLS tank farm: piping work towards horizontal tanks continued; now three different pipes visible
SN20/S20 work continued, aft section and in engine area
B4 work continued; TPS installation for Raptor engines continued; some work around COPVs
PPS: Staircase segments assembly continued
S21 nosecone rolled out of tent 3, at least 3 nosecone still inside
Ship fwd dome with label
B9 thrust puck delivered and unloaded, this is the first one for 13 engines (10+3) instead of only 9
Booster methane transfer tube (downcomer) delivered (two parts) [add Dec: not first one; first one see early Oct, likely for B7/B8]
NSF
Mary
LabPadre
23.10.2021
HLS nosecone began to be scrapped; lowest rings cut off
B2.1 (not same as BN2.1) work continued
RB32 delivered to production site
Ship aft dome sleeve infront of tents
S21 nosecone and nc barrel section still missing some few tiles
Wide bay construction work has continued
B4 and SN20/S20 worked on
Chopsticks/carriage: some minor work
QD arm moved towards tower
Two raptor engines loaded onto truck, likely back to McGregor; on identified as RB2
Catch arms carriage travelling block installed and disconnected from crane (7.49pm)
S21 fwd section stacked on common dome section in mid bay
NSF
Mary
Nic
LabPadre
22.10.2021
Two Raptor engines delivered to launch site; some left
PPS work on staircase sections continued
Booster aft tank#5 and #3 spotted [B6?, signs look like B4 and B5]
B2.1 work continued
3-ring barrel section outside tent 1
Two RC and one RB engine loaded onto raptor van
B4 work on aft section and engines continued; start of thermal protective cover installation
Plumbing work to new horizontal CH4 tanks at OLS tank farm continued
LR11350 disconnected from chopsticks/carriage which now sit on a jut like part that sticks out from the tower column
PPS: two more staircase segments loaded onto SPMT
Wide bay: first sturctural beam lifted
NASA worm logo removed from HLS mock up
SN20/S20 three RC installed late in the eventing/early next morning
NSF
Mary
Nic
LabPadre
21.10.2021
Delivery to SoLS tank farm (LN2 tanker)
SN20/S20 work continued
Plumbing attached to new horizontal taks at OLS tank farm
Grove GMK6300L-1 crane (Berry) moved to launch site
B4 work at top continued, as well as in the engine sections (new thermal protection)
Red support structure for chopsticks/carriage disassembled
LR11000 moved from OLS tank farm to landing pad
B2.1 work continued
Wide bay: beams prepared/rigged for assembly
S21 fwd dome section work
B5 aft tank #5 (LOX section, 4-rings, no lead-ins) moved
Header tank panels spotted at the production site
High bay rooftop bar work continued
Raptor 2 engine factory contstruction progress at McGregro [Reagan Beck]
SN20/S20 Static fire #1 (Rvac5) and #2 (Rvac5 and SL raptor)[229], at least 8 tiles lost during fires [see vid 22]
NSF
Mary
Nic
LabPadre
20.10.2021
Alert notice for today issued, but RC for today canceled
OLS, IT: Single skate removed and reinstalled Carriage arms opened for installation on OLS, IT [unclear when]
Chopsticks/carriage lifted from red structure by LR11350, crane rotated; lowered to correct height, installation on OLS, IT began
B4 new framing around the Raptor engines, possibly part of the new thermal protection system mentioned by Elon Musk
B2.1 work continued
Another hydraulic actuator moved to launch site, possibly for chopsticks
Two stair sections moved from PPS next to high bay
Wide bay construction; beam attached to white/blue Atlas crane (PBI)
NOTMAR for October 21 issued
FAA second public hearing for environmental assessment draft
NSF
Mary
Nic
LabPadre
19.10.2021
Evaporator at SoLS tank farm in action after SN20/S20 test
New dome on sleeving stand
B2.1 work through hatch outside mid bay
SN16 work/inspection at hatch
S21 nosecone and nc barrel section look nearly ready
Chopsticks and carriage rigged for a test lift; lifted and rigging adjusted for balance
SN20/S20 work around/in aft section
Hydraulic actuator delivered to launch site "rod side proofed, smile"
B4 work on raceway
CH4 horizontal tank (the second one) and cryo tank shell #7 (final one) rolled out to OLS tank farm
Work on GSE2 befor covering it
New RCs for October 21 (5pm-12am), 25, 26 (10am-6pm)
Alert notice issued, but later RC for tonight canceled
NOTMAR issued for SF on October 20
Shell #7 attached to LR11000 and lifted over GSE2 at OLS tank farm; the 8 tanks now complete
NSF
Mary
Nic
LabPadre
18.10.2021
LR11350 rotated towards carriage/chopsticks
Alert notice issued to Boca Chica residents for possible SN20/S20 static fire today between 4pm-1am (later corrected to 5pm-midnight); NOTMAR issued
Cryo tank shell #8 CH4 [according to label] moved from PPS to OLS tank farm (9:37-10:41), bumpers installed on the bottom inside of the shell, attached to LR11000, lifted and put over GSE8 on the most south western position
New intermittent RC for October 19 (9:30-11:30am)
OLS tank farm work continued, especially on newly delivered horizontal tank
Ship aft dome sleeved [S22?], then removed from sleeving stand
Large methane tank at PPS cleaned
PPS: Staircase work continued
PBI Manitowoc 12000 being readied at the new wide bay area, another white-blue crane already there
Raptor gimbal joints spotted
Rigging work for chopsticks/carriage; attached to LR11350
B4 work continued on its top; hydraulic power unit sled wrapped in plastic, possibly in preparation for installing aerocover
OLS tank farm: venting from ground pipes
SN20/S20 preburner test of Rvac5, vents around nosecone! [vid 19]
SN20/S20 no big apparent damage to TPS, most tiles missing were missing before test [vid19]
FAA first public hearing for environmental assessment draft
NSF
Mary
Nic
LabPadre
17.10.2021
LR11350 detached from chopsticks
Crane detached from S21 nosecone barrel section
B5 construction in high bay continued
Yellow grove crane RT915OE moved to PPS
Several LOX (yellow label) and LN2 (green label) trucks at PPS
LR11000 moved back to OLS tank farm after having lifted one catch arm to the carriage
Perlite delivered to OLS tank farm
OLS, IT: Carriage linear bearing "skate" lifted onto the tower, reinstallation began; they allow the carriage anch chopsticks to move up and down the tower; likely all skates installed this day; cable carrier [?] installed as well; a wheel spotted below the QD arm [when installed?]
Carriage welding work
B4 work continued in several areas
SN20/S20 work in skirt area
LR11350 more crane counterweights added
One of the two large tanks (for LCH4) moved from PPS to OLS tank farm
LR11000 lifted crew in a basket
OLS tank farm: First ever LOX delivery; at least 4 tankers
SN20/S20 work through upper hatch
Cocoa facility: Mk2 nosecone being dismantled
NSF
Mary
LabPadre
16.10.2021
Starbase driving tour
The chopsticks are now fully attached to LR11350 only
Grove crane delivered to launch site
NSF
Mary
15.10.2021
B2.1 [?] hybrid test tank still outside mid bay
Forward dome caps delivered; "NIPPON STEEL Stainless Steel Corporation, Yawata, made in Japan"
Raptor engines that have been moved to production site yesterday were now loaded onto raptor van (RC62, RC72, RC74)
Methane transfer tubes "downcomers" delivered (two)
OLS tank farm work continued
CH4 boil-off buffer (horizontal storage tank at OLS tank farm) constantly venting (likely LN2); "CH4 boiloff goes into buffer tanks, gets slowly condensed in Blu, goes back into buffer tanks, and returns to main storage tanks once depressurized." [The_Denks]
B4 work continued in different areas
SN20/S20 work under aft skirt continued, as well as through top hatch
Wide bay foundation work continued, many I beams ready and moved around
PPS: Booster thrust simulator work continued
Barrel section moved into tent 1
Shift aft dome outside tents
New intermittent RC for October 18 (9.30-11.30am)
LR11000 detached from second catch arm
Two Raptor engines delivered to launch site
NSF
Mary
Nic
LabPadre
14.10.2021
S22 comm dome sleeve (3-rings) outside of tents
Starship aft dome in a tent [S22?]
Barrel section with TPS tiles attachment points moved around
S21 nosecone and nc barrel section TPS installation continued
I beams unloaded from a flatbed near wide bay foundation
PPS: crane attached to a booster transport stand
New Starship thrust puck spotted at production site
PPS: Work on stairs continued
Manitowoc 12000 crane rolled back to production site
OLM work continued
Plate compactor lifted onto berm (near the tunnel)
Raptor engines removed from B4, 5 engines visible
More perlite sacks delivered to OLS tank farm; work on OLS tank farm piping continued
SN20/S20 work inside aft skirt continued
Booster thrust puck spotted at the ground tracking station
Yellow triangular shaped structure and pipes delivered to production site
RC62, RC72, RC74 moved back to production site
SN20/S20 scrubbed static fire attempt
NSF
Mary
Nic
LabPadre
13.10.2021
Overpressure notice for today's SN20/S20 static fire attempt issued
B5 first grid fin installed during night; a second one was installed later Assembly of catch/stack arms "chopsticks" and carriage continued
OLS tank farm: work on the pad north of GSE tanks; work on piping continued
Perlite delivered and unloaded at OLS tank farm; "Perlite is an insulating layer between the cryo shell and GSE tank". Kilns at the OLS tank farm expand the material into low density insulation
SN20/S20 work in the aft skirt area ahead of potential static fire
Grove GMK7550 counterweights moved to production site
RC for today cancelled, SN20/S20 static fire NET Thursday
Hybrid test tank moved out of mid bay, NSF calls it B2.1 [confusing]
S21 fwd section in tent 3 TPS tiles installed [also see yesterday]
COPV covers for booster aft section at production site
Header tank panels spotted at production site
Pulley cable spool lifted on to OLS, IT and installed to dead anchor
New RCs for October 18-20 (5pm-12am)
Todays RC cancelled
NOTMAR posted for October 14 for potential SN20/S20 static fire; Alert notice issued
NSF
Mary
Nic
LabPadre
12.10.2021
Both catching arms installed, main pin fully lowered at about 2:16 am
Raptor engines moved from launch to production site
B5 stacking continued; CH4 tank now 13 rings tall and thus completely stacked
S21 nosecone TPS work continued
S21? nosecone barrel section (the one that has been standing there since a long time) TPS installation
RB11 and RB27 loaded onto raptor van at production site
Tent 3: 4-ring barrel section with a lot of TPS tiles attached [vid 13 labelled S21 fwd section]
Wide bay foundation work continued; new blue crane on the site
Chopstick work continued
Dirt moved around at launch site, possibly for a berm?
B4 work on aft section
SN20/S20 work continued on aft section, Rvac5 installation completed
B5 first grid fin installed
NOTMAR posted for October 13 (5pm-12am)
NSF
Mary
Nic
LabPadre
11.10.2021
Second chopstick (catch/stack arm) moved from its construction area on the landing pad towards the OLS
More Raptor engines removed from B4, eg RB27 visible; furthermore RB11 and RC79 and another with invisible SN
Wide bay foundation work continued
More high bay windows ready for installation
S21 nosecone TPS tiles installation has progressed
3-ring barrel section near sleeving stand
Booster aft section with installed COPVs spotted in a fabrication tent [B6?]
Braided hose delivered to production site
S22 [sic! it's S21] in mid bay likely 6-7 rings tall
Catch/stack arm "chopstick" #2 attached to LR11000, lifted and rotated, moved into position next to the first arm on the red structure for installation on carriage system ahead of lifting on tower
Rigging on cables between arm 1 and LR11350 adjusted in order to level it
Two out of likely 12 skates/linear bearing lifted to OLS, IT (column facing the OLM); the carriage will be installed on them; they will allow the carriage to slide up and down the tower
Rvac5 engine installed on SN20/S20
SoLS/landing pad earth and concrete work continued
16:42:29 the second skate fell down from the tower; scaffolding damaged
RC for October 12 cancelled
NASA document: explaining how they intend to use the WB-57 aircraft for monitoring Starship re-entry, they target a reentry observation opportunity near March 2022
Chopsticks moved into position inside carriage near midnight
NSF
Mary
Nic
LabPadre
10.10.2021
Raptors delivered to launch site (Rvac and Sea level/RC)
Rvac6 spotted in a production tent
PPS: Staircase production continued
S22 common dome section in tent 1 (3-ring)
Single ring in front of tent (the one with a hole spotted last week)
Ring section collapsed in high winds
Green crane parts? delivered to production site, origin unknown
Cable carrier moved to launch site; possibly for the chopsticks "as it allows cables to neatly connect to moving parts", "provides power, data and hydraulics to the catching arms"
OLS tank farm work continued, especially on piping
Chopsticks: both arms will be attached with the same pin; second arm moved towards carriage
NSF
Mary
Nic
LabPadre
09.10.2021
B5 stacking continued; 3 out of 3 sections stacked
OLS tank farm: more plumbing installed near GSE2; new equipment delivered that looks like the one that has been installed yesterday
Catch/stack arms "Chopsticks" prepared to lifted, moved under LR11350 and attached to it; lifted and flipped/rotated into correct position; lowered adjacent to carriage system
OLS, IT work continued
More Raptor engines loaded onto truck
LR11000 crane began to move away from OLS tank farm, towards landing pad, likely to help with chopstick installation
Barrel section with TPS tiles (some empty spots) (3-rings with lead-ins) hooked to crane in front of mid bay, possibly for S21?; another 4-ring section in front of mid bay
Stand moved around at production site
Wide bay foundation work continued
S22 cmn dome section seen
S21 common dome moved into mid bay
Steel cladding added to a container wall
NSF
Mary
Nic
LabPadre
08.10.2021
S21 nosecone TPS heat shield tiles installation continued, red tape added to the top, some tape on the flap TPS tiles
Starship aerocover spotted, likely for aft flap
Deliveries to production site
High bay rooftop bar work continued
Ground fabrication building expansion work continued
Wide bay foundation work continued, pins/points for columns spotted
Starship thrust simulator with six hydraulic rams at PPS?
PPS: Ship aft skirt test article worked on again
OLS tank farm: New equipment lifted into place near the eastern LOX subcoolers; welding work on some pipes
Raptor engines loaded onto truck at launch site, RC58, RB26 visible; at least to other on pad
Crane basket moved at production site
Earth work at the launch site
OLS, IT: QD arm operational under own power for the first time
NSF
Mary
Nic
LabPadre
07.10.2021
LR11350 disconnected from carriage system on red stand; work on it continued
Loadspreader attached to LR11000
Catch/stack arms "Chopsticks" work continued
LN2? delivered to OLS tank farm
OLS tank farm: work on/around the ground piping
GSE8 tank rolled out to OLS tank farm, attached to LR11000 crane, lifted and placed onto final empty stand at the most south-western slot; only two shells now remaining to be rolled out
Pin (likely at the connection point to the chopsticks) placed into carriage for fit check, then removed
OLS, IT: work continued, more pipes lifted into place
Concrete forms for new wide bay delivered
PPS: funny looking black tank rolled around
SN2 shown behind scrapyard
S21 nosecone work continued; progress on TPS installation marginal; as well as on barrel section
New ship fwd dome on sleeving stand [the one seen on October 5?]
Work on high bay rooftob (bar) continued
Wide bay foundation work continued
SPMT spreader bars moved to build site
RC for October 11 cancelled
NSF
Mary
Nic
LabPadre
06.10.2021
New booster thrust puck for 13 engines [B5/B6?] lifted from truck
S22 cmn dome being worked on on the sleeving stand
B5? grid fin moved into tent 1
Booster thrust puck moved out of tent 2, then moved back into the tent again
Ship aft dome moved into tent 3
S22 cmn "comm" dome sleeve (3-ring) placed on a stand
B5 fwd section stacked in high bay (currently 6 rings?)
Second huge propellant storage tank delivered to PPS
S22 cmn dome section sleeved
Single ring section outside tents (near fwd dome), hole cut into the side
Delivery of different parts to production site
B5 fwd CH4 tank section now likely 9 rings tall; more sections ready
Wide bay foundation work continued
PPS: Stair enclosing work continued
OLM work continued
OLS, IT: welding work
Carriage system for chopsticks attached to LR11350, then lifted and flipped to a vertical position; then lifted higer, crane moved forward and the carriage system was placed on the red stand/hurdle structure [great closeup]
RCs for October 7 and 8 cancelled, new RCs for OCtober 12-14 (5pm-12am) and for October 7 (11am-1pm)
NSF
Mary
Nic
LabPadre
05.10.2021
OLS tank farm: Work on GSE2 and ground piping continued; grey horizontal tank lowered into place behind the west LOX subcoolers (near the white tanks that have been added recently)
OLM work continued, painting
OLS, IT work continued, including on the QD arm (there is a work platform on the arm)
B4 work continued, especially around the aft section with the QD ports and COPVs
Concrete poured south of landing site
New red structure (two big "hurdles") assembled between OLM and OLS tank farm bunker, look like a temporary structure; a tall one and a smaller one
LN2 delivered to SoLS tank farm
Booster thrust puck with old 9 engine design shown
PPS: Stair construction continued with walls beginning to be added
PPS: Concrete work
Wide bay work continued with concrete poured into place for foundation
Barrel section near tent disconnected from a crane
B5 fwd #4 section spotted (4-ring with lead-ins)
B6 fwd #2 section spotted (3-ring "triple stack")
B6 aft #5 section spotted (4-ring, "4.0mm")
S22 cmn dome on sleeving stand; a fwd dome in front of it
B5 grid fins shown
High bay work continued with more windows being lifted and installed
Mid bay: Hybrid booster-ship tank construction continued; B fwd section and B aft sleeve with S thrust puck
Booster fwd section spotted in a tent [B5/B6?]
Heat exchanger place next to ground fabrication building
Nosecone [S21?] work in tent 3 continued, TPS tiles being attached
Steel cladding added to a container wall
Huge Liquid Methane tank delivered to Starbase on two SPMTs led by a truck, accompanied by a small convoy; power lines had to be removed in order to let it pass [to PPS]
Booster [B5/B6?] thrust puck with 13 engine mounts delivered for booster with new 33 engine design (3, 10, 20 vs 1, 8, 20)
NSF
Mary
Nic
LabPadre
04.10.2021
Deliveries to production site
B5? fwd section prepared for stacking, attached to crane
Ground fabrication building addition worked on
High bay rooftop bar work continued
Booster thrust simulation stand work at PPS, possibly preparing transport
Booster 3-ring fwd section [thought to be B5?] stacked on the booster sleeve with ship thrust puck for unknown reason
OLM work continued, especially around booster QD system
OLS, IT: work continued; work on the possible carriage system rails
B4 work continued; workers on top of the fwd dome; work on one of the long pipes (tightening screws); inspection
OLS tank farm: work via crane basket lifted by LR11000
The small diameter tank in high bay could be, together with the 33? hole ring segment, part of a "header tank" or separate tank for the booster that would be used for boost back and landing due to slosh (WAI)
NSF
Mary
Nic
LabPadre
Wai
03.10.2021
Two large crates loaded onto truck
OLM work continued
LR11350 crane shortened; later raised in the new configuration without jib but still with power boom
OLS tank farm: work at the top of GSE2 tank continued
SN20/S20 work in aft section
B4 worked on in several areas with man lift goint up to the top, orange "AVI" bags near the top of the line
Catch/stack arms "chopsticks" and carriage system work continued
LN2 delivered to SoLS tank farm
GSE8 still waiting infront mid bay for roll out
LR11000 disconnected from Shell #3
SN20/S20 aft flaps opened during flap test [vid 04]
OLS, IT: welding work [vid 04]
NSF
Mary
Nic
LabPadre
02.10.2021
Booster thrust sleeve (3-ring) with ship thrust puck spotted, unclear use
New Liebherr LTR1220 crane spotted at production site
Concrete forms used for wider high bay/wide bay shown
Tubular part first spotted on September 19 still at production site
S21 4-ring section in mid bay waiting for stacking to begin
Fwd dome spotted inside tent 1
Delivery of a cabin and a ring segment with 33 holes
PPS: currently seven stair segments nearing completion
Rigging attached to a crane (GTC-900 Mantis)
OLM work continued
B4 work continued with man lifts up to the top; work on the center lines
OLS tank farm: Shell #3 lifted by LR11000 and placed over GSE6; the most southwestern stand now empty for GSE8; work on GSE2 strengtheners continued
Booster thrust puck delivered [B5?, B6?]
NSF
Mary
Nic
LabPadre
01.10.2021
SN20/S20 venting
LR11350 disassembly continued
SN20/S20 thrust ram removed from engine section/pad B
RB29, RB30, RC80 engines delivered to production site and unloaded
Ship fwd section spotted infront of tents (4-ring)
Catch/stack arms "chopsticks" and carriage system work continued
OLS tank farm: Work inside shells #5 and #6 [?]
Ship [S21?] cmn dome with TPS tiles attachment points and CH4 header tank spotted
S21 nosecone work continued, second aft flap installed
Crane counterweights delivered to production site
RC for October 4 cancelled
New RCs for October 2 (12.01-1am, intermittent), 07 (5pm-12am), 08 (6-12pm), 11 (5pm-12am)
NSF
Mary
LabPadre
Date
Description
Source
Link
30.09.2021
OLS, IT work continued
OLM work continued
LN2 delivery to OLS tank farm
OLS tank farm: GSE2 tank work continued; work in shell #5
LR11350 "Frankencrane/Bluto" lowered; likely needed for a bridge installation somewhere else
Insulated piping delivered to launch site "DXS1 cryoproof XC, Orbital"
Dog walking around
Bearings installed to Catch/stack arms "chopsticks" for transport; lines/pipes installed to carriage system
B4 work around the skirt area continued and hull
PPS: Stair work continued
B5 fwd dome section moved into high bay
B5 grid fins ready for installation
S21 nosecone and nosecone barrel section TPS tiles installation; first fwd flap installted to nosecone
B6 cmn dome section (3-ring with stiffeners and hole) spotted
RC for today cancelled
FAA: Public comment period for environmental assessment extended to November 1, Public hearing moved to October 18 and 20 at 5pm
NSF
Mary
LabPadre
29.09.2021
New RCs for September 30 (5pm-12am), October 1 (6am-12pm), October 4 (5pm-12am)
OLM work continued; it is suggested that the OL platform includes a system of 20 QD systems that will absorb the outer booster engine chill so the cold vents don't damage the hold down clamps and other structures
OLS tank farm: Ventilation hose coming out of Shell #5, workers inside
Catch/stack arms "Chopsticks" and carriage system work continued
SN20/S20 work continued ahead of testing
LOX delivery to SoLS tank farm
LN2 delivery to OLS tank farm
Shipping container painted black
B5? fwd section (3-rings with stiffeners) outside high bay
Large black pipe outside high bay
Barrel section (3-rings with lead-ins) moved out of high bay
Concrete trucks at PPS
S21 Nosecone TPS tiles installation continued inside tent 3
B5 cmn dome section worked on in high bay; LOX section is hooked to bridge crane
High bay rooftop work continued
New barrel section with tile attachment points spotted
Work on structure behind mid bay continued
SN20/S20 cryo proof test
New future ship/booster test stand foundation spotted near the current location of B4
B5: Two grid fins spotted
NSF
Mary
Nic
LabPadre
RGV
28.09.2021
S21 nosecone TPS tiles installation continued
3 Raptor engines loaded onto truck (two gimbaling, one fix)
Wide high bay "Wide bay" foundation work continued; concrete poured
Work on the five stairs at PPS continued
Cement truck cleaned at cleaning facility
Toy trucks spotted on flatbed
OLM construction continued
RCs for today and September 29 changed to 3pm-12am
SN20/S20 testing scrubbed
Michael Sheetz: SpaceX is working with Dr. Saul Perlmutter at UC Berkeley on a space based telescope that would be launched by Starship. They could launch satellites that have 10 times the resolution of the Hubble.
RC for today canceled
NSF
Mary
Nic
LabPadre
Michael Sheetz
27.09.2021
Crew raised in a basket over cryo shells at OLS tank farm
LR11000 still attached to shell #3 at OLS tank farm
OLM work continued
OLS tank farm: LN2 delivery continued; Shell #1 huge venting
B4 work at upper LOX tank
OLM work continued
SN20/S20 prepared for testing; thrust simulator has been installed earlier; work around the quick disconnect fitting
Catch/stack arms work continued
High bay glass panel installation and rooftop work continued
Wide high bay foundation work continued
Rig moved
Possible methane transfer tube "downcomer" delivered
Barrel section with lead-ins [S21?] spotted in mid bay
Welding robot delivered
SN20/S20 pneumatic (ambient) proof test (some TPS tiles lost) and cryo proof test
10000ft TFR extended for October
NSF
Mary
Nic
LabPadre
26.09.2021
S21 aft section outside tents (5 rings and lead-ins; thrust and skirt sections)
S21 nosecone TPS installation continued
B5 fwd #4 section (4-ring and lead-ins) spotted
S21 cmn "comm" dome section (3-ring) spotted; previously slated for S22
Catch/stack arms "chopsticks" and carriage system work continued
LN2 deliveries to OLS tank farm continued
B4 rolled away from OLM
SN20/S20 worked on
LOX delivery to SoLS tank farm
High bay: more class panels installed at rooftop bar
LR11000 detached from Shell #5 at OLS tank farm; attached to Shell #3
NSF
Mary
LabPadre
25.09.2021
Grove GMK 7550 crane moved to launch site; extra parts on SPMT
PPS: stair production continued
Dome sleeving stand hooked to crane
Methane header tank outside tents for weeks now
GSE8 seems to be more or less ready for roll out
LR11350 and load spreader attached to B4
Two horizontal white tanks transported to OLS by two SPMTs; installed at OLS tank farm, south from GSE tanks and shells
B5? fwd section inside production tent spotted, with stringers (vertical supports)
Catch/stack arms work continued
B4 lifted off from the OLM/pad by LR11350, likely not to damage the booster during installation of catch/stack arms on OLS, IT; carefully placed onto booster stand
Common dome section flipped [?]
LR11350 detached from B4
NSF
Mary
Nic
LabPadre
24.09.2021
S21 barrel sections with TPS tiles attachement in progress spotted
Blue booster COPV cover [B4/B5?] spotted
Thrust puck shucker (center engine thrust simulator) rolled out to launch site
B4 workers at the top
RC for today cancelled
Booster stand rolled out to launch site for B4
Cryo tank shell #5 lifted at 10.35am and put over GSE1 by LR11000; touched ground at 11.15am
RC for Monday changed to 3pm-12am
S21 nosecone TPS installation continued in tent
RVac puck shucking equipment for SN20/S20 returned to launch site, installed under Ship on test stand B, with center engine thrust pucker
LR11350 lifted a loadspreader towards B4 ahead of destacking from OLM
Catch/stack arms "Chopsticks" and carriage work contineud
Large pipe spotted infront of high bay [B5 downcomer?]
A small diameter tank spotted in high bay next to B5
B5 lifted in high bay to facilitate further stacking operations [vid 25]
NSF
Mary
LabPadre
Starship Gazer
23.09.2021
SN20/S20: cryo pipes installed to test stand [?]
S21 fwd dome sleeved
S21 fwd flaps spotted
S21 4-ring barrel section with TPS blankets spotted
OLM work continued, more venting from GSE5/#1
QD arm extension lifted by LR11350 and installed on OLS, IT by 12.30 pm
Catch/stack arms and carriage system work continued
PPS: stair construction continued
Deliveries at production site
Foundation work for wide high bay continued, rebar laid
LN2 deliveries from PPS to OLS tank farm
PPS: Crane attached to the center engine thrust simulator, which uses hydraulic rams to simulate Raptor engine thrust during proof tests
SN17 aft dome scrapping continued
Cryo tank shell #5 lifted to remove the SPMTs; SPMTs moved back to production site
OLS tank farm: Cryo test at around 9.20 pm
QD arm extension unhooked from LR11350
NSF
Mary
LabPadre
RGV
22.09.2021
GSE8 rolled out of mid bay
RC for today cancelled
New RCs for 27-29 September (5-11pm)
S21 fwd dome on sleeving stand, 4-ring barrel section connected to crane
LN2 deliveries to OLS tank farm continued
OLS tank farm venting: testing for first time; GSE5/#1 (LOX) tank tested with nitrogen (cryo proof test?)
Deliveries to launch site
Catch/stack arms work continued
OLM: flexible feeding pipes installed to quick disconnect system
SN17 aft dome scrapping continued: dome cut out
Foundation work for wider high bay continued
PPS: nitrogen production for OLS tank farm [?]
NSF
Mary LabPadre
21.09.2021
S21 nosecone receiving thermal blankets ahead of TPS tile installation
S21 mid LOX section with lead-ins and a lot of TPS tiles installed spotted
QD arm extension attached to LR11350 and another crane and flipped upright
Many deliveries to launch site: red steel parts and helium
Unused nosecone next to scrapyard likely to be scrapped
B4/B5/B6?? fwd dome sleeve spotted (3-ring with strengthening/enforcement)
B4/B5/B6?? aft tank #3 segment spotted (4-ring)
Delivery of some red equipment to production site
Black pipe sticking out of high bay
The columns wrapped in blue sheets now called "industrial columns for chemical processes" [the ones delivered on and around July 19th?]
PPS: stairs being built within grey T-bar structure; at least four under construction
CH4 delivery to propellant plant (PPS)
Stormy weather arrived
Catch/stack arms and carriage system work continued as rainfall began
SoLS work; all available space used for storage and work
SN17 thrust section at scrap yard, not looking very good
GSE5 LOX tank venting; likely cryo proof test performed with LN2
NSF
Mary
Nic
LabPadre
20.09.2021
More LN2 deliveries for OLS tank farm
New intermittent RC for today (9-10:30am) QD arm extension moved to launch site, arrived at 9:50 am
Load spreader from LR11000 attached to cryo tank shell #5 at 10:40am (will be lifted over GSE1)
RC for September 21 cancelled
GSE1 bottom hatch closed as well and scaffolding removed
Catch/stack arms and carriage system work continued; parts painted black
Red blocks with cross beams delivered to launch site
GSE4 modifications continued
Unused nosecone at production site, some TPS tiles have been installed
Foundation work for new wider high bay continued, SN17 aft section (with thrust dome & thrust puck from inside) visible at scrapyard
GSE8 still in mid bay, reaedy to roll out soon, pipes have been installed
Fwd flap aerocover with TPS tiles attachment points visible spotted; different types of pins/points: some with a round head, some with a pointed head
Unknown, long rusty tube remained at production site
NSF
Mary
Nic LabPadre
19.09.2021
OLS tank farm: LN2 (liquid nitrogen) delivered!! [at least three trucks], cryo fluid moved through the pipes
OLS tank farm: GSE2 work continued
B4: RC67 continued to be removed (raptor installation platform has been used for first time); returned to production site
Catch/stack arms and their carriage system work continued
RC64 delivered to launch site; installed on B4 via installation platform and Tesco Hi-Lift later (11.25am)
SN20/S20 work under aft section
Nosecone with TPS attachment points in tent 3
Unknown strcuture (some sort of long pipe) spotted infront of high bay
Remedios Rd still closed [?]
Rvac engine moved at production site
Ship cmn dome still on sleeving stand
Rvac and another Raptor engine moved back to launch site
OLM: cryo hose attached as part of QD system
B5 stacking continued, now 20 rings tall LOX section
NSF
Mary
LabPadre
18.09.2021
Concrete poured for new wider high bay
SN17 thrust dome section being scrapped
GSE4 had a smaller grey vertical tank attached to its side
Ship [S21?] aerocover delivered
B5 stacking continued; 16 rings tall and a new 4-ring segment prepared in high bay
Ship cmn dome on sleeving stand
OLS tank farm: GSE1 and GSE2 work continued
OLM work continued
Catch/stack arms "chopsticks" work continued
SPMT arrived at launch site
Starship 4-ring barrel section spotted with TPS mounts and white covering [what's the name for it?]
B4: Raptor engine RC67 removed
Temporary RC of Remedios Rd due to "small tank testing" from 12pm to 12am [vid 19]
NSF
Mary
LabPadre
17.09.2021
B5 fwd dome moved into production tent; stacking of LOX section continued, now 16 rings tall
Methane transfer tube [S21?]delivered to production site (downcomer)
Cryo tank shell #5 rolled to the launch site [according to label slated for GSE1, LN2]
Possible raptor installation platform (stair tower) rolled out to launch site together with shell #5
OLS, IT: hardware lowered from the top of the tower; LR11350 auxiliary hoist seems to be operational again
OLM work continued
Catch/stack arms (chopstick) and carriage work continued; big rail installed on one of the arms
Possible QD arm extension work continued; more lines and cables have been installed
Two new stair towers under construction at PPS?
GSE4 work at PPS continued; likely new adapters installed on the top of the dome
SN20/S20 work continued (access hatch open, work inside)
FAA: draft environment assessment for starship/superheavy launches from Starbase. Public comment period ends at October 18
NSF
Mary
LabPadre
16.09.2021
Possible QD arm extension work continued
High bay rooftop bar construction continued
Grove RT 913 OE-2 crane moved down hwy4
B5 stacking in high bay; now at least 12 rings [?] tall LOX section
Deliveries to production site; aerocovers for new Starship delivered [S21?]
B4 and OLM intense work continued
3-ring barrel section moved outside the tents
New grey T-bar structure with stairs assembled at PPS
Lift placed into a 4-ring barrel section
Foundation work for wider high bay continued
Nosecone with TPS tile attachment points spotted inside tent 3
GSE8 work in mid bay continued
GSE8 unused fwd dome (2-ring and scrapped dome) moved outside on a stand (it was seen inside the tent at the beginning of the month)
Roll of steel cable delivered
SN20/S20 work inside the aft section
OLS tank farm: GSE1 hatch closed [actually earlier], GSE2 hatch closed too
Catch/stack arms (incl carriage) work continued
New intermittent RC for September 17 (9.30-11.30am)
SpaceX McGregor: Now 5 Raptor test stand bays available; foundations for new Raptor 2 factory spotted
NSF
Mary
Nic
LabPadre
15.09.2021
Deliveries to production site
OLM work continued
OLS, IT work continued (as every day; a lot of pipes have been installed)
B4 prepared for testing
OLS tank farm: some work on GSE bunker
Catch/stack arms work continued; third and fourth carriage system extension has been added
SN20/S20 work continued; manlifts up at access hatch; TPS work continued as well, some markings and missing tiles in the aft area; Raptor engine installation
B5 stacking in high bay continued; now apparently 12 rings tall
Possible QD arm extension work continued
PPS: GSE4 test tank worked on at the top
Foundation work for new wider high bay continued; much rebar and concrete plates prepared
New nosecones spotted in tent 3
GSE8 now fully stacked in mid bay, pipe installation continued
RC for September 17 canceled
New RCs for September 22, 23 (5-11pm), 24 (6am-9pm)
NSF
Mary
Nic
LabPadre
14.09.2021
SN20/S20 hatch opened for work; TPS tiles looking nearly fully repaired
LR11350 crane worked on, taking advantage of the storm; lifted again later
Carriage system for "Chopsticks" (stack/catch arms) work continued
Coil of stainless steel delivered
Possible QD arm extension work continued, other side received some sort of cap (instead of adapter) as well
Ground fabrication building expansion work continued
GSE8 tank aft dome section (dome+3-ring sleeve) flipped
B5 stacking in high bay seems to have continued (another LOX tank section?)
GSE8 tank in mid bay: more pipes installed
Foundation work for new wider high bay continued
Barrel section with TPS tile attachment points in scrapyard
B5 fwd tank section #2 (3-ring stack) infront of tents
GSE8 aft section moved towards mid bay; later hooked to crane outside mid bay and lifted into it for final stacking
S21 (potentially?) cmn dome and a methane header tank spotted
S21 cmn dome sleeve (4-ring section) spotted
B5 fwd dome sleeve moved (with dome)
S21? cmn dome has been placed on sleeving stand
OLS tank farm: GSE1 access hatch closed after 4 month of work
NSF
Mary
Nic
LabPadre
13.09.2021
Tropical storm Nicholas impacted Boca Chica
RC for public saftey during storm
LR11350 has been lowered, possibly to anticipated high winds [but not LR11000]
Booster transport stand shown in vid
Barrel sections at production site: some are likely for B5
Possible QD arm extension work continued, adapter [?] added on one side
B5 cmn dome section and aft #2 section stacked in high bay by bridge crane; now likely 8 rings tall [actually already yesterday]
Robot inspected a barrel section in a tent
OLS tank farm: work continued; GSE1 and GSE2 access hatches still open
New RCs for September 17 (6am-12pm), 20, 21 (5-11pm)
New intermittent RC for September 14 (3-5pm)
NSF
Mary
Nic
LabPadre
12.09.2021
Catch/stacking arm work continued overnight and during the day
OLS, IT: work continued overnight
B5 thrust dome sleeve flipped at 2:01am
B5 fwd section now sleeved, put on a stand
The extended arms (U+L shapes) now being called carriage system by NSF; according to NSF, the chopsticks will be attached to the carriage
Possible QD arm extension work continued, more lines installed, together with some pneumatics
B6 cmn dome sleeve spotted (4-ring section)
Old nosecone spotted outside of tents, may be scrapped soon
B4 and OLM work continued, QD system has been retracted
SN20/S20 TPS tiles work continued; hatch was closed
B5 cmn dome section and aft #2 section stacked in high bay by bridge crane; now 8 rings tall
NSF
Nic LabPadre
11.09.2021
B5 fwd dome sleeved with 3-ring (enforced) section
Robotic welders spotted on a flatbed
Possible QD arm extension work continued; many lines and pipes have now been installed on it
Raptor engines [Big chongus and FULL SEND] delivered to production site
GSE8 work in mid bay continued
Foundation work for new wider high bay continued
Work on nosecones in tent 3
Loadspreader moved down Remedios ave
SN20/S20 work on TPS tiles seems quite complete by now, a few missing on the top of the nosecone, especially around the crane attachment points
Scaffolding stored and staged at launch site
New claw arms spotted, yet unclear if these are for catch system or QD arm [u-shaped pieces added to one of the L-shaped structures near the catch arms]
Work on stack/catch arms continued
S22 cmn dome sleeve has apparently been spotted [L2?]
B4 and LR11350 detached
NSF
Nic
LabPadre
Marcus House
10.09.2021
Rvac engine arrived at launch site at 1:36 am; fitted on SN20/S20 at 4:22 am
Liquid nitrogen truck at PPS again
Foundation and earth work (excavations) for new wider high bay continued
SN6 aft dome scrapping continued
GSE8 work in mid bay continued; hooked to crane; outside pipes still to be installed
Possible QD arm extension work continued
B5 fwd dome sleeve flipped at 9:16 am
B5 fwd dome placed on sleeving stand [B5 fwd dome sleeve right behind the yellow crane in the video]
B5 cmn dome moved into high bay
OLS, tank farm: GSE cryo tank shell #6 lifted at 9:54 am, placed over GSE7 at 10:47 am; red protective balloons used during stacking process
B4 and OLM work continued
Unknown equipment left launch site
SPMT with a black ring at the OLS tank farm
4th perlite kiln delivered to launch site
NSF
Stephen
LabPadre
09.09.2021
Liquid nitrogen delivery to PPS continued (at the PPS, there are two big and one smaller horizontal white tank next to the refinery)
PPS: Work on prop prod plant continued; also, new storage areas are being built under the solar panels next to hwy4
Foundation work for new wider high bay continued; rebar being laid and concrete poured; in the background SN6 aft dome (4-ring barrel section with dome) lied around and being scrapped, looking very damaged
SN2 work being done (was a test tank, now acting as a water tank)
Possible QD arm extension work continued
OLS tank farm: work on GSE1, GSE2 and GSE7, where LR11000 lifted a work platform
Catch and stack arms work continued
B4 and OLM work continued
OLM; earlier this month, brackets have been attached to a leg of the OLM, similar brackets on another leg were used for water pipes
GSE pipes lifted into place at launch site near landing pad [?], pieces of insulated pipes being connected
OLM: Quick disconnect extended towards booster at 10:11 am
RC for September 10 canceled
New intermittent RC for September 13 (9-11am)
NSF
Stephen
Nic
08.09.2021
SN20/S20 damaged TPS tiles replacement continued, most marked tiles have been replaced or repaired; work in the engine bay
Catch/stack arm work continued; pneumatic or hydraulic lines have been installed (they will likely control small actuators along the arm)
Foundation work for new wider high bay continued
Liquid nitrogen transfer at PPS
GSE8 work in mid bay continued
Work on possible QD arm extension continued
B4 lifted onto OLM/platform by LR11350 (following outer engines identified: RB12, RB18, RB15, RB17, RB3, RB6, RB2 RB27?, RB4, RB20, RB5, RB9, [RB25?, RB26?], RB19, RB21, RB24, RB11, RB12); touch down at around 11:52 am; secured onto platform
OLS tank farm: GSE7 work through work platform lifted by LR11000
OLS, IT: tower work continued at several points
SN20/S20 work continued in several areas
NSF
Stephen
Nic
LabPadre
07.09.2021
B5 aft dome sleeved early in the morning
B4 was removed from bridge crane in high bay at 1:02 am
B4 rolled back to launch site; (roll out started at 8:04 am, hwy4 at 8:18, arrived at launch site at 9:34 am)all 29 Raptor engines appear to have been installed; but there are no thermal insulation coverings around the engines
B4 hooked to LR11350 crane
GSE8 fwd dome (sleeved) hooked to crane; moved to mid bay and stacked onto the rest of the current stack
OLM work continued
SN20/S20 work on TPS tiles continued; coloured labels slowly getting less
Foundation/earth work for new wider high bay continued
NSF
Stephen
Nic
LabPadre
06.09.2021
Work on Raptor engine at launch site ahead of installation on SN20/S20
SN20/S20 work near/through access hatch
Booster [B5?] aft dome ready for sleeving on the stand
Barrel sections with TPS tiles attachment studs spotted
Possible QD arm extionson work continued
B4 work in high bay continued
SPMT moved towards high bay/B4 for transporting it to launch site later
Cryo tanker truck at PPS; venting from the huge horizontal tanks
B5 aft dome barrel section ready for sleeving; flipped at 2:47 pm
GSE8 in mid bay
Foundation/earth work for new, wider high bay continued
SN20/S20 Raptor engines being installed (RSL); work on TPS tiles continued, now blue and turquoise markings appeared
Catch arm work continued
OLS tank farm: GSE1 work continued (this tank will hold liquid nitrogen, LN2)
Engine driven welders loaded onto a truck
NSF
Nic
Stephen
LabPadre
05.09.2021
SN20/S20 work under skirt ahead of Raptor installation
SN20/S20 TPS tiles replacement continued
Catch arm work continued
Delivery of huge brown pipes at production site
B5? dome section (4-ring) prepared for flipping
B4 work in high bay continued
NSF
Stephen
LabPadre
04.09.2021
SN20/S20 work on aft section (manlifts going up under skirt) continued as well as on TPS tiles; more work through the access port
Catch arm work continued
OLM work continued
Compressed gas tube moved into position at OLS tank farm (bunker area) (typically used for helium or nitrogen storage)
OLS tank farm: GSE tank work continued (on GSE1)
Foundation/earth work for new "wider" high bay continued
Old flap storage shown, likely a flap for SN17 spotted
Raptor engine unhooked in one of the tents
QD arm extension work continued
B4 work at its aft area in high bay
OLS, IT: work continued
3 Raptor center engines delivered to production [sic!, launch] site [vid 05]; identified as RSN73, RSN78, RSN69
NSF
Stephen
Nic
LabPadre
03.09.2021
SN20/S20 work continued
OLM/platform work continued
B4 work in high bay continued
Cryo tank shell #6 rolled out to OLS tank farm (to be put over GSE7) and arrived at 9:38 am, now three remaining shells at PPS; load spreader and LR11000 attached to shell #6 at around 10:30 am
Barrel section with access port spotted in a tent
Foundation and earth work for new "wider" high bay continued
Delivery to production site
The possible QD arm extension begins to take shape, seems to get some sort of gripping mechanism, likely to stabilise the booster/ship on the launch pad
Unknown fwd dome spotted, parts of top appear to have been cut off
New intermittent RC for September 10 (9:30-11:30am)
NSF
Nic
LabPadre
02.09.2021
OLM work continued during the night; a lot of welding
SN20/S20 TPS tiles work continued
Barrel section with unusual reinforcment on middle ring (3-ring with lead-ins) spotted in tent
New structure possibly for QD arm extension (or catch arm segment) worked on
B5? aft dome spotted
GSE8 fwd dome put on sleeving stand and later sleeved with a 2-ring barrel section
B4 still in high bay, work looks rather finished
Cryo tank shell #7 unhooked from yellow crane, now ready for transport
New high structure being built at production site; it could be a Raptor installation platform
LTM 1350-6.1 packed up for return after it helped installation of QD-arm on OLS, IT
Foundation/earth work for new "wider" high bay continued
GSE8 tank now identified in mid bay
Tent 3: nosecone in production with an aerocover, this might be a test as usually the flap is installed first
QD arm work on OLS, IT continued
SN20/S20 prepared for upcoming cryo tests
Catch arms (also used for stacking Starship) work continued
New intermittent RC for September 7 (7:30-11:30am)
OLS tank farm: GSE cryo shell #1 (most north-eastern) fully filled with Perlite insulation, lines removed [????]
NSF
Mary
Nic
LabPadre
01.09.2021
GSE7 has been placed next to GSE2 by LR11000; later crane was detached at 10:30 am
OLS tank farm: work on LOX subcoolers continued; piping
Catch arms work continued; one of them has been flipped onto its side ahead of installation
OLS, IT work continued (as every day)
OLM work continued
Possible QD arm extension work continued
Foundation work for new wide high bay continued
Stainless steel ring moved to scrapyard
B5 [?] common dome sleeved (4-ring)
New intermittent RC for September 3 (7:30-10:30am)
RC for September 2 canceled
NSF
Mary
Nic
LabPadre
Date
Description
Source
Link
31.08.2021
SN20/S20 still awaiting testing on Pad A; work on TPS tiles continued
Catch arm work continued; one catch arm has been flipped at 2 pm
OLS tank farm: GSE1 work continued
Plumbing work near the LOX subcoolers (grey horizontal tanks)
GSE4 test tank rolled back to production site; to PPS
QD arm installation continued
GSE7 rolled out to OLS, arrived at OLS tank farm at 10:27 am; load spreader attached (by LR11000) at 12:59 pm; GSE7 lifted at 3:57 pm, touched down at 5 pm next to GSE2
B4 work continued near interstage and grid fins
Tent assembly continued
Concrete placing boom infront of OLM;
OLM booster quick disconnect
New intermittent RC for September 2 (3-5pm)
RC for September 1 cancelled
Standard TFR renewed, higher than previous (10000ft), ending on September 31
NSF
Mary
Nic
LabPadre
30.08.2021
OLS Tank farm: work around the base
OLS, IT: QD arm installation continued
Cach arm work continues (Also called the chostick arm, chopsticks or catch & stack arm)
OLM: work on QD equipment
LTM 1350-6.1 soon ready
B4 work in high bay continued
Beams delivered to production site
GSE7 work looking finished
New tent under construction [!] (north of where they're building the new high bay)
QD arm extension being worked on
New intermittent RC for September 1 (8am-12pm)
NSF
Nic
LabPadre
29.08.2021
QD arm lifted by LR11350 and installed on segment #5 of OLS, IT; attachment points are on the upper cross beam of segment #4 and middle cross beam of segment #5
Catch arm work continued, some welding
SN20/S20 work continued
Unknown items delivered to production site
GSE7 tank work outside mid bay continued
B4 work in high bay continued; engine RB5 moved into high bay for installation
Work on QD arm continued; detached from LR11350 at 3.45 pm; later first actuation test started at 5.25 pm
OLM construction work continued
NSF
Mary
Nic
LabPadre
28.08.2021
New intermittent RC added for August 31 (8am-12pm)
New structure at production site; looking like the QD for OLM [?] GSE7 tank work outside of mid bay; nearly all pipes have been installed now
B4 Raptor engines continued to be added
OLS tank farm: Work continued, work on GSE1
Hwy4 work in front of launch site [new slope grading?]
Catch arm work continued
QD arm, now fully painted black, prepared for lifting onto OLS, IT; work on the arm's hinge area; later the arm was moved towards LR11350, hooked to crane, lifted above ground and reoriented
SN20/S20 work on TPS tiles continued
New LTM 1350-6.1 crane configuration changed
Inspiration4 astronauts flew low over Starbase
NSF
Mary
Nic
LabPadre
27.08.2021
S21 aft dome section (3-ring and dome) flipped infront of tents; inside of dome clearly visible
LTM 1350-6.1 raised its jib; now higher than LR11000 [?]
B4 work, especially at the aft section, continued in high bay; RB2, RB27 and RB4 spotted on B4; also some center Raptor [RC] engines have been spotted outside high bay
S21 nosecone barrel section moved; a label on it indicates that it is made of 3.6mm steel [!!!!]
Booster inner engine thrust simulater (Triangle-stand) work has continued; same stand was used for BN2.1 testing, as well as part of the nosecone test rig (new info according to NSF)
Pipe stands delivered to production site
SN15 and the moon shown
GSE7 in mid bay; unknown 6-ring section right to it [GSE8?, S21?, B5?]
Nosecones being worked on in tent 3
GSE7 rolled out of mid bay
OLS, IT: scaffolding lowered by LR11350; QD arm actuator installed at 5.30 pm
OLM work continued
Catch arm work continued
QD arm work continued, being painted black; later moved towards OLS, IT
SN20/S20 work continued
Hwy4 work continued; "Manual Checkout Cart" arrived at launch site
Mobile crane form Bigge moved to launch site
NSF
Mary
LabPadre
Austin Barnard
26.08.2021
S21 aft section (3-ring sleeve with dome) on stand, not yet flipped
OLM work continued; Quick disconnect for booster installed (for loading propellant into booster) [the structure spotted on August 19 and 21?]
OLS tank farm: more pipes added around propellant subcoolers (the grey horizontal tanks)
Catch arm work continued
QD arm work continued
New black steel structure delivered to build site
New wider high bay: Earth work continued for foundation
New smooth nosecone work in tent 3 continued
B4 work in high bay continued
SN20/S20 work continued
Cryo tank shell #3 disconnected from LR11000
NSF
Mary
Nic
LabPadre
25.08.2021
New intermittent RC for August 26 (9.30-11.30 am)
New 4-ring barrel section spotted made of 3.6mm steel (0.36mm less?)
B4 work continued; aerocover truss added on external COPVs, aerocovers will mount to these and protect the COPVs from aerodynamic forces during flight
B4 Raptor installation continued; RB4 spotted
According to NSF, the new smooth nosecone is made of 2 rows of strech formed steel, whereas previous cones were made of 3 rows of stamped steel
Two 4-ring barrel sections with lead-ins outside production tents
OLM work continued
OLS, IT: Stairs removed by LR11350
OLS tank farm: GSE1 work continued
Catch arm contstruction proceeded; use of truss section unclear
QD arm work continued
SN20/S20 TPS tiles work continued, still a lot of red labels; new red labels added near aft flap
GSE4 test tank cryogenic proof test; According to NSF, the reason was to validate construction methods used for the OLS tank farm
OLM: Booster quick disconnect delivered to launch site and lifted onto OLM
Unknown 4-ring section lifted into mid bay at 11:05 pm [GSE8?, S21?, B5?]
NSF
Mary
LabPadre
24.08.2021
GSE8 fwd dome on sleeving stand; sleeved with 3-ring section
B4 work in high bay continued
New structures delivered this week (with black beems) still at production site
Coil of stainless steel delivered
Raptor engines prepared for roll out to OLS
Insulated plumbing loaded for transport to OLS
S21 nosecone barrel section (seen already yesterday, 4-ring) in tent 3 spotted
Work on new wider high bay "super hb" foundation continued
Work on new smooth nosecone continued
Triangle-stand now called "Booster inner engine thrust simulator" by NSF
GSE7 in mid bay, pipes partly attached
New ship or tank section with lead-ins spotted in mid bay [GSE8 or S21??]
Pipes delivered to production site
OLM work continued
OLS, IT: work continued, more pipes being added; "The concrete fill pipe has been extended to columns of section 2 of the OLIt meaning Section 1 columns are now filled with concrete"
OLS tank farm: work on GSE1 continued through upper access hole
Catch arm work continued
QD arm work continued, more pipes installeed
Raptor installation on B4 in high bay continued; RB26, RB6, RB27 spotted
Circumhorizontal arc over Boca Chica
NSF
Mary
LabPadre
spoilt-sport
23.08.2021
GSE4 [test tank?] rolled out to launch site, arrived at 10.23 am
RC for August 24 canceled
OLS, IT: Work continued
QD arm work continued
Catch arm work continued
OLM work continued
New structures spotted at production site
New orange production robots delivered to production site
Tent 3: 3 nosecones and one barrel section visible
PPS: Cryo tank shell #7 still attached to crane, looks more or less finished
GSE4 test tank [?] rolled out to launch site; towards SoLS Pad A
SN20/S20 TPS tiles work continued
Three Raptor engines delivered in front of high bay; RB17 and RB20 spotted; engines likely began to be installed
Smooth new nosecone section still missing a piece
RC for August 24 canceled
NSF
Mary
LabPadre
22.08.2021
OLM welding work
Cryo tank shell #3 remained attached to LR11000
Catch arm work continued; a lot of scaffolding around it
SN20/S20 still with a lot of labels on TPS tiles
QD arm work continued; more feeding pipes installed
GSE7 apparently fully stacked in mid bay
Black painted triangle-stand now called "Thrust sim stand" by NSF; work on it continued
Ring section spotted, marked "Not for flight use*
Smooth nosecone work continued
OLS, IT: work continued; QD arm hinges visible
S21 fwd flap "flap py - studded" arrived at tent 4
NSF
Mary
LabPadre
21.08.2021
B5 aft dome booster section spotted (3-ring)
New black structure at build site [see vid 19]
Nosecone section outside tent 2 (lowest nc ring)
More concrete torn out for new wider high bay foundation
New "smooth" nosecone spotted with fewer panels spotted
GSE7 attached to crane in mid bay
SpaceX cat spotted
OLS, IT work continued; possible QD arm attachment point spotted on the south-west side, left of OLM [RGV] on segment #5
Catch arm work continued
B5? fwd tank #2 booster section (3-ring with lead -ins) spotted
Plumbing transported from build site to OLS
QD and catch arm work continued
LR11000 and load spreader attached to cryo tank shell #3 at most southwestern position; to be lifted over GSE6
B6? thrust puck spotted
NSF
Mary
LabPadre
RGV
20.08.2021
S21 sleeved aft section lifted off from sleeving stand
Small GSE tank stacked with GSE4 aft section (3-ring and dome) and GSE4 fwd section (1-ring and dome); purpose unknown
Concrete north of high bay broken up, presumably for new wider high bay ("Super high bay")
Work on triangle-stand continued
Aditional parts lowered into 4-ring stack at PPS
Work on grey circular booster test stand continued
New stand (simple, black, circular) constructed
OLM work continued; water deluge nozzles spotted between hold down clamps of OL platform [RGV]
QD arm strengthened; line boring a quick disconnect arm hinge
Catch arm work continued
LR11000 moved to OLS tank farm
OLS, IT: work continued
OLS tank farm: new equipment/pipes installed
RB24 engine delivered
Small GSE tank work continued
New intermittent RC for August 23 (9-11.30am)
NSF
Mary
LabPadre
RGV
19.08.2021
I-Beam transported at build site
S21 aft dome sleeve (3-ring) spotted
GSE4 aft section on a stand (sleeved with dome, 3-ring, with lead-ins)
Work on triangle-stand continued, painted black
Two raptor engines delivered [RC]
B4 work in high bay continued
Catch arm work continued, more upwards facing pipes attached; work on catching mechanism
QD arm work continued; readied for installation on OLS, IT
OLM work
OLS tank farm: pipe work
SN20/S20 still attached to LR11000, still a lot of green and red labels on TPS tiles
S21 aft dome prepared for lifting; lifted on stand; sleeved with 3-ring aft stack
New structure with black beams at the build site
SN20/S20 disconnected from LR11000 at 3.08 pm
Cryo delivery (nitrogen) to OLS tank farm at 3.40 pm
Outline of new high bay visible [RGV]
Jib pieces for LTM1250 crane delivered
NSF
Mary
LabPadre
RGV
18.08.2021
RCs for August 19 and 20 canceled
At least two Rvac engines that were installed on SN20/S20 left Boca Chica
Musk: fwd flap design error and changes announced
B4 work in high bay continued
Starship aft section moved (3-ring); will be used for fit test on a stand; moved to PPS
Stand mounting points prepared at PPS
Aft section lifted and placed onto stand at PPS [stand next to the stand with yellow railings]
OLM work continued
SN20/S20 still hooked to LR11000
Work on black catching arm continued
OLS, IT; pipes continued to be installed along the outside of the tower; grey metal extension on segment #1 has been added again
QD arm work continued [the yellow/black arm]
BN3/B3 LOX tank still on pad A
New RCs for August 24-26 (5-11pm)
3.6mm 304L stainless steel delivered
NSF
Mary
LabPadre
17.08.2021
OLM work continued
LR11000 moved from SoLS pad A to pad B
B3 dismantling work continued
SN20/S20 prepared for move to SoLS pad B for testing (ambient and cryo proof/pressure testings expected); work through access hole
Catching arm for OLS, IT continued
QD arm work continued
GSE2 being worked on
High bay bar work continued
B4 work continued in high bay, external box has been added [?]
B5 aft dome sleeve (3-ring) spotted
New trinagle stand structure continued to be worked on
SN20/S20 moved towards pad B; lifted onto the pad by LR11000 (6:13pm)
Berm extension and berm tunnel spotted; possibly on the south side of OLS tank farm [RGV]
NSF
Mary
LabPadre
RGV
16.08.2021
B3 LOX tank attached to LR11000 for further scrapping
Work on triangle-stand continued
Possible inner booster thrust simulator at PPS [the one from Pad B???]; moved towards triangle-stand
PPS: Booster thrust sim [grey circular structure] attachment clamps installed
Unknown structure [black stand with yellow railing] loaded onto SPMT at PPS; moved around
GSE tank dome outside tents
B4 work in high bay continued
SN20/S20 work on raceway (electrical wiring) continued
Work on possible booster catch arm and QD arm continued; insulated plumbing installed at QD arm
Pipe delivered to launch site
Todays RC canceled
Tomorrows RC canceled
OLS, IT: Cryo pipe installation has begun
NSF
Mary
LabPadre
15.08.2021
BN3/B3 scrapping continued; CH4 tank further cut into parts
SoLS pad B work continued
QD arm work continued
Catch arm (black pipes) continued to be worked on, especially on upwards facing arm
GSE1 and GSE2 still have scaffolding going up to access hole as well as internal ventilation
OLM work continued, now completely painted grey
PPS: Cryo tank shell work continued
B4 work in highbay continued; dents have appeared and disappeared again as the booster expands and contracts (normal)
OLS, IT: Exterior cladding beginning to be added on segments #1 and #2
SN20/S20: TPS tiles work continued; also some work on external wiring
SN20/S20 work continued during the night [vid 16]
OLM and OLIT work continued during the night [vid 16]
Catching arm work continued; mounting points added [vid 16]
NSF
Mary
LabPadre
14.08.2021
BN3/B3 attached to LR1100 with spreader bar
GSE aft dome spotted (3-ring with dome); GSE8?
B4 work continued in high bay
Stand with triangles work continued at PPS
GSE7 nearing completion in mid bay; more pipes have been attached
Booster thrust simulator: more parts added
QD arm work continued
Lift and catching arm work continued
BN3/B3 began to be scrapped; cut in half; upper segment lowered
OLS tank farm: more pipes attached for horizontal tanks
OLM/table work continued
NSF
Mary
LabPadre
13.08.2021
PPS: Cryo tank shell #7 work progressed; stacking complete
B4 work in high bay continued
SN20/S20 prepared for roll out
S21 aft dome moved into production tent
QD arm work continued; some propellant seem to have been installed
Tower arm (catch arm) work continued
OLS, IT: New parts lifted; taken down again; new pipes at segment #1 installed; scaffolding continued to be removed
OLM/table work continued
SoLS Pad B thrust ram removed (without being used), moved to build site at 12:47am SN20/S20 a lot of TPS tiles removed from nosecone barrel section
SN20/S20 moved back to launch site; arrived at 11:57am
Boom lifts moved to launch site
GSE6 lifted by LR11000 and placed west to GSE3/Shell#4
Coil of stainless steel delivered
Diverse deliveries to the build site
FCC report for Starlink operation for ground testing on Starship
LR11000 moved towards pad A
OLS, IT: Scaffolding installed for QD arm installation
New RCs: Intermittent RC for Aug 16 (9am-1pm); RC for Aug 18&19 (5-11pm); RC for Aug 20 (6am-12pm)
NSF
Mary
LabPadre
12.08.2021
SN20/S20 TPS tiles inspection/repair work continued; blue markings "E1", "E2" seen
S21 aft dome spotted
S21 legskirt spotted (2-ring); label still "SN"
OLS; work on QD arm and tower arm continued
Work on potential booster test stand with triangles continued
SN20/S20 TPS tile replacement began
B4 work in high bay
OLM work continued; a work lift has been installed [day unclear]
OLS, IT; scaffolding being removed
B4 Raptor engine removal continued
Grove GMK5275 crane arrived in Boca Chica
Liebherr crane parts arrived [?]
New intermittent RC for August 13 (9.30am-12pm)
NSF
Mary
LabPadre
11.08.2021
B4 rolled back to build site on two SPMTs; during the transport, the booster was kept pressurized; moved into high bay
GSE6 rolled out to the OLS tank farm; both met near the road block
SN20/S20 moved out of the high bay to prepare it for B4; positioned outside mid bay
Methane transfer tubes (downcomers) delivered to build site
Two Raptor eninges loaded onto Raptor van
Potential booster test stand with triangles work continued; purpose yet unknown; more plates added
Booster thrust ram/simulation (grey circular structure) work continued
Caged ladder moved around
SN20/S20 work on TPS tiles continued (labels)
GSE7 aft dome sleeve (3-ring) spotted
B4 Raptor engines began to be removed
OLS tank farm: Cryo shell #4 lifted with LR11000, placed over GSE3 at 1:50pm (southeastern location)
GSE6 hooked to LR11000
NSF
Mary
LabPadre
10.08.2021
B4 prepared to be lifted from OLM
B4 removed from OLM at 7:45 am by LR11350; detached from crane/load spreader at 3:06 pm
SN20/S20 more colored labels attached to TPS tiles
PPS: Cryo tank shell #7 stacking continued
B5 comm dome sleeve (4-ring stack) and fwd tank #2 (3-ring stack with lead-ins) spotted
Top platform added to circular structure with triangles
OLS tank farm: work on GSE1 and GSE2 continued
Work on black pipe structure (tower arm) and yellow pipe stucture (quick disonnect arm, confirmed) continued
Stainless steel roll delivered
GSE8 fwd dome stack #2 spotted [GSE8 will replace the scrapped GSE4)
New intermittent RC for August 11 (7am-12pm)
GOA's decision deniying the HLS protests by Bluo Origin and Dynetics released; confirming SpaceX's concept of operations, involving 16 total launches each 12 days apart and three different categories of Starship (HLS lander, tanker, undisclosed variant [DELETED])
NSF
Mary
LabPadre
09.08.2021
SN20/S20 more TPS tiles marked
Cryo tank shell #4 LOX rolled out to launch site; SpaceX label: "Outer Shell#4 LOX"; slated for most southeastern GSE tank [GSE3, see August 06]; load spreader and LR11000 attached to the shell
GSE2 work continued
Weather balloon released near production site
PPS: huge tanks still packed in blue plastic
New intermittent RC for August 10 (7am-12pm); later canceled
BN2.1 placed on a concrete stand at PPS
NSF
Mary
Jack
LabPadre
08.08.2021
B4 work for preparing to remove it from OLM
B4 attached to LR11350
OLM legs are being painted grey
SN20/S20 colored labels attached to TPS tiles, likely to indicate damage that needs repairs
Deck installed on possible raptor installation platform
PPS: Cryo tank shell stacking continued on shell #7 (likely final shell)
BN2.1 inspection work
Hydraulic rams installed on a new potential raptor thrust sim
GSE7 fwd tank section ready to be stacked on aft section; hooked to crane in mid bay; later both parts were stacked together; now likely full hight
Work on new stand like structure with triangles continued
Work on black/yellow structure continued; now NSF calles is the "quick disconnect arm" which "will load propellant into Starship prior to launch"
OLS tank farm continued to be worked on
NSF
Mary
LabPadre
07.08.2021
GSE7 in mid bay, outside pipes apparently already installed
GSE6 still at production site [!]
Work on a test stand like structure at PPS
New parts delivered to production/build site; some parts from McGregor arrived
Lower bulkhead for Superheavy booster spotted [B5?]
S21 nosecone spotted in tent 3
PPS: Cryo tank shell construction continued: shells #3-6 likely complete; shell #7 likely more than 10 rings tall
SN20/S20 Rvac engines removed and moved around
SN20/S20 Sea level raptor engines removed
B4 reattached to LR11350
Work on black and yellow pipe structures continued
GSE? section (6-rings) attached to crane/load spreader
NSF
Mary
LabPadre
06.08.2021
SN20/S20 more TPS tiles installed
OLS, IT; OLM; OLS tank farm work continued
SN20/S20 stacked onto B4 by LR11350, fully assembled rocket for the first time ever!!
SN20/S20 removed from B4 by LR11350 after first fit check for final construction, touch-down at 9:45 am
SN20/S20 moved back to build site; into high bay; hooked to bridge crane
Time for today's RC changed to 11.30am-2pm
GSE3[?] lifted over the tank farm and lowered onto OLS tank farm foundation; placed at the most southeastern foundation
GSE3[?] detached from load spreader after being lifted into place by LR11000
Musk: different new information
New intermittent RC for August 09 (7am-12pm)
NSF
Mary
LabPadre
05.08.2021
SN20/S20 and GSE6 [NSF]/GSE3 [LP] rolled out to OLS [apparently it was GSE3, vid 07]
Black and yellow tubular structures continued to be worked on
GSE5 sleeved with a cryo shell [the one in north-eastern position]
B4 detached from LR11350
SN20/S20 attached to LR11350
New intermittent RC for August 06 (9.30am-12pm)
SN20/S20 lift scrubbed due to high winds
NSF
Mary
Jack
LabPadre
Musk
04.08.2021
SN20/S20 nosecone lifted into high bay; stacked at 4:11 am
B4 CH4 tank condensation at 3am
B4 attached to LR11350 load spreader
B4: GSE hoses detached ahead of lifting
B4 lifted onto OLM by LR11350 in a very careful manoeuvre
Musk: Mechzilla (OLIT) not yet ready, but for future rockets
SN20/S20 unhooked from bridge crane, now fully assembled!
NSF
Mary
Jack
LabPadre
03.08.2021
Standard TFR renewed for covering ground testing such as cryogenic and staic fire tests (5000ft, until August 31)
Work on SoLS pad B continued with some welding
SN20/S20 work continued outside high bay
B4 detached from high bay bridge crane
New intermittent RC for today (9:30am-3pm)
B4 roll out to OLS, near OLM
Musk infos about catch mechanism on OLS IT
FCC/Starlink update [Sheetz]: up to 400 satellites per launch on Starship (vs 60 per Falcon 9)
RV5 and another RVac engine moved towards Starship SN20/S20 likely for a fit check
SN20/S20 moved into high bay ahead of nosecone stacking
OLM work continued
New intermittent RC for August 05 (6:30-9am) canceled
Everyday Astronaut interview with Elon Musk
SN20/S20 nosecone moved and stopped just outside lowbay, more TPS tiles added; later moved to high bay for stacking as well
SN20/S20: all six Raptor engines (3SL, 3Rvac) have been installed [Musk]
NSF
Mary, Jack
LabPadre
E. Musk
02.08.2021
RC74,64, RCxx, RCxx, RCxx, RC65, RB22 installed on B4
B4 work in high bay continued on mating the two halves
B4 had 29 Raptor engines installed in just one night
SN20/S20 nosecone: TPS tiles installation continued
SN20/S20 rolled out of mid bay, nearly fully covered with TPS tiles on one site (still some needed near the section welds)
SN20/S20 aft flap installed (with TPS tiles)
GSE3, GSE6 work continued
Stainless steel coil delivered
PPS: [not launch site] concrete poured
OLS tank farm: Work on GSE1 and GSE2 continued
LR11000 and LR11350 detached from OLM platform
LR11000 moved back to OLS tank farm
OLM welding work
Yellow pipe structure growed
Blcack pipe structure welding work continued
SN20/S20 second fwd flap installed, second aft flap installed
NSF
Mary
LabPadre
01.08.2021
B4 more grid fins installed
Fit check of B4 on OLM NET Tuesday [Musk]
Black tubular structure work continued
Yellow pipe/tubular structure work continued
OLM: work on attaching the platform on the legs
GSE2 work continued
BN3/B3 still on pad A, plans unclear
RB engines arrived from (RB17, RB18, RB9, RB21, RB22)
S20/SN20: first forward flap attached to nosecone; smaller sice visible; work on the TPS tiles installation continued
Stainless steel coils delivered
GSE3 and GSE6 work at production site continued
New pipes for black tubular structure arrived
RB
B4 LOX tank moved in high bay and work platform installed ahead of final stacking
B4 CH4 tank lifted by high bay crane and stacked onto LOX section; final stacking; met at 4:37 pm
B4 Raptor engines roll out in this order [where?]: RB7, RB2, RB3, RB15, RBxx, RBxx, RB9, RB21, RB19, RB18, RB4, RB6, RC74, RC79, RC58, RB8, RB11, RB14, RB20
B4 raptors installed late night: RB7, RB2, RB3 pictured; at least 14 Raptors already installed as of 1:20 am of August 02 [?!]
NSF
Mary
LabPadre
Date
Description
Source
Link
31.07.2021
SN20/S20 nosecone stacked onto barrel section at wind break; quadratic TPS heat shield tiles spotted near the flap attachment rig; lead-ins removed after the two parts have been welded together
More black tubular structures delivered (see July 20, 24, 27, 29)
Yellow pipe structure work continued, now getting higher; could be a lift sliding up and down the OLS IT
GSE6 work at build site continued
Plating from booster thrust simulator mount at PPS removed
SN20/S20 tank section work in mid bay continued
Rvac engine delivered (after another delivery last night, at least three on site now, fourth wasn't unloaded yet)
OL platform / table lifted by LR11350 and LR11000 onto OLM legs!!, touchdown at 1:46 pm
The OL platform has 20 hold down clamps installed
Several more Raptor engine deliveries
Musk: Possibly steering away from traditional grid fins in the future to something with more drag
Musk: OL platform weighs 370 tons
SN20/S20 first aft flap installed in mid bay
NSF
Mary
LabPadre
30.07.2021
Yellow pipe structure work continued; getting really huge
Black pipe structure attached to crane
OLM preparation work continued; work at the base of its legs
LR11000 crane moved towards OLS, IT/landing pad after shortly leaving the OLS onto hwy 4
PPS: Cryo tank shell construction continued with shell #6 looking nearly complete (some 2-3 rings short) but still attached to crane; shell #7 stacking began with first section (dome+ring) stacked onto another section
New brick building behind mid bay
B4 thrust section /aft dome section (3-ring with lead-ins) moved into high bay; stacked with LOX section later
SN20/S20 nosecone: TPS tiles being installed; aft flaps moved near tents
B4 stacking continued in high bay, methane tank section looks to be complete (13 rings) and LOX tank as well
Ship aerocover unloaded (SN20?)
New container wall being built at launch site
B4? grid fins spotted
B4 methane tank moved out of high bay; moved back later
B4 grid fins installation on methane tank section began
NASA/GAO: Denies BO and Dynetics protests of HLS contract awarded to SpaceX
New intermittent RC for Monday, August 02 (3-7pm)
WAI/RGV: Work on new pads and concrete foundations at OLS with rebar laid (near landing pad, at OLS tank farm and staging area, terminal for trucks for fuel delivery, around/north of OLM)[312]
LR11350 and LR11000 moved into position for OL platform lift [vid 31]
B4 first grid fin installed on upper methane tank section [vid 31]; apparently they can't fold (confirmed by Elon Musk)
Rvac engine delivered [vid 31]
NSF
Mary
LabPadre
Michael Sheetz
WAI/RGV
29.07.2021
B4 fwd #4 section ready for stackign (4-ring with lead-ins)
Nosecone with blankets and TPS tiles rolled outside tent (likely for SN20/S20)
GSE5 has been detached from LR11000
OLM readied for installation of OL platform (table) with scaffolding being installed
LR11350 disconnected from IT, stacking of the tower appears to be complete
OLS: concrete work
New Raptor engines arrived at launch site
SN20/S20 aft flap installation rig moved inside mid bay and affixed to the ship for flap installation
Work on GSE3 and GSE6 continued at production site
Concrete forms placed in a circular stand like shape at the build site
Work on grey circular structure continued at PPS
B4 methane tank stacking continued with top 9-ring stack (fwd) stacked onto another section (fwd #4), methane tank section looks completed now
Another black pipe structure delivered to OLS (see July 20, 24, 27)
Grate lifted onto OLS, IT by LR11350
Fwd flap delivered to build site (SN20?)
NSF
Mary
LabPadre
28.07.2021
OLS, IT: Segment #9 with a winch wheel lifted by the LR11350 crane with an American flag after a huge winch extenseion has been added instead of a fourth column; slowly lowered onto segment #8
GSE5 transported to OLS by two SPMTs
OL platform transported to OLS by two SPMTs after some scaffolding has been added on it
GSE2 detached from LR11000
GSE5 lifted into place at OLS tank farm by LR11000 right to the east of GSE1
Two RBoost and two SL Raptors have been delivered
B4 thurst dome has been flipped
B4 methane tank stacking: 6-ring fwd section attached to high bay crane and stacked to another 3-ring stack (now 9 rings tall)
NSF
Mary
LabPadre
27.07.2021
B4 methane transfer tube "downcomer" installed early in the morning
OLS, IT: Work on segment #9 continued, with an intermediate floor and black winch wheels being installed (5th pulley has been installed); later LR11350 and load spreader attached to the segment
Gravel delivery to OLS
OLS: work on yellow pipe structure continued
More large black pipes arrived at launch site (see July 24, July 20)
PPS: work on cryo tank shell #6 continued, now likely full height
OL platform work continued, some parts have been painted
Raptor engines delivered to build site (likely those earlier removed from BN3/B3)
GSE3 and GSE6 now again labelled as those being place more north
GSE5 moved
GSE2 work continued
B4 LOX tank section inside high bay ahead of stacking
New intermittent RC for Wednesday, July 28 (9-11am)
BN3/B3: GSE pipes for fuelling disconnected
WAI internal SpaceX info: B4/S20 [SN20] ready on OLM by August 5th as internal goal![316]
NSF
Mary
LabPadre
WAI
26.07.2021
B4 stacked with fwd 5 section (4-ring), now 20 rings tall (~37m) at 12:50 am
B4/B5? downcomer pipe spotted
OLS, IT: Segment #9 third and fourth pulley installed
SpaceX: 100th build of a Raptor engine complete (RB16)
GSE3? work continued [isn't this GSE5]
Work inside GS*3
Test nosecone used in the cargo bay pathfinder scrapped
Work on a transport stand at PPS
OL platform work continued, more parts delivered
Stainless steel roll delivered
OLM: Scaffolding installation continued
GSE1, GSE2: Installation of stringers for strengthening of the tanks continued; GSE2 still attached to LR11000
Hwy4 repaving work continued, milling machine tearing up the highway
OLS, IT: Segment #9 work continued, new equipment lifted into it
Work on yellow pipe structure (possible fuelling arm) continued
Brick work at high bay base continued
GSEs: GSE3 infront of high bay, GSE5, GSE6 a bit north (according to NSF; not congruent with previous information!)
GSE3 has stringers already installed
Possible B5? thrust dome outside tents
Nosecone barrel section with TPS base layer (for SN20/S20?) lifted into windbreak
Nosecone with TPS base layers being worked on in tent 3
Raptor vacuum mount and thrust puck for starship delivered
Possible GSE tank 4-ring section with lead-ins moved into high bay
NSF
Mary
LabPadre
25.07.2021
Pesticide spray plane flying low over starbase against mosquitos
B4 aft 5 (4-ring with lead-ins) outside high bay
B4? aft dome sleeve outside tent 1 (3-ring); later hooked to crane and flipping jig, flipped
OLS, IT: Segment #9 work continued
GSE6 (13-rings) rolled out of high bay near GSE3, pipes not yet fully installed?
GSE5 work continued
Nosecone barrel section prepared for TPS tiles, with lead ins, possibly for SN20/S20
PPS: Cryo tank shell work continued; Shell #6 (13-rings) lifted and stacked on another 4-ring section; shells #3-5 looking quite finished
OLS tank farm: work on GSE1 and GSE2 reinforcements continued
OLM: Worik platform? installation continued
SoLS, pad B: third thrust ram for RVac installed
SN20/S20 work in mid bay continued with several man lifts up
B4 aft dome/thrust dome placed on sleeving stand
SoLS tank farm venting a lot; WAI suggested possible OLS tank farm GSE tanks test as both are connected
NSF
Mary
Stephen
LabPadre
WAI
24.07.2021
B4 stacking continued in high bay, now 16-rings tall
OLS, IT: Parts for suspected IT carriage delivered to launch site
2 Raptor engines delivered, RC, RB; three engines (RC62 identified) loaded onto truck
GSE7 aft dome sleeved (3-ring plus dome); GSE7 stack #2 fwd dome sleeve (2-ring) spotted
GSE6? work in high bay continued
PPS: Cryo tank shell construction continued on shells #5 and #6, according to Brendan shell #7 commenced with dome stacked with first ring
Work on circular grey structure continued
OL Platform work continued, pipes have been installed
More large black pipes/tubular components delivered to launch site (looking the same as spotted on July 20)
OLS, IT; Work on base continued, equipment added to segment #1; segment #9 construction continued with a large beam being added
Yellow pipe structure work continued
OLM: work platform installation began
GSE1 and GSE2 reinforcement work continued
Liquid nitrogen delivered to OLS tank farm !!!!
B4? fwd dome placed on sleeving stand
Super heavy booster aft dome work in tent 1 continued
Delivery to SoLS tank farm
GSE3 moved north
Reinforced barrel section flipped ahead of stacking (no dome inside)
B4 fwd sleeve flipped at 3:35 pm
Elon Musk: Bigger highbay to be constructed later
NSF
Mary
LabPadre
23.07.2021
RC57 moved to launch site
SN20/S20 tank section now fully stacked
RC62 removed from BN3/B3 at 2:22 pm, moved to build site
Special yellow pipe section with pivot points for a possible GSE arm delivered at 2:24 pm; work on structure continued
GSE6? aft dome section (3-ring section with dome and lead-ins) outside high bay, lifted into high bay
Superheavy booster thrust dome in tent 1, another one as well (likely earlier in the production process)
Nosecone moved from scrapyard to rear of production tents; TPS tiles on aerocover
SN20/S20 under construction in mid bay (at least 16 rings tall)
GSE5 pipe work continued
New barrel section prepared for stacking (lead-ins installed)
Welding work on a transport mount
Grey circular structure work continued; potential Super Heavy outer ring thrust ram or a Max Q simulator
PPS: Work on cryo tank shell #6 continued
New barrel section (4-ring) attached to crane and lifted into mid bay, possibly beginning GSE7
Brickwork added to the base of high bay
Stainless steel roll delivered
Pathfinder nosecone with barrel section moved out of windbreak, payload bay has been cut into leeward side, hooked to crane; tip of nosecone cut off, likely going to scrapyard - New payload door design with conventional side doors instead of previously suggested mouth like opening? [WAI][321]
SN20/S20? nosecone with TPS mount points in tent 3
Work on SoLS Pad B continued with new black structures being installed (RVac puck shucking hydraulics)
A lot of black small pipes delivered to launch site
OLS, IT: Segment #9 assembly continue
Liquid nitrogen delivered
GSE2 reinforcement work continued, still attached to LR11000
PA system on top of tank
Concrete work near Starhopper (SH)
B4 aft 4 outside high bay (4-ring with lead ins)
NSF
Mary, Stephen
LabPadre
WAI
22.07.2021
OLS, IT: Segment #9 or #8b assembly began at the launch site with columns set into place by PBI 12000-1 crane and cross beams added
SN20/S30 thrust section (5-ring section) moved into mid bay, connection point for GSE fuelling arm visible for the first time
Elon Musk: narrower and lighter flaps
OLS, IT: Work on the base continued and roof of winch room; also some work at a column of segment #2
Yellow pipe structure: welding work continued
OLS: Work at new concrete pad continued
OLM: Work continued
GSE2: Scaffolding erected at the base, access hole opened
BN3/B3 top dome venting; work at the engine section; RC59 removed, packed and transported back to the build site
GSE3 moved out of mid bay towards high bay, near GSE5
GSE6 hooked to high bay crane
Grey circular mystery structure work continued
OL platform work continued
Super heavy booster aft dome being worked on in tent
RC57 removed from BN3/B3 at 11:54pm
11:16 pm: first cargo door was cut out and removed from pathfinder nosecone
NSF
Mary, Stephen Marr
LabPadre
21.07.2021
B4 stacking progressed in high bay, aft tank #2 has been stacked (at least 10 rings tall now)
Hydraulic cylinders delivered and installed on grey circular mystery structure (lifted by Grove ORT 8100 crane), likely all around the structure
Grey circular mystery structure: piping installed
PPS: Rebar laid for a new foundation
GSE5 work outside mid bay continued, more pipes installed
PPS: Work on cryo tank shell #5 and #6 continued
Stainless steel loaded onto truck
Aft dome now sleeved (likeyl made out of scrapped parts)
Booster aft dome without thrust puck near the tents; status unclear
Storm in Boca Chica
OLS tank farm: GSE2 attached to LR11000
Concrete work between the two berms towards OL tank farm
Work on yellow pipe structure (some black pipes visible too) continued
Generators delivered
New sections of the black piping at launch site lifted
BN3/B3 lower LOX tank hatch closed
NSF
Mary, Stephen Marr
LabPadre
20.07.2021
BN3/B3 wok continued (inspection of raptors and aft section)
Two white/blue cranes drove to the launch site
Genie SX-180 crane (blue) sptted at launch site; yellow grove crane driving around
PBI Manitowoc 12000-1 crawler crane boom has been lowered previously
OLS, IT: Work on winch room continued
Aft dome lifted onto sleeving stand [tag ripped off, someone noted B2.1 on it, BN2.1], sleeved with a super heavy aft ring stack, likeyl to practice dome mating with scrapped parts
RB2 (raptor boost 2, named "R2B2") arrived
OL platfrom work continued, possible hold down clamps installed [?]
OLS, IT: Load spreader detached from segment #8, LR11350 moved back, load spreader lowered
OLS: New concrete rebar between the two berms towards OLS tank farm
Black steel structure delivered to launch site
Huge black pipe structure delivered and lowered into place at launch site [possibly someting to do with the yellow pipe structure?)
OLS, IT: Three single-hight columns for segment #9 delivered to launch site by SPMT (possibly to be lifted individually), fourth column, smaller than the other three, delivered later at 1:42 pm
Ship [S20?] aft flaps spotted on a stand, with TPS covering; likely some 30% smaller than previous
Grey circular mystery structure work continued at PPS
The black stand with yellow railing still standing around
B4? aft dome (3-ring stack or sleeve) spotted
B4 aft 4 (4-ring with lead-ins), B4 aft 5 (4-ring with lead-ins), B4 fwd 4 (4-ring with lead-ins) ready
GSE tank ring stack (4-ring with lead-ins) spotted
GSE5 work continued, more pipes attached
GSE3 work continued in mid bay
B5 "aft dome" sleeve (unfinished) spodded
OLS: staging area foundations for starship and superheavy progressed
NSF
Mary
LabPadre
RGV
WAI/RGV
19.07.2021
OLS, IT: LR11350 still attached to segment #8
OLM work continued (or inspection)
OLS: concrete work at landing pad
Unknown piping delivered to launch site and attached to crane
Work on yellow pipe structure continued
Liquid Methane delivered
PPS: Cryo tank shell construction continued with stacking of GSE shell #6 (dome with top ring stacked onto a new segment)
Transformer delivered
GSE5 work continued outside of mid bay with more pipes being installed
GSE3 and S20 still in mid bay; work on S20 continued
Grey circular structure at PPS: welding work, some brown metal/steel parts have been added recently
Black stand-like structure with yellow railing lying around
OL platform work continued
Booster aft dome sleeve (3-ring section) spotted [B4?]
GSE fwd dome sleeved (with 2-ring stack) [GSE4/GSE6?]
BN3/B3 static fire
NSF
Mary
LabPadre
18.07.2021
OLS, IT: Segment #8 detached from and reattached to laodspreader at least 3 times in order to balance the load for liftting (due to one column being taller); crane turned to move the segment closer to tower ahead of stacking; then lifted by LR11350 and stacked to tower; extension platform looking towards OLM
Alert notice for July 19 for Static Fire attempt on BN3/B3 issued (12-10pm)
NSF
Mary
LabPadre
17.07.2021
Work on Starship thrust ram installed on SoLS Pad B
OLS tank farm work continued, pipes moved
OLS, IT: Two parts of electrical conduit lifted inside tower by LR11350; segment #8 work continued
Rebar laid for new concrete pad between landing pad and blast berm
Potential B4? aft section (3-ring) hooked to flip rig and flipped; no dome installed yet inside!!
Raptor engine delivered
New equipment delivered to build site "HYM-211, TLH_Axial 11"
Work on a GSE tank inside mid bay (not GSE6? or GSE4?), GSE3 fully stacked inside mid bay [?]
Grey circular mystery structure work continued with a parts lifted into it
Black stand like structure work continued
Hydraulic rams loaded onto Flatbed truck
GSE5 moved out of high bay, now waitng outside
Work on a nosecone barrel section with lead-ins outside tent 3 and low bay
Ship aft dome laying around near PPS
PPS: Cryo tank shell #5 nearly fully stacked now (the 6th of eight 12-m tanks)
GSE tank aft section (3-ring with dome) moved [GSE4/GSE6?]; label, likely outdated, mentioning B4: "BN4 aft dome stiffed panel"
OLS, IT: Roof installation on winch room continued
OLS, IT: Segment #8 attached to LR11350
Pieces possibly for catching and lifting system delivered to build site
NSF
Mary
LabPadre
16.07.202
B4 work in high bay continued
Nosecone moved to scrapyard (previously infront tent 3)
PPS: Grey circular mystery structure work continued; black stand like structure work continued
OLS tank farm progressed with new GSE installed; control panels spotted; white tanks (possibly for compressed helium/nitrogen) moved around
SN20/S20? aft flap with TPS tiles spotted; the first time with curved tiles like this [!]
OLS, IT: Roofing installed on tower winch room [east and south side base extension]
OLS, IT: Segment #8 prepared for stacking
Yellow pipe work continued
Liquid nitrogen delivered to SoLS tank farm
Pipe parts delivered "Not Cryo cleaned", "Not clean for LOX", "Do not use"
OL Platform work continued
PPS: Second flare stack installed, possibly just temporary solution
B4 aft 4 and B4 aft 5 (both 4-ring stacks with lead-ins) spotted
NSF
Mary
LabPadre
15.07.2021
B4 aft 3 section (4-ring stack with lead-ins) infront high bay
B4 common dome section stacked in high bay [likely with aft #2?]
BN2.1 hooked to crane
PPS: unknown, tall black stucture spotted
PPS: Grey circular mystery structure looking nearly complete
PPS: Cryo tank shell #4/5???? construction work continued, 5-ring section lowereed into scaffolding (official name: "Cryo Shell: 01445452-505 Shell#5, Cryo Shell#4; Item:01445452-535 - TRANSITION QUAD STACK; WO:1687287)[pic: second-lowest 5-ring stack) and the other section (13 rings and dome) stacked onto it
PPS: truss sections delivered
PPS: Flare stack in action; first ignition at 2 am
White pipes delivered
OLS, IT: Part lowered by LR11350; stairs lifted out; segment #8 moved; work on east side base extension continued
OLS tank farm: work at horizontal tanks continued
OLS: Yellow pipe work continued
BN3/B3 work continued
RC for today canceled
New RCs for July 19-21 (12-10pm)
NSF
Mary
LabPadre
14.07.2021
Aft flap delivered [SN20?]
Many deliveries to build site
RB11 (Raptor boost) spotted
SN20/S20 nosecone spotted: new forward flap mounting jig design; lots of TPS pin attachments; four port RCS thruster (vs 3 on previous SNs); superman logo near top of flap mounting jig
Overpressure notice to Mary for today (12-10pm); but testing RC later canceled
SN20/S20 work in mid bay continued
GSE3? waiting in mid bay
OLS, IT: Segment #8 roll out after work on the sideward extension had progressed
PBI Manitowoc 12000-1 crawler crane moved to the launch site
PPS: Cryo tank shell work continued
Unknown black stand-like structure attached to crane
Work on grey circular mystery structure at PPS continued (likely part of the launch mount)
GSE1 welding work
Pad B thrust ram installed for future cryo tests with Starship
Yellow pipe mystery structure continued to grow
Cryo shell load spreader removed from LR11000 and placed on SPMT, returned to build site
B4 fwd 2 section (3-ring stack with lead-ins) spotted
Astronomical/tracking telescope dome spotted
FAA: "The FAA warned SpaceX that, due to the agency's ongoing environmental review, the massive Starship launch tower is yet unapproved and could need to be taken down.
"The company is building the tower at its own risk," an FAA spokesperson told CNBC."; "The FAA's warning to SpaceX traces back to this letter in May, but the company has continued forward with work in the past few weeks"
Overpressure notice issued for July 15th
NSF
Mary
LabPadre
13.07.2021
Second raptor delivered to launch site (BN3/B3) at 2:28 am
Both additional raptors installed until 5:57 am; confirmed to be RC57, RC59, RC62
Lightning appears to have striked SN16
LR11350 lowered for some work and risen again later
OLS concrete work
OLS, IT: East side base extension roof beams added
OL platform work continued with parts lowered into it [hold down clamp?] and a part lifted out
SN20/S20 leg skirt with lead-ins (fewer than with old sections)(2-ring stack) moved; covered TPS tiles attachment pins; lifted onto a mount
SN20/S20 thrust section outside tent 1 (3-ring stack, with access hole)
SN20/S20 thrust section stacked onto leg skirt
GSE tank under construction in high bay [!] at least 5 rings, with dome [GSE5?]
Cryo tank shell #2 lifted by LR11000 onto an empty tank farm stand (most south-western)
RC for today canceled
Intermittent RC for tomorrow added (2-4pm)
NSF
Mary
LabPadre
12.07.2021
Second BN3/B3 raptor, identified as RC59, lifted on 12:10 am local; but moved back to build site later
Cryo tank shell #2 moved to launch site [the other is a water tank]
Some road work on pad A ramp
Ring section likely for TPS tiles testing spotted [NSF: possibly for SN20/S20]
Several deliveries to build site
Booster section attached to flipping jig inside high bay [B4?]; later flipped [vid 13] [why booster; could it be SN20?]
PPS: OLS, IT: Work on segment #8 progressed, special extension added
BN3 work continued
BN3/B3 Cryo proof test
LR11350 6m crane section (old) transported away
GSE5 mid section #2 (4-ring with lead-ins) moved outside high bay [vid 13]
Second Raptor delivered to BN3/B3 at 11:36 pm
NSF
Mary
LabPadre
11.07.2021
Second raptor engine for BN3/B3delivered to launch site at 12:52 pm, unknown RSN
Installation of first engine on BN3 continued (RC57) [Raptor Center]
A downcomer (LOX or CH4) has been moved into mid bay on July 05 at 10:42pm
LR11350 extension work continued with parts added to jig; jig now reattached to boom
LR11350 lifted
PPS: Cryo tank shell #5 stacking continued with top 6-ring section stacked onto another 5-ring section; shell #4 seems still 1-2 rings short
GSE5 fwd dome section outside [inside?] mid bay, at least 6 rings tall now
OLS tank farm work continued
OLM beam welding work continued
SoLS tank farm filled
PPS: OLS, IT: Assembly of segment #8 continued
Black steel boom [?] delivered to launch site
Nosecone in front of tent 3 [the one spotted earlier] hooked to crane and stacked on barrel section; "both sections have tape markings indicating payload door tests" [the_denks]; NSF: "Nosecone 18 going onto SN17's barrel section" [vid 12]
4-ring barrel section infront of high bay; another one in tent [vid 12]
NSF
Mary
LabPadre
10.07.2021
New Superheavy [B4?] thrust puck (for nine engines) delivered
PPS: OLS, IT: First column of segment #9 delivered, along with an even smaller column
BN3/B3 work continued
PPS: Cryo tank shells #4 and #5 work continued
PPS: OLS, IT: Segment #8 work continued
OL Platform work continued
GSE5 fwd dome spotted (sleeved?)
RB6 engine moved inside tent
Hwy4 work continued
LR11350 extension work continued with a white segment inserted into boom (above power boom section)
Next large cylinder (wrapped up in blue) delivered to PPS
OLS tank farm: more plumbing added
Unknown parts delivered to buil site
RC57 delivered to launch site at 6:55pm; installation on BN3/B3 began on 10:13pm
NSF
Mary
LabPadre
09.07.2021
PPS: Cryo tank shell #5 hooked to crane
PPS: Piping lifted into place
GSE3 moved outside of mid bay; moved in again, moved out again
GSE4 fwd dome outside tent 1 for scrapping [!] [it has been already stacked, but now cut off]
Steel parts delivered to production site
New black stand-like structure at PPS
PPS: parts lfted into grey circular mystery structure; circle now complete
OL Platform work continued
LR11350 extension work continued
bN3/B3 work continued with several man lifts up and work through access holes
OLS tank farm: more pipes installed and moved around near horizontal grey tanks
Two huge cylinders delivered to build site
Cryogenic vaporizor (heat exchanger for regazifying liquified gases stored as liquid under cryogenic temperatures) delivered to launch site
Work on booster transport stand (welding)
RC for today canceled
New RCs for Tuesday-Thursday (12pm-10pm)
Tweet by Elon Musk showing 9 raptor engines [RSN27 and RC59 identifiable, at least one RB]
NSF
Mary
LabPadre
08.07.2021
RB5 delivered (Raptor Boost Serial Nr 5)
RC for July 8 changed to 6pm-12am
BN3/B3 venting early in the morning [thrusters or pressure?]
BN3/B3 work continued with several man lifts up ahead of testing
BN3/B3 ambient pressure test
Thrust ram lifted into suborbital Pad B [not yesterday?]
PPS: Cryo tank shell construction work continued (shell #4 and shell #5 with new dome)
OLS Tank farm: more pipes have been installed, scaffolding tent removed
Liquid nitrogen delivered
OLS, IT: work at the base continued (east side base extension, more beams added)
OLM work continued
PPS: Natural gas generators delivered and installed
LR11350 extension work continued
Two nosecones outside tent 3, one with TPS tiles at flap attachment point
Land cleared next to production side (east)
NSF
Mary
LabPadre
07.07.2021
PPS: OLS IT: Segment #8 fourth column lifted at 9:26 am; cross beams added to fourth column; the column has an extension for ninth segment [?]
BN3/B3 work continued through the night
PPS: Cryo tank shell #4 work continued with stacking on next ring section; some first rings for shell #5 appear to be ready
GSE3 (fully stacked) and SN20 (two sections) now in mid bay
Tent 3: new ring section in production (with vertical strengthenings)
Between high bay and tents: Three 4-rings stacks with lead-ins ready for stacking
PPS: Grey circular mystery structure: New parts have been delivered; work continued
OLM work continued (5 man-lifts working simultaneously)
Work on yellow pipe structure continued [for OLS, IT?]
LR11350 boom disconneced and moved away by SPMT ahead of extension
Puck shucker lowered into Test Stand/Pad B at 5:48 pm
NSF
Mary
LabPadre
06.07.2021
PPS: OLS IT: Segment #8 fourth column arrived
LR11350 parts for extension arrived (boom parts and winch)
Single ring section stacked onto 2-ring section infront of tents [SN20/S21 aft section used on June 30??]
OL Platform work continued
BN3/B3 work preparation work continued
OLS, IT: More beams added to east side base extension [white winch likely installed now, see vid July 16]
LR11000 at OLS tank farm; moved new grey tank
Excavator picked up SN11 debris and placed it into scrap bin at launch site
PPS: More ducting installed
OLM work continued at cross beams
High bay top work continued; beam lifted and put into place
New RC [BN3/B3] for Thursday, July 8 (12-8pm); Friday, July 9 (6am-8pm); Monday, July 12 (12-8pm)
Puck shucker moved down hwy4 towards launch site at 11:02 pm
NSF
Mary
LabPadre
05.07.2021
Loadspreader and LR11000 detached from BN3/ B3 at 8:42 am
Inspection robot in tent checked a new ring section (3-ring with lead-ins)
BN3/B3 test preparations work continued with lots of wires and some piping installed; ventilation hoses run into booster
Small berm north of landing pad looking finished
OLM work continued
OLS, IT: More equipment installed on east side base extension
Work on orange pipes continued
Two SPMTs moved under GSE3 tank ahead of potential move; later moved towards entrance/mid bay[?]
OL Platform work continued
LR11000 moved towards OLS tank farm
PPS work continued with ductings lifted into place
High bay roof top work continued, only a few glass panels still missing
Gray circular mystery structure work continued
B4 aft tank #2 4-ring section with lead-ins moved between tents towards high bay area [still labeled BN4][vid 06]
A downcomer (LOX or CH4) has been moved into mid bay on July 05 at 10:42pm [LabPadre, Redstone, July 11]
NSF
Mary
LabPadre
04.07.2021
PPS: Cryo tank shell #4 work progressed; work on cryo tank shell #5 (of 7) began [?]
LR11350 extension work began
OLM: welding at the cross beams
Booster fwd dome [B4?], Starship aft skirt, S21 aft dome infront of tents
Work on a booster? barrel section (3-ring) inside tent 1
Welding work on booster transport stand
OL Platform work continued
Nosecone barrel section and nosecone still ready for stacking infront tent 3
Earth work east of mid bay area
B3 work continued
SN20 mid LOX section with tiles spotted on July 2 during lift into mid bay [Maria Pointer]
NSF
Mary
LabPadre
Maria Pointer
03.07.2021
4-ring barrel section with lead-ins inside high bay, likely with dome in it
SN20 common dome (3-ring stack) with lead-ins and TPS-tile cover spotted (passive pressure relief valve on it); hooked to crane and lifted into mid bay for stacking it onto Mid-LOX section (header tank visible)
3 Raptor engines delivered: RB3, RB4 ("RBoost - Engines without gimbal, with higher thrust and lower throttling ability" [incorrect according to Musk]), sign: "Hello my name is boost"; RC79 (Former RSN79 - RC for Raptor Center)
SN21/S21 thrust dome upgraded
B4 common dome on sleeving stand, sleeved with 4-ring stack ("CMN Dome Stiffend[?] Barrel")
Long tube moved to BN3/B3 at launch site (possibly a part of its raceway)
BN3/B3 work continued, still attached to LR11000
OLS, IT: More beams installed for east side base extension, first equipment installed [winch room in video July 16]
OLS tank farm work continued
PPS: Cryo tank shell #4 work continued
NSF
Mary
LabPadre
Oskar WrĂłbel
02.07.2021
OLS, IT: LR11350 disconnected from tower
LR11350 lowered for third extension RCs for July 6 and 7 cancelled
BN3/B3 secured on Pad A, still attached to LR11000; work at the base/stand; later, man lifts went up, work on booster through access holes
OLS tank farm only progressing slowly at the moment
B4 "comm dome" section (4-ring stack with some small holes in it) spotted
B4? fwd dome section and S21? aft section near each other after stacking test
GSE fwd dome on sleeving stand and sleeved later
GSE4 fwd dome section scrapped: fwd dome and a single ring has been cut off; remaining 4-ring section attached to crane and moved to scrap yard
PPS: Cryo tank shell #4 construction continued with welding
Booster transport stand at build site
High bay roof work continued
At least three nosecones under construction in tent 3
PPS: Work on unknown structure (tall, grey, circular) has progressed; some parts still missing
Work near base of SN15; pressurization rig for starship shown
OL platform work continued
NSF
Mary
LabPadre
01.07.2021
OLS, IT: Segment #7 lifted and stacked
BN3/B3 roll out (36-rings tall, engines won't be covered as with Starship, lowest ring is the aft dome; hot gas thrusters haven't been uninstalled, pipes sticking out of lower section side and huge COPV on other side); huge manlift went up to attach the load spreader of LR11000 to the booster; detached form transport stand, lifted onto Pad A by LR11000 [no engine section???]
New RCs for July 6 and 7 (7am-5pm) [likely for BN3/B3 testing]
NSF
Mary
LabPadre
Date
Description
Source
Link
30.06.2021
Potential starship aft section (2-ring stack) spotted
Potential B4 fwd dome sleeve (3-ring stack with fin attachment structures and thruster holes) spotted, moved outside tent
Deliveries to production site
PPS: Cryo tank shell #4 construction work continued
Three Raptor engines delivered! (RC57 identified)
Stage separation mechanism tested [?] between booster and starship sections: Starship aft section mated with booster fwd section by crane
Nosecone and nose cone barrel section with lead-ins outside tent 3
OLS tank farm work continued, man lifts up and ground piping installed
Berm work continued as well as hwy4 work
OLM work continued, all beams have been attached
OLS, IT: work continued; stairs installed to segment #7, moved towards crane, attached to LR11350
OLS, IT: More beams installed for west side base extension installed
LR11000 began moving towards Pad A, possibly for BN3/B3 lifting
PPS: OLS IT: Segment #8 fourth collumn missing
BN3/B3 work continued, later unhooked from bridge crane
GSE5 mid #2 section (4-ring stack with lead-ins) outside tents
Concrete poured in the base of OLS IT
NSF
Mary
LabPadre
29.06.2021
Super heavy booster transport stand staged next to high bay; later moved into high bay
BN3/B3 lifted onto transport stand; the section is 23 rings tall (engine section, LOX tank, common dome); some sort of fins have been installed on the engine section; lead ins on the common dome section, prepared for stacking
BN3/B3 fwd tank (CH4, 13? rings tall) stacked onto lower booster section; now at full height!
SN15 lift up, some work
GSE tank construction in mid bay
PPS: New grey sections being assembled, forming a circle; pars wore delivered on June 22
PPS: Ground work near propellant production plant
GSE5 tank mid section 1 (4-ring section with lead-ins) in mid bay
New mount sections delivered
OL platform construction work continued
New sign at stargate building
OLS tank farm contstruction work continued
PPS: Cryo tank shell work continued; shell #4 being painted
NSF
Mary
LabPadre
28.06.2021
PPS: Cryo tank shell work continued on shell #4 with stacking the 5-ring to stack onto another section and on shell #3 with welding (now apparently full height)
New barrel section with lead-ins spotted in a tent
IT: Segment #7 roll out to OLS; there appeared to be a slight problem as they needed to stop for a short time, they adjusted the weight distribution/horizontal alignment
OLM work continued, fifth beam added
Pad A modification work continued with support beams added to the super heavy adapter
New berm being constructed from Starhopper entrance gate eastwards (north of landing pad, indicating that SpaceX plans to use the landing pad in the future)
OLS, IT: LR11350 detached; elevator section for segment #5 lifted into place
OLS, IT: More beams installed for west side base extension installed
New RC (with beach) for July 1 (7am-3pm)
FCC: "SpaceX has filed for Starlink terminals to be flown on [orbital] Starship and Superheavy. FCC filing is for August 1st - October 1st." For SpaceX, this is a "logical extension" of the existing authorization to use Starlink on suborbital flights for demonstration
NSF
Tyler Gray
LabPadre
27.06.2021
BN3/B3 fwd tank section moved in highbay; work on booster continued
Celebration/party at Boca Chica with fireworks, party at high bay top
OLS, IT: Sixth tower segment stacked by LR11350 (lifted, crane moved forwards, lowered; guiding weights used); Fifth and sixth segment have no lift installed yet; segment #7 nearly ready for roll out
Pad A work continued
PPS: Cryo tank shell #3 work continued, fully stacked; work on shell #4 had commenced [date unclear]
Sleeved aft dome and new fwd dome sleeve outside the tents
OL platform work continued
S21 aft dome with vacuum raptor engine mounts spotted
First vacuum raptor engine delivered to Boca Chica build site
NSF
Tyler Gray
LabPadre
26.06.2021
Sections of new transport stand delivered
BN3/B3 work on fwd tank section work; the fwd dome spotted earlier this week has been stacked onto other fwd tank section (4-ring); another stack waiting outside
BN3/B3 fwd ring section spotted (4-ring stack)
BN2.1 and stand now near SN15 and 16
GSE tank fwd dome in tent
Pad A: Super Heavy test stand adapter mounted to Pad A, previously used as lower part of BN2.1's stand; according to Elon Musk it is planned to use B3 for testing on Pad and make a new booster for flight
Hwy4 roadwork continued; foundations laid for new berm from starhopper entrance eastwards
OLM: 4 of 6 curved cross sections now added
Staging areas for SH booster and Starship spotted next to the integration tower (one 6-column foundation, one 12-column foundations; both with quadratic pad with rebar) [RGV]
NSF
Tyler Gray
LabPadre
25.06.2021
BN2.1 and its test stand moved from launch site to build site (near SN15 and SN16)
Work on Pad A, preparation for Super Heavy testing
OLS, IT: segment #6 attached to LR11350
OLS, IT: first beam for west side base extension installed
PPS: Cryp tank shell #3 work continued
PPS: OLS IT: Work platforms added to segment #7
OLM: Second, third and fourth beam added between pillars (of total 5)
Work on a ring stack with lead ins
Round metal? parts delivered
New S21[?] thrust/aft dome sleeved (3-ring stack)
BN3/B3 fwd tank 2 section spotted
New intermittent RC for June 28 (11:30am-1pm)
NSF
Tyler Gray
LabPadre
24.06.2021
PPS: Cryo tank shell #3 work continued, shell #2 ready for roll out waiting at the gate
PPS: OLS IT: Scaffolding added to segment #7
BN3/B3 moved to the left in high bay; CH4 section work began with fwd dome connected to high bay bridge crane
GSE tank fwd dome on sleeving stand, another near tents
SN20/S20 aft dome in tent
BN2.1 lifting jig attached, removed from part of its test stand
LR11350 detached from tower, preparation work for connecting it to segment #6
OLM first cross beam added
Todays RC cancelled
OLS, IT: Segment #6 attached to LR11350
New intermittent RC for June 25 (10am-12pm)
NSF
Tyler Gray
LabPadre
23.06.2021
PPS: Cryo tank shell #3 work continued
PPS: OLS IT: Segment #7 looking finished
SN16: work around it, especially at the top
GSE3 tank work continued
BN3/B3 moved slightly in high bay [New naming scheme, B and S insead of BN and SN]
OL platform work continued
LR11350 still attached to tower
New intermittent RC for June 24 (3-5pm)
NSF
Tyler Gray
LabPadre
22.06.2021
BN3? fwd dome on sleeving stand
BN3? fwd dome sleeve moved and sleeved onto the fwd dome on the stand and moved into tent 1; new hot gas thrusters have been added at the top of the sleeve (for Reaction Control System RCS thrusters; "It is beleived these will burn methane and liquid oxygen")
Large hardware delivered to the PPS
PPS: Cryo tank shell #2 ready for roll out
OL platform work continued
Work at the top of the high bay continued
PPS: OLS IT: Segment #8 third column added
Starlink ground stations (white domes) delivered, three moved to the tracking station
Work on a ring section in tent 3
NSF
Brady Kenniston
LabPadre
21.06.2021
PPS: OLS IT: Parts and columns for segment #8 (smaller) arrived, first two columns lifted; work on segment #7 continued
PPS: Cryo tank shell #2 moved between 2.10 pm and 2.20 pm GSE fwd dome section has counterweight attached
LR1600/2 disassembly continued, parts loaded onto truck
Launch site: dirt/gravel work
Hwy4 work continued
Curved stainless steel sheets delivered
Mobile office section delivered to launch site [or left?], looking blast-hardened
OLS tank farm: work continued at GSE tank foundations with attachment pins being added
OLM work continued
NSF
Brady Kenniston
LabPadre
20.06.2021
Inspection robot working on a ring stack inside tent 1
GSE tank fwd section was rolled into tent 1
Ring section outside tents received top stabilisation ring
Work on transport stand
NOV ADS-30Q hoist (removed from Phobos) now installed on the IT base
LR11350 reattached to OLS IT
LR1600/2 parts at OLS
OLS: work on yellow pipes continued
Fwd dome caps spotted outside tents
NSF
Brady Kenniston
LabPadre
19.06.2021
LR11350 detached form OLS, IT; loadspreader detached
New Superheavy (BN3?) fwd dome sleeve spotted; first sleeve was likely a pathfinder
BN3? fwd dome sleeve mounted in the flip rig (which one?); later detached without flipping it
BN3 attached to bridge crane
Welding robot in tent 1
PPS: Cryo tank shell #3 stacking continued
LR1600/2 "Bluto/Tankzilla" now disassembled RIP
Hwy4 work north of launch site continued
OLS, IT: NOV ADS-30Q Drawworks hoisting system delivered, rated for a hook load of 1245 tons with 16 lines
GSE tank fwd dome spotted [?]
OLS, PB: a lot of equipment in the bunker installed
LR11350 lifted ADS-30Q onto the launch tower (on a steal construction at the base, south side)
PPS: Cryo tank shell #3 stacking continued [vid20]
GSE tank fwd dome spotted [vid20]
SN20 aft section in tent 1 [vid20]
Raptor engine partial combustion chamber and nozzle spotted outsides [vid20]
NSF
Brady Kenniston
LabPadre
18.06.2021
OLS, IT: Segment #6 rolled out to launch site
OLS, IT: Segment #5 still attached to LR11350
Rebar and shipping container delivered to launch site
Hwy4 work near OLS
OLS: New GSE pipes with orange part spotted
LR1600/2 "Tankzilla/Bluto" disassembly continued
PPS: Cryo tank shell stacking continued
Curved steel sections delivered, potentially for a new stand
WAI/RGV:
GSE Bunker: Compressed nitrogen tanks added
CH4 recondenser added between the two white vertical tanks
New foundation south of blast berm
New road/expansion of OLS extending southeast
Work around pad A: (water?) pipes; possibly for BN static fire
PPS: New building between LOX plant and airstream trailer park
SN15 kept under pressure, possible not simply a display stand
Gwynne Shotwell speach: Countdown/Timer released (likely time since first engine shipped for orbital flight)
OL platform: more hold down clamps installed
NSF
Brady Kenniston
LabPadre
17.06.2021
PPS: Segment #7 more cross beams added; segment #8 nearly soon ready for roll out, work plattforms added
PPS: Cryo tank shell work continued; shell #2 looks finished, work on shell #3 (5-ring) continued with stacking onto another section
Raptor van arrived, but no Raptors on board; one crata delivered, another returned to McGregor
OL platform work continued
High bay: more glass pannels installed
PPS: LOX distiller painted white
BN2.1 cryo proof test
Launch tower stands moved back to build site
Work on 3-ring barrel section outside the tents
New intermittent RC for June 18th (9-10:30am)
OEAAA information (June 14th): LR11000 "to support SpaceX orbital launch site construction and launch operations [...] most frequently be at height of 350ft."; 18 month permit until 12/29/2022
NSF
Brady Kenniston
LabPadre
16.06.2021
PPS: OLS IT: Segment #7 cross beams added, segment #6 nearly complete
PPS: Cryo tank shell stacking continued
OLS, IT: Segment #5 stacked onto tower by LR11350 crane (attached to crane, lifted, moved forward, lowered)
SN16 removed from high bay, turned down Remedios Avenue, to display stand at PPS, near SN15; 1935 TPS tiles spotted
White GSE delivered
BN3 fwd dome sleeve unhooked and moved into tent 1
SN20 aft dome moved around
LR1600/2 "Bluto/Tankzilla" boom removed, possibly being disasssembled
NSF
Jack Beyer
LabPadre
15.06.2021
BN3 "booster 2" LOX section (20 rings) relocated, then stacked onto aft/engine section
PPS: OLS IT: Segment #7 all four columns lifted; work on segment #6 continued
BN? fwd dome sleeve hooked to crane (unknown 3-ring stack from yesterday)
BN3? fwd dome with attachment pins waiting to be sleeved
OL platform work continued
OLM work continued
OLS, IT: segment #5 prepared for lift and elevator installation
OLS: yellow GSE pipes mated; work at tank farm coontinued; concrete work outside OLS on hwy 4
LR11350 moved around, lifted the next temporary elevator section into OLS, IT
NSF
Jack Beyer
LabPadre
Elon Musk
14.06.2021
Unknown 3-ring stack with multiple holes and side attachments spotted, later removed from flipping rig and moved; potentially for booster (BN3?)
Starship SN21 or above thrust puck spotted
PPS: Cryo tank shell construction continued, work on shell #3 began with new dome stacked onto ring section
Test nosecon: tip removed
Semicricular steel parts delivered
Launch tower transport jig moved back to build site (by SPMTs)
Work on possible super heavy stand/mount continued
Hwy 4 road work continued
OLS, IT: LR11350 crane detached form tower
SpaceX recently purchased Massey's Gun Shop and Range on the way to Boca Chica; some sources have indicated "That this location will be the 'Raptor Facility' and possible uses may include repair, rebuild and testing of rocket engines."
RCs for June 15 and 16 canceled
NSF
Jack Beyer
LabPadre
13.06.2021
Lift up at SN15
PPS: Cryo tank shell construction and painting work continued
Test nosecone moved to scrapyard
OLS, IT: Load spreader attached to LR11350, tower segment #4 attached to crane, section partially unbolted from transport rig, safety meeting, segment lifted slightly, completely unbolted from transport rig, lifted a bit, rotated, let down a bit; LR11350 moved backwards, segment lifted, crane moved forwards, segment lowered into place at 6pm local
NSF
Jack Beyer
12.06.2021
LR11350 boom lifted and lowered again; work continued on crane
Cryo tank shell moved to LR11000, attached to crane and lifted; positioned west of GSE2
OLS work continued; nitrogen vaporizer moved to tank farm; earth work contineud
Road work on Hwy 4; currently only one way, traffic lights installed
Launch tower column delivered
PPS: Work on cryo tank shells continued; stacking continued on third tank (cryo #2, prev #3; possibly now 17+4 rings tall), welding
RSN72 "Philosoraptor", RSN74 "Plaid Mode" delivered; RSN56/59 plus one onknown RSN loaded onto truck
BN2.1: welders worked on the top of the test tank
NSF
Jack Beyer
LabPadre
11.06.2021
Water tank lifted at 9am, lowered at OLS tank farm, just behind GSE2; detached from LR11000
OLS IT segment #5 moved to launch site, arrived at 11:47am
SN20 thrust/aft dome sleeved (with 3-ring stack)
New nosecone barrel section spotted in tent
Parts delivered to OLS
NSF
Jack Beyer
LabPadre
10.06.2021
LR11350 lifted, work on jib, lowered again later [vid11]
Nosecone barrel section and nosecone still waiting for stacking; Nosecone: Section Serial 502B, For Nose Serial NC1B, WO# 1554305, Start date 1/20/21
OLM: work at the leg/extension joint
BN2.1 inspected
GSE pipe moved at launch site
High bay bar work continued
OLS work continued
GSE5 aft dome section (3-ring and dome) outside tent
Nitrogen vaporizer delivered; nitrogen tanks moved to launch site
GSE? fwd section moved
New RCs June 15-17 (12-8pm)
NSF
Jack Beyer
LabPadre
09.06.2021
OLS IT: Segment #4 rolled out
Water tank [prev. refered to as cryo tank shell #2] for OLS tank farm rolled out [first double roll out]
Concrete work at PPS
Load spreader attached to LR11000, water tank attached to it later
OLS: earth work
PPS: Cryo tank shell #3 stacking progressed
PPS: OLS IT: More cross beams added to segment #6
New intermittent RC for June 11 (10.30-11.30am)
NSF
Jack Beyer
LabPadre
08.06.2021
Intermittent RC for today cancelled; testing closure extended to 10pm
PPS: tank #2 moved, work continued; Cryo #3 (now cryo #2) work continued
Cryo #2 now confirmed as water tank, thus not as a cryo tank shell
PPS: OLS IT: Work on segment #6 continued and fourth column added, cross beams added; segment #4 ready for roll out, moved closer to hwy 4
New dome on sleeving stand
Ring segment (3-ring) with hole spotted in tent
Temporary elevator parts delivered
OLS: work around PB continued; work on and around horizontal GSEs continued
OLM: work at the welds between leg and extension
Huge pipes and other equipment delivered
Container and wind radar moved by SPMT
New intermittent RC for June 09 (8.30-10.30am); RC for June 09 (12-8pm) cancelled
NSF
Mary
LabPadre
07.06.2021
PPS: OLS IT: Work on three segments continued; scaffolding on segment #4 nearly complete; more columns delivered; segment #6 third column added; launch tower braces delivered
PPS: Work on second cryo tank shell (weld) continued; work on third cts continued
Stainless steel rolls delivered
High bay: top glass work continued
OL platform work continued
OLS work continued; pipes fitted and removed at east horizontal GSE tanks
LR11350 extension now attached, work continued
Intermittent RC for today cancelled as well
New intermittent RC for June 8 (9.30-11.30am)
McGregor: At least 3 engine tests of different length
NSF
Mary
LabPadre
Reagan
06.06.2021
BN3/booster 2 methane downcomer delivered, lifted into high bay
PPS: OLS IT: Segment #6 work coninued, second column lifted
PPS: Work on second tank continued, third cryo tank construction began
LR11350 extension work continued
Pipes delivered to OLS
OLS work around horizontal GSEs continued
RC for Monday afternoon cancelled
"Mini Bakery" delivered ("The Bakery = heat shield manifacturing facility in Cape Canaveral, Florida)
NSF
Mary
LabPadre
05.06.2021
PPS: Cryo tank shell #2 now some 22 rings tall; welding work
PPS: OLS IT: scaffolding installation at segment #4; work on segment #5; first column of segment #6 lifted
Crane claw attachment delivered
LR11350 extension work continued; new 2-armed jib installed
OLS, IT: Staircases removed as elevator now is operational
OLS: work around horizontal GSEs continued
BN2.1 preparation work continued
OLM: Fifth and sixth (final) extensions added to legs
OLS, PB: ground equipment delivered
Berry crane Grove GMK6350L at PPS
SN20 "aft" dome spotted
NSF
Mary
LabPadre
04.06.2021
BN3 stacked onto another 4-ring section (now 20 rings tall) [Booster section#5?]
OLM: Fourth leg went up for third time at 7:46am
BN2.1 work near Pad B, pressure and thrust tests expected soon
[SN20?] nosecone and barrel section still outside tent three
PPS: OLS IT: work ont segments #4 and #5 continued
PPS: Work on cryo tank shells continued
High bay work continued
OL platform work continued
Work on a new stand commenced; with black side extensions [!, some suggest for launch platform]
LR11000 moved to pad north of OLS tank farm; possibly awaiting new GSE/shells to arrive
OLS: insulated pipes installed around western horizontal GSE tanks; earth work continued
LR11350 extension work continued: boom tip removed, new jib prepared
BN3 "fwd 3" section (3-ring stack) spotted near tent 3
SN14 practice dome weld area cut out
New intermittent RC for Monday, June 7 (10:30-11:30); possible segment #4 roll out
McGregor: 15sec static fire of the new vertical raptor test stand for first time (5.30pm)
NSF
Mary
LabPadre
03.06.2021
SN7.2 moved to an unknown location (12:52am)
OLM: Fourth extension lifted at 9:54 am; later removed; up again, removed again
BN2.1 (test tank on test stand) moved to the launch site
New RCs Mon-Wed June7-9 (12-8pm), possibly for testing BN2.1
GSE6 Mid #1 stack spotted
SN14 sleeved dome, reused to test Raptor vacuum mounts and Boster outer engine mounts; now SCRAP
PPS: Second cryo tank shell stacked onto next ring section
PPS: OLS IT: Work on section #4 continued; cross beams added to to segment #5
BN3 Booster Section #5, 4-ring section with lead-ins prepared for stacking
SN17 engine section at scrap yard (near SN5)
SN7.2 at scrap yard (near SN5)
OLS, IT: Work continued (elevator); segment transport mounts moved back
Unknown roll delivered
Crane Berry, gmk6350L moved
OLS: pipe work; dirt work
LR11350 extension work began
GSE7 "fwd dome" (not stack #2) barrel section spotted, 2-ring stack
Robots in tent 3
NSF
Mary
LabPadre
Starship Gazer
Austin Barnard
02.06.2021
New intermittent RC for June3 (2-4pm)
PPS: Piping added to second cryo tank shell
PPS: OLS IT: segments #4 and #5 work continued; third and fourth columns lifted
PPS: Cement work
OLS, IT: Work continued, elevator installation continued
OLS, PB: Work continued
OLS: Horizontal GSE tanks (east) received some pipes ["Subcoolers, chill LOX and CH4 to near their freezing point to maximize efficiency", NSF]; wor at and around the tank farm bases continued; Dirt work near exesting berm
SoLS: "Seems to be a staging area for OLS components and equipment" [NSF]
Header tank assembly jig spotted on a truck
SN11 remains left Boca Chica
NSF
Mary
LabPadre
01.06.2021
OLS: Four horizontal GSE tanks placed onto stands east of tank farm (2 more empty foundations) [likely on May 31?]
Unknown GSE parts delivered (big steel pipes/tanks), Five blue/white Diesel generators from Leroy Somer delivered
Crane inspection
OLS: Rebar placed north of tank farm for pad extension (west of new pad) and later concrete poured; the two horizontal GSEs (for subcooling propellant) west of tank farms received some piping on top
PPS: OLS IT: Work on segment #4 continued; later segment #5 first column lifted at 5:15pm, second column lifted at 6:03pm
PPS: Work on second cryo tank shell continued, stacked onto another ring section; welding of some ring section; the second tank has another dome than the others - possibly for water storage [?]
OL platform work continued, some welding; 8 hold down or support clamps/arms now installed [RGV]
LR11350 crane detached from OLS IT; crane lowered later for boom extension
OLM: third cap/extension installed
NSF
Mary
LabPadre
RGV
Date
Description
Source
Link
31.05.2021
Memorial Day - mot much work
Downcomer pipe section delivered
BN2.1 test tanks lifted onto new test stand for thrust test (Modified nosecone stand)
OLM: second leg cap/extension added
SN15 has been bolted onto a display stand
NSF
Mary
LabPadre
RGV
30.05.2021
The SH thrust puck is for the 9 center, gimbeling Raptor engines
PPS: some minor work on shells and IT segment continued; SN15 still on stand
3 Raptor engines spotted in a van, likely the SN15 engines for sending them back to McGregor
Two launch tower stands still on launch pad
OLS IT: LR11350 still attached to segment
OLM some inspection at the top of a leg, later first launch mount leg cap installed on it
OL platform work continued
BN2.1 left mid bay, moved next to tent 3, near thrust shucking stand
Deimos under construction for launch next year
Orbital duration static fire of a Raptor engine at McGregor for first time!
NSF
Mary
LabPadre
Elon Musk
Teslarati
29.05.2021
GSE7 stack #2 fwd dome spotted
Super heavy thrust puck delivered [BN3?], confirming a total number of 29 engines (adding a center engine), which was confirmed by Musk [later to be risen to 32]
BN2.1 puck shucking stand hydraulic rams installed
PPS: second cryo shell stack continued
New ring sections spotted at the production site
Some sort of lift moved into tent
Starship fwd dome (stacked and flipped) hooked to crane [SN20??]
IT segment still remained attached to LR11350
OLS: concrete poured north of tank farm (rebar laid on May 27-28)
SN11 wreckage cleanup, some still lying around
Two large horizontal GSE tanks moved east of tank farm
High bay work continued
Air force budget for a research project "Rocket Cargo" involving Starship released
Raptor production at 48h/engine
NSF
Mary
LabPadre
Elon Musk
28.05.2021
SN17 destacking: mid LOX and cmn dome section cut in two
PPS: cryo tank shell moved to launch site
OLS, IT: segment #3 attached to LR11350, stacked onto segment #2 ("Klein Tool")
LR11350 parts unloaded (arrived yesterday)
Large grey tank delivered to the launch site, as well as more crane parts (ropes)
OLS: work north of tank farm continued
Rolling 5000ft TFR added (June 1 - July 31)
NSF
Mary
LabPadre
27.05.2021
OLS IT: Ladders installed to third segment, moved to launch site; elevator installed on stacked sections (McDonough elevator)
PPS: OLS IT: work on fourth segment continued, some parts at the top removed [?]
BN3: stacked to 16 rings, with common dome on top
New nosecone still outside tent 3, near barrel section with heat sheet tiles and lead ins [SN20?]
Starship 3-ring common dome full with TPS mounting pins [SN20?]
PPS: Cryo tank shell work continued, crane disconnected from second stack; full stack moved a bit
Robotic welder moved
OL platform work continued
Prefabricated buildings delivered
OLS: rebar laid north of tank farm for new pad and earth work continued (lower level than farm, same as street); concrete work
Robotic dog walked around
LR11350 parts delivered for boom extension
New RC intermittent for May 28 (10am-12pm)
NSF
Mary
LabPadre
RGV
26.05.2021
LR11350 moved/turned
OLS work continued, insulated piping delivered
RC extended to 5pm
SN15 put on transport stand, moved up Hwy 4, turned into Remedios Avenue, parked near nosecone test rig at PPS
New intermittent RC for May 27 (2.30-5pm)
PPS: OLS IT: Segment #3 prepared for roll out as work platforms being attached
Pipes delivered to production site
PPS: Cryo tank shell #2 stacked onto another ring section
OL platform: hold down clapms spotted, firs one installed on the inside
Test tank spotted in Mid bay [BN2.1]
Modified test stand to work as new puck shucker for SH test tank BN2.1 as hydraulic cylinders are visible inside the structure [the_denks]
BN3 stacking continued [?]
Phobos dismanteling work continued
NSF
Mary
LabPadre
RGV
Nomadd
Shane Overvold
25.05.2021
New intermittent RC for May 26 (2-4pm)
SN15 attached to LR11000
OLS: concrete pouring at access to OLS tankfarm as well as south of it, work on tank farm continued (GSE tanks and foundations)
BN3 (some 12 rings high) moved in high bay, new stack moved into it and attached to bridge crane, stacking continued; LOX tank now at the bottom according to Elon Musk (unlike BN1)
LR11350 (Kong/Frankencrane) detached from IT, load spreader removed
PPS: OLS IT: work on segments continued
PPS: Second cryo tank shell work continue, as well as piping on first tank
BN3 aft tank #5 section (4-ring, with lead-ins) spotted
Crane moved to launch site
High bay work continued, more glass pannels installed
Nosecone test stand modifications continued
OLM work continued
OLS, PB: containers lifted on roof of PB
NSF
Mary
LabPadre
RGV
24.05.2021
9m transport stand moved to launch site together with counterweights, possibly for transporting SN15 back
OLS, IT: segment #2 attached to LR11350 load spreader, detached from stand and lifted. Crane moved forwards, segment lowered and stacked onto existing structure
OL platform work continued
PPS: Cryo tank shell work continued, second shell growing
Nosecone test stand modified
SN20 common dome with CH4 header tank still outside tents
LR11000 rolled toward Pad B, SN15
NSF
Mary
LabPadre
23.05.2021
BN3 section lifted in high bay, stacked onto new section
PPS: Cryo tank shell work continued
OLS, IT: Segment #2 prepared for stacking, assisted by LR11350; work on segment #1 [built] continued; stacking loadspreader attached to LR11350; work lift lifted into the base
GSE parts [see May 20, possibly for prop subcooling, vaporization or recondensing] moved, stacked on the new concrete foundations ("pedestals") west of OLS tank farm
OLS: more pipe channels put into place west of OLS tank farm
OLS: valves and piping arrived; steel structures lifted into place at tank farm
New Starship [5-?] ring section with a lot of TPS tiles in a new arrangement and lead-ins moved out of mid bay [SN20?]
SN15 flaps tested (4:53pm-5:15pm)
SN20 aft dome near high bay
BN3 fwd tank #4 booster section spotted
Robot arm worked on nosecone in tent 3
SN17 section now cut out
NSF
Mary
LabPadre
Starship Gazer
22.05.2021
SN21 common dome [not yet stacked] now for GSE5 (fwd dome)
GSE5 fwd 2-ring stack spotted
GSE5 fwd dome "Stack #2" lifted onto sleeving stand, sleeved later
New section in tent 1
OLS, IT: work continued, work platforms added to the top of the first segment
SN7.2 probably going to scrapyard
PPS: OLS IT: Work on segment continued
PPS: cryo tank shell work continued, again attached to crane, stacked onto new ring section, looking like a rather difficult task
Nosecone test stand modified
OL platform: work on the inner structures continued
Work on a heavy duty transport stand
OLS: concrete plates added east of tank farm; concrete plates removed west of tank farm
SN15 work continued
Some damage to one of the satellites
NSF
Mary
LabPadre
21.05.2021
IT section #2 started to move to launch site (landing pad) at 8:15 am, ladders installed on the inside of the section
LR11350 raised, apparently in a small configuration that will need to be extended for stacking upper segments
SN20 common dome spotted (3-ring), covered in TPS tile attachment pegs, with lead ins, CH4 header visible
SN21 common dome spotted [Starship Gazer]
GSE aft section (3-ring) with reinforcement and lead ins next to SN20 cmn dome [GSE5?]
SN17 section outside mid/high bay, some tiles cut out [mid lox&cmn dome stack]
More 4-ring stacks with lead-ins spotted
SN15: RSN54 removed, as well as a second raptor engine and third engine later, brought back to build site
BN3? fwd dome spotted
OLS, IT: Preparation work for stacking
Tent 3: two nosecones inside it, one nosecone outside it
According to Marcus House: BN3 stack in high bay is common dome on fwd LOX section (total of 8 rings). GSE4 in mid bay has been stacked this week onto its aft section, now complete.
Marcus House: Combinations SN20-BN3, SN21-BN4, SN22-BN5, SN23-BN6, then major upgrades for SN24-BN7
NSF
Mary
LabPadre
Starship Gazer
Marcus House
20.05.2021
PPS: OLS IT: Scaffolding errected on top of a segment, possibly for some stacking at the site [?]
PPS: cryo tank shell work continued, segments lifted and stacked
SN15 inspection/work
OLS building east of tank farm concrete poured
SN11 wreckage still not fully cleaned up
GSE equipment (4 greay tanks with 4+ inlets) delivered to launch site
OLS, IT: work continued
High bay glass work continued
Test nosecone rig disassembly continued
PPS: pipes and tanks delivered
New nosecone rolled out (without flaps), barrel section with work platform near it
Intermittent RC May 21 (09:30-12:00)
NSF
Mary
LabPadre
19.05.2021
HLS bill modification: selection decisions or awards that were announced prior to the date of enactment shall not be recscinded, terminated or modified
Thundersotrm in the area, some damage at the production site; crews left site
BN3? CH4 assembly spotted, 28 pipes for all 28 enginges "Super Heavy Propellant Manifold", feeding methane to engines from downcomer
Nosecones in tent 3 [SN17?, SN20?]
Tent 1: Robot working on new ring stack
LR11000 fully assembled
LR11350 "Frankencrane/Kong" nearly complete, hookblock attached
PPS: OLS IT: Assembly work continued
PPS: Cryo tank shell work continued
High bay: more glass panels installed for bar
BN3 in high bay [consensus]
OL platform work continued
OLS work continued, new concrete bars east of farm, earth work north of farm, building work west of farm continued
OLM legs now full of concrete, curing done [RGV]
NSF
Mary
LabPadre
RGV
18.05.2021
LR11000 "King" assembly continued, raised
LR11350 crane assembly continued
GSE4 aft parts lifted into mid bay [where the rest of GSE
Test dome put on sleeving stand, Rvac engine mount visible
PPS: Cryo tank shell construction work continued; dome lowered onto a new ring section
PPS: OLS IT: work continued
OLS tank farm work continued, as well as earth work around (N, E, W) it; SW foundation
Mysterious new parts delivered to build site
Scrap 2-ring barrel section hooked onto crane for sleeving, sleeved with test dome
Earth work near launch site entrance, north of landing pad
NSF
Mary
LabPadre
17.05.2021
PPS: OLS IT: Level four fourth column lifted at 9:17am, work on other segments continued
PPS: Lift moved into the shell stacking area
OLS work continued, earth work between berm and OLS tank farm, as well as between it and PB
LR11000 assembly continued by the help of Tankzilla/Bluto, counterweights and boom parts delivered
SN20 fwd dome outside tents (not stacked yet)
Three ring section outside tents
OLS, IT: Work continued
OLM work continued, welding of rod caps with mount legs
OLS tank farm: NW foundation concrete plates removed
Test dome spotted outside tents
STARBASE sign and coloured lights [vid May18]
NSF
Mary
LabPadre
16.05.2021
LR11000 (max 1000tons, 220m) assmebly began/continued; Bluto/Tankzilla assisting hereby; more parts delivered (trucks waiting in lane at entrance of launch site)
LR11350 "Frankencrane/Kong" assembly continued; power boom part nearly finished
OLS work between tank farm and PB continued
PPS: OLS IT: Work on fourth level continued
PPS Cryo tank shell assembly work continued
PPS wiring at the outside of container wall, conduit laid near STARBASE sign
New nosecones in tent 3 [?]
SN15 being inspected thorugh access hatch; starling dish inspected
Cidco Road: (New) piece of equipment now erected, as high as the remaining section of Mk2; some suggest it to be a ISRU Methalox part for fuel Starships
SN20 MID-LOX and Leg skirt spotted (again)
BN3 fwd tank #3 spotted
NSF
Mary
LabPadre
John Winkopp
Starship Gazer
15.05.2021
OLS work continued, new building foundations between tank farm and berm
Crane mats placed north of tank farm
BN2/BN3 section in high bay rotated
Test nosecone disassembly continued
PPS; OLS IT: third column added on fourth level
PPS: work on cryo tank shell continued
STARBASE sign installed at PPS container wall, letters ignited in the evening
Marcus House: Tank farm speculation: 1 nitrogene tank, 3 oxygene tanks, 3 methane tanks (2 rings shorter, higher concrete foundation), 1 water tank; capability for 2 full stack launches
NSF
Mary
LabPadre
14.05.2021
RC for today cancelled
SN15 lifted onto Pad B; 8:58am; flaps closed at 09:02am
FAA: "SpaceX mus meet all licensing requirements before Starship/Super Heavy can launch"[392]
PPS: OLS IT: Level/Segment 4 work began with first column being lifted, more columns delivered
Red crane parts delivered to launch site
Work on SoLS Pad A as well as Pad B
LR11350 crane assembly continued
OLS IT: work continued
OLS tank farm work continued
OLS: concrete plates for new building? between tank farm and berm
PPS: cryo tank shell assembly work continued
Test nosecone scrapping continued
OL platform work continued
SN15 lifted from SPMT by Tankzilla/Bluto; SPMT moved away, flaps retracted, lifted onto pad B; SPMT left launch site
Nosecone test rig moved behind PPS [vid 15]
"Bob" Test nosecone dismantling continued [vid 15]
SN15 unhooked from Bluto/Tankzilla on pad B (previously on pad A) [vid15]
New crane LR11000 parts delivered to launch site [vid15]
Bluto/Tankzilla moved [vid15]
Super heavy booster section moved into high bay for stacking, BN2 or BN3 [vid15]
NSF
Mary
LabPadre
Chris B
13.05.2021
PPS: OLS IT; Parts delivered, work on the sections continued
PPS: cryo tank shell scaffolding
OLS tank farm work continued, concrete poured at NW foundation
Box culvert parts moved for underground pipes
LR11350 ("Kong/Frankencrane") assembly continued
OL platform work continued; coverings inserted on the outside
High bay: window installation continued
Work on an incomplete dome section
FCC: orbital test flight information, NET June 20
SpaceX
NASA: awarded SpaceX a $50 mio contract for "on-orbit large scale cryogenic propellant management and transfer demonstration" [=refuelling], to be completed by gthe end of 2022
"Bob", test nosecone scrapping began; top section removed
OLM construction work late night [video next day]
Nosecone test rig disassembly continued [video next day]
Bob: Cut in half [video next day]
SN17 MID-LOX tank section next to tent 1 [video next day]
NSF
Mary
LabPadre
Michael Baylor
12.05.2021
Test nosecone rig: Cage lifted by bridge crane, nosecone rolled out, cage lowered again
RC for May 14, (10am-12pm, intermittent)
PPS: Cryo tank shell work continued
SN15 waiting to lifted onto Pad B
SN15 work on the base, around the skirt area
OLS tank farm work continued
LR11350 assembly work continued, more parts delivered
PPS: OLS IT level 2 work continued; lift caps installed on a segment
Delivery of steel [IT?] parts to build site
Elevator delivery to build sited
PPS: new yellow crane delivered [see video yesterday as well]
NSF
Mary
LabPadre
11.05.2021
Loadspreader attached to Bluto/Tankzilla
SN15 moved to SoLS pad B, attached to Bluto/Tankzilla
LR11350 crane assembly continued, becoming very colourful, more parts delivered
OLS, IT: work continued
Steel parts delivered to launch site
SN11 cleanup continued
Nosecone test rig moved back to build site, into high bay, bridge crane removed cap, closeup shows clear dents
OLS tank farm, concrete plates added to wester GSE foundation as well as south easter (high) foundation
OLS, PB: work on ground equipment around the building
PPS: cryo tank shell stacked onto next part
NSF
Mary
LabPadre
10.05.2021
SN17? and another nosecone in tent 3, flap mounting hardware visible
GSE4 aft dome flipped
GSE4 stacking in mid bay [fwd dome section onto other section?]
Test nosecone flap pieces now at bild site
PPS: Cryo tank shell work continued, welds checked and analysed
PPS: OLS IT work continued
OLS tank farm work continued
OLS, IT: work continued
LR11350 "Kong" assembly continued
GSE2: special object hanging down from aft dome
SoLS Pad B work
Manitowoc 12000-1 crane moved to OLS tank farm area
Liebherr LTR1220 moved down the road to launch site, soft closure between 8:50-9:15 am
White poles ? delivered to build site
Test nosecone rig loaded onto SPMTs [video May 11]
Tankzilla/Bluto moved to SoLS pad B [video May 11]
LR11350 crane parts delivered, assembly continud [video May 11]
RC for May 11 (12-2pm, intermittent)
NSF
Mary
LabPadre
09.05.2021
OLS, PB: Much GSE equipment around it
OLS tank farm: concrete plates removed, two high foundations appear to be ready soon.
SPMT loaded with counter weights
Nosecone test rig work continued
High wind warning through loud speakers
SN16 work continued; work platform being removed
Big white tank delivered to PPS; now there are three white tanks
PPS: work on cryo tank shell and IT continued
High bay: first glas panel for roof bar installed
OL platform work continued
NSF
Mary
LabPadre
08.05.2021
SN16 moved to the side of high bay, possibly to make place for booster assembly
SN17 section (7 rings tall, with lead ins, upper part with many TPS tiles, some damaged), one stack called Mid-LOX, moved out of mid bay [Mid LOX and common dome], possibly indicating a hold
PPS: OLS It: Work on both level continued
PPS: Work on cryo tank shell assembly continued
OLS tank farm work continued
OLS, IT: work at the top
OLS: Work between PB and tank farm, earth piles visible
SpaceX crane GMK7550 moved at launch site (to OLS tank farm)
Work on nosecone test rig
Tent 3: Work seems pretty finished
Electrical transformers delivered to launch site
Phobos, Deimos: SpaceX request to use Starlink terminals onboard the platforms
Phobos: Remaining towers, some of the room-structures and other objects removed [Shane Overvold, Levy]
NSF
Mary
LabPadre
07.05.2021
SN15 saving continued: legs appeared to be crampled, at least one TPS tile missing, some have been damaged during flight
OLS tank farm work continued with concrete pouring and other
SN16 detached from crane and work platform removed, second aft flap added
PPS: OLS IT: work on both level continued, level 3 received fourth pillar
PPS: work on cryo tank shells continued; big stack lowered into scaffolding
3-ring dome sleeve spotted
OL platform work continued
SN17 nosecone barrel section with lead ins and work platform
LR11350 moved to OLS (IT)
SN20 mid LOX section (4-ring stack) spotted
SN15 moved to center of landing pad
OLS, IT: work on top of level 1
SN15 landing legs removed, some of them looking burnt a bit
BN3? common dome flipped (3-ring and dome)
Test nosecone rig: both flap simulators removed
NSF
Mary
Jack Beyer
LabPadre
06.05.2021
SN15 saving continued; lift went up 06:06-07:02, working on right fwd flap and later put on mega SPMT; aft flaps extended
PPS: OLS IT work continued on both levels
PPS: cryo tank shell work continued; 5 ring stack stacked onto high (8-ring?) stack
GSE3 work on plumbing continued
Delivery of unknown white carriage like structures to build site
OL platform work continued
BN3 fwd tank #2 section (4-ring) spotted
SN6 remains moved to scrap yard
SN16 work continued; received one aft flap
Tankzilla/Bluto moved to region of pad A
RC from yesterday extended to 12pm
RC (intermittant) for May 7 (10-12)
NSF
Mary
Jack Beyer
LabPadre
05.05.2021
SN15 successful flight and landing
GSE3 work continued
BN3 aft dome still attached to flipping jig
SN16 remained attached to bridge crane, work platform still there
OLS tank farm: work on tank foundations continued
PPS: cryo tank shell work continued; the tank in the scaffolding lifted; three more domes ready
PPS: OLS IT: level two assembly continued (top beams added); level three third column added
NSF
Mary
LabPadre
others
04.05.2021
SN15 flap testing at 6:22 am, as well as later in the morning; FTS armed
SN15 scrubbed flight attempt
SN15 pressure vents (double depress)
OLS, PB: work continued
OLS, tank farm: progress on foundations; third foundation now ready [?]
Landing pad: more water deluge system sprinklers installed [date unclear]
BN3 aft dome flipped and placed on a cart
GSE4 fwd dome section attached to crane
SN16 still attached to crane
GSE3 pipe work continued
New 4-ring stack with lead ins spotted outside tents
PPS: OLS IT: level two more cross beams added; level three: two columns raised and cross beams added
PPS: Cryo tank shell now painted white
OL platform work continued
NSF
Mary
LabPadre
03.05.2021
BN3 aft dome section attached to flipping rig
SN16 still attached to crane; crews entered through access hatch
PPS: Cryo tank shell dome sections stacked onto another section (now probably 8 rings tall)
PPS: OLS, IT level two: more cross beams added; fourth column raised
New thrust puck delivered
Painted chair arrived at boca chica village
Deliveries of steel parts to build and launch sites
OL platform work contineud
OLS: work between PB, tank farm and hwy 4 continued ("Raptors Loose")
OLS tank farm: concrete plates with weird shape for north eastern foundation
SN15 preparation work continued
PPS: cryo tank shell dome painted
RCs for May 4-5 (12-8pm) added
NOTMAR added for May 4-6
TFR unl added for May 6
SN15 ambient pressure test
Alert notice issued for May 4
NSF
Mary
LabPadre
02.05.2021
Nosecone "Bob" in test rig has been undergoing stress tests as buckling of panels visible
SN15 ambient pressure test
PPS: OLS IT level 2: cross sections and third column added (at 10:25am)
PPS: More solar panels added
SN17 nosecone barrel section infront of tent 3; attached to crane
SN16 still attached to crane
Single ring sent to scrap yard
High bay work continued
Tent 3 work continued; apparently getting a second east gate
OLS: work between PB, tank farm and hwy 4 continued ("Raptors Loose")
OLS: tank farm work continued (foundations)
OLM: caps (the ones with rods) being welded to the legs
SN15 work on aft section
Alert notice issued for May 3
TFR unl added for May 5
TFR for May 3 removed
NSF
Mary
LabPadre
01.05.2021
TFRs for Monday and Tuesday added
TFR for Sunday removed
OLM: Leg grinded
GSE3 soon ready for roll out; work through access hatch
NSF
Mary
LabPadre
Date
Description
Source
Link
30.04.2021
SN15 scrubbed flight attempt
Evac notice for 10am, depending on weather
SN16 nosecone moved to high bay, attached to bridge crane; stacked onto tank section
GSE3 (fully stacked) still attached to crane, more pipes added
SN17 nosecone barrell section full with heat shield tiles in front of tent 3; work platform errected, attached to crane
Single ring "Super stringer stack" spotted
OLS, PB: entrance gate added
OLS work continued (eg at tank farm)
PPS: Assembly of second OLS IT level (construction at PPS, then the whole level will be transported to the OLS and put onto the current columns)
PPS: Cryo tank shalls construction work continued
OLS: the two tanks now painted white
Berm work continued
OL platform work continued
Video shows collection of earth movers
Raptor RSN? "insert meme here" delivered
Alert notice for Saturday issued, but no RCs
New TFR for Sunday (two identical TFRs); one TFR for Sunday removed
TFR for Saturday removed
NSF
Mary
LabPadre
29.04.2021
SN17 nosecone work in tent 3
OLM: more caps delivered
New 3mm stainless steel single ring spotted
GSE3 aft dome section work
GSE3 hooked to crane, stacked on aft dome later
SN5 and SN6 at scrap yard
Raptor van with crates
OL platform work continued [again]
Vacuum raptor engine (RVac) mounts spotted
PPS: 12m dome with single ring lifted
Downcomers delivered
OLS, PB: surrounding work continued
Berm work continued
OLS, IT: ready for next level
SN15 work under skirt
LR1300 moved, and left launch site together with Tankzilla/Bluto
SN11 debris cleanup continued
SN15 FCC approved starlink antenna from April 28 to June 28
Landing pad repair work finished
FAA authorized the next THREE Starship launches
Alert notice issued for tomorrow
TFRs from Fri-Sun
OLM all center supports cut off
SN16 moved from mid bay to high bay (19:27-19:48)
SN15 FTS installed at 22:26-00:44
NSF
Mary
LabPadre
Tank Watchers
Christian Davenport
28.04.2021
SN16 nosecone removed from crane; a stack covered with TPS tiles near it
GSE [GSE4 fwd?] dome on sleeving stand, sleeved with 3-ring stack
RSN59 [?] delivered "The Mighty DOGE"
RSN55 loaded onto raptor van, probably left
3/4-ring stack moved into mid bay
OLS work continued
OLS, IT: four columns connected
The two blue (military grey) tanks to be painted white
OLM: support structure beginning to be removed
Berm work continued
SN15 broken TPS tiles removed
Landing pad repair work
OL platfrom work continued
SN15 flaps unchained and unfolded
RC for April 28-30 (12-8pm/8am-5pm)
NOTMAR for April 29 and 30
SN17 common dome (3-ring stack full with TPS tiles) moved into mid bay; stacked on its LOX tank section (4-ring stack)
TFR for 29 April removed
Road closed at 16:35, pad clear at 18:32, Nosecone test; road opened at 19:48
NSF
Mary
LabPadre
27.04.2021
SN15 Static Fire #2
SN20 aft dome being constructed
SN16 Nosecone work continued, still attached to crane
Stainless steel rolls delivered
OL table work continued
COPVs delivered on Raptor van
PPS 12m "cryo tank shells, top dome" work continued, "cryo shells may potentially be used to insulate cryogenic storage tanks"
PPS: parts of OLS IT
OLS, IT: work continued
Work between PB and tank farm continued
OLS, PB: concrete poured on the ground
OLM work continued
SN15 some TPS tiles damaged during static fire #1
OLM cap [?] see April 22, delivered to launch site
Blast berm work continued
Red crane loaded on SPMT at launch site
TFR for April 28 removed
TFR for April 29 added
NSF
Mary
LabPadre
26.04.2021
SN15 Static Fire #1
Fwd dome sleeved on a 4-ring stack [?]
GSE 2-ring and 3-ring stack from yesterday
GSE3 aft dome section, ready for stacking
SN16 nosecone stacked on its barrel section
OLS berm work continued; more earth work on the east side of it
OLS, IT: cross beams added between columns, both vertically and horizontally; more columns delivered
OLS, PB: work continued; red roll-lift near it
OLS tank farm: concrete form being added to fifth foundation; earth work between it and PB
OLM work continued
Tankzilla/Blute loaded on SPMT
PPS: Huge 12m diameter domes; work continued; supposedly for putting over GSE tanks for insulation?
Phobos: derrick tower removed, much of the helipad and accommodation block as well [Gavin Cornewll]
RC 26-28 April (12-8pm)
Blue Origini protest about NASA HLS selection
Alert notice for April 27
NSF
Mary
LabPadre
Gavin Cornwll
25.04.2021
TFR unl added for April 28
OLS, IT: Fourth column lifted again, cranes moved; work for 143 meter tower continued
BN1 final section hooked to crane for scrapping
GSE3 work on pipes continued
OLS, PB: concrete forms removed
OLS Tank farm: Work on the two next concrete foundations continued, seem to be taller thant the two for GSE1 and GSE2
Nosecone test rig at SoLP: work continued
SN15 work on aft section (under skirt)
Bluto/Tankzilla moved towards gate
BN3 aft section removed form sleeving stand
Tent 3 expansion work continued (east and west walls)
Huge white tanks at the PPS; more solar panels added to the PPS fence
OL platform work continued
New [Sn16?] nosecone washed in front of low bay; Other nosecone [Sn17?] in tent 3
Fwd dome moved to and lifted on sleeving stand; three ring stack beside it
New two ring stack spotted
Alert notice issued for April 26
RC for April 26 (12-8pm)
TFR for April 27 removed
NSF
Mary
LabPadre
24.04.2021
SN16 nosecone RCS testing
GSE3 more pipes added
BN3 aft sleeve (3-ring) near the BN3 aft dome (on sleeving stand), later sleeved ["aft dome booster WO# 1626306)
Mounting hardware for RVac engines delivered (Vacuum raptor engines)
4-ring section moved into tent
SpaceX cat seen
Stainless steel roll delivered
OL platform work continued
Work on tent 3 west wall
OLS, PB: concrete forms removed
OLS, IT: work continued connecting the three columns; fourth column delivered, installed and later taken down again
PPS: one tank attached to crane, rebar for a ring foundation
Rapotor vacuum mount on a test dome (former SN14 thrust dome)
TFR for Monday removed
NSF
Mary
LabPadre
23.04.2015
SN15 cryo/ambient test with tank farm activity and venting (skirt, methane, LOX, front tri vent?)
GSE4? aft dome flipped
SN16 nosecone with flaps installed in tent 3, moved next to wind break, near a 4-ring stack with work platform
BN thrust dome, possibly for BN3 spotted
GSE3 prepared to be stacked onto aft section
OLS, IT: column delivered at 10:45am
OLM last caps with rods lowered
Blast berm work continued
SN17? ring section spotted with a lot of TPS heat shield tiles attached
2-ring stack scrapped
SN16 tank section fully stacked in mid bay
OLS, IT: Third column attached by Bigge crane
OLS, PB: concrete poured
TFR for Monday (unl.)
RC cancelled; new one for April 26 (12-8om)
NSF
Mary
LabPadre
22.04.2021
OLM leg cap delivered (some sort of gray pipe)
GSE3 attached on crane, stacked onto mid LOX section (now 10 rings tall), they haven't been very cautious with it
GSE4 section (3-ring stack with dome) moved [aft?]
Test nosecone moved to launch/test site, between SoLP A and B
OLS, PB: work continued
GSE tank farm: more foundation work, concrete poured into third foundation
OLS, IT: Work continued, connecting beams placed between the two poles
OLM more caps, with rods lowered into legs
GSE2 moved into final position
Zeus and Apollo spotted walking around
SN15 big TPS panel completed at 2 am
Berm reinforcement continued
2 Nosecones [SN16, SN17?] inside tent 3
Aft fin delivered to build site, accompanied by a toy dump truck
TFR for Friday cancelled
Elon Musk, X-Prize: Lunar Starship will deliver up to 200 tons of payload to moon
Overpressure notice for April 23
Road closed, venting
NSF
Mary
LabPadre
21.04.2021
TFR unl. for April 24
RC updated to 5-7pm
RC updated to 12-2pm and 5-7pm, then to 10:30am-12:30pm and 5-7pm, 5-7pm cancelled later
"The FAA has not signed off on the SpaceX Starship SN15 flight yet, but I'm told they are close, working through documentation for some of the new components."[417]
LR11350 moved to build site (crane yard)
Second column for IT delivered to the OLS, lifted at around 4:38pm
OLM legs recieved caps with steel rods hanging from them
RCs for April 22: 7-9:)0 [sic!]a.m. and 5:30-6:30pm
RC for April 23: 7am-12pm (beach and road)
BN2 aft section flipped
GSE3 more pipes attached
GSE3 mid LOX (mid #2) tank (4-ring stack) spotted and moved
Test nosecone rig assembly work continued
Round stand parts delivered
OL platform work continued
OLS tank farm: work on fourth jig started with concrete plates
OLS, IT: parts lowered into base
Blast berm work continued
SN16 tank section now fully stacked in mid bay
Overpressure notice for April 21
RC added for April 22 (7-9am, 5:30-6:30pm) and 23 (7am-12pm)
NSF
Mary
LabPadre
Christian Davenport
20.04.2021
SN16 aft section (5-ring stack) moved into mid bay, other sections stacked onto it
B2.1 dome spotted inside tent 1
New 3-ring stack spotted
Test nosecone rig assembly continued
OLS, IT: first steel column added at a corner, (9:22am lifted, 11:09am released from crane)
OLM preparation work continued
Bluto/Tankzila still attached to GSE2
OLS, PB: Work continued
PPS: fourth ring added to the [tank]
High bay roof work continued
3-ring stack moved out of tent 1
New [?] nosecone inside tent 3 [possibly SN17]
Overpressure notice for tomorrow, April 21 (12-8pm)
TFR unl for April 23
NSF
Mary
LabPadre
19.04.2021
SN15: RSN54 installed at around 5:53am local
New RC for today from 12pm to 1:30pm
OLS, IT: steel parts delivered
GSE3 aft dome sleeved, not yet flipped
OLS, PB: cement/concrete poured into wall forms
Blast berm work continued, rebar added on top [?]
GSE2 moved out of mid bay, put on transporter, moved to OLS tank farm
Tankzilla/Bluto placed GSE2 on concrete jig adjacent to GSE1
(2:34 left build site, 3:57 entered launch site)
Test nosecone rig work continued, more pieces added
3-ring stack at PPS removed from crane
OLS, Bunker; work, scaffolding on south side
LR11350 nearly fully assembled (small configuration), work on its support boom
Yellow crane near IT
BN2 aft dome section (not flipped yet)
OL platform wedling
GSE3 aft dome craner removed
TFRs removed
RC for tomorrow cancelled
NSF
Mary
LabPadre
18.04.2021
FAA: SN15 launch authorization pending
Lowest part of a nosecone spotted [?]
SN11 debris field still not fully cleared
OLS: pipes coming out of the ground at the far NE corner
OLS tank farm: concrete plates added to third base
SN15 more tiles added
New concrete fields in the village area
TFR unl for Wednesday, April 21 (7am-8pm)
Overpressure notice for SF tomorrow (third raptor still missing)
RC for Monday cancelled
SN15 third raptor delivered: RSN54 again
NSF
Mary
LabPadre
Chris B
Austin Barnard
17.04.2021
Remaining raptor has left the launch site at 3:15 am
OL platform: welding work
Airgas truck at the launch site
SN11 debris still lying around SoLS, later compacted into dumpster
SN15 work under skirt (Raptor installation)
Earth wall / berm work continued
OLS, IT: has two huge entrances facing west and south
LR11350 parts arrived, some yellow some red [?]
OLS, PB: work continued
Tankzilla/Bluto still at OLS tank farm
Pipes deliverd to build site, unloaded
Tent 3 front wall not yet completed
TFR unl. for Tuesday, 20 April (7am-8pm)
NSF
Mary
LabPadre
16.04.2021
SN15: RSN61 moved under skirt early morning, lifted at dinner time
Second rapter lifted at 11:00 pm, lift came down at 12:06am next day
GSE3 fwd dome section stacked onto MID #1 section
2-ring stack moved to scrap yard
Propellant production site (PPS): parts delivered
Test nosecone rig: work continued
Fwd dome barrel section spotted (2-ring)
LR11350 assembly continued
OLS, IT: work continued
Dirt berm between OL tankfarm and landing pad growed, compacted with steamroller; excavtor compessed the west facing slope
OLS, PB: concrete forms removed
GSE3 aft dome barrel section moved into tent 3
NASA, Artemis: SpaceX's Starship selected exlusively for the development of HLS (Human landing system)
SN15 more TPS tiles added
NSF
Mary
LabPadre
15.04.2021
Deliveries at building site, steel hexagon delivery
Foklift stuck in gravel
OLS cranes moved, Bluto/Tz still near OL tank farm
BN2 fwd aft dome section moved (3-ring stack)
SN20 comn dome barrel? section spotted (3-ring)
SN20 fwd dome spotted
SN16 4-ring section lifted into mid bay for stacking
Raptor van picked up RSN56
GSE3 fwd dome section (2-ring and dome): pipes attached
Test nosecone rig: rods attached
2-ring section moved to scrap yard
OLS, PB: concrete poured
OL tank farm: work on third stand
Launch site: new signs ("Raptors loose")
LR11350 assmebly continued
Work on earth wall between OL tank farm and landing pad continued
High bay work continued, sections moved up
RC for Friday, April 16 cancelled
Progress on Phobos [Shane Overvold]
New RCs: prim Monday, April 19 (12-8pm); sec Tues-Wed, April 20-21 (12-8pm)
SN15 three Raptors delivered to launch site: RSN54, RSN61, RSN66
NSF
Mary
LabPadre
14.04.2021
SN15 pad A puck shucker (thrust simulation ram) removed
RCs cancelled
BN1 scrapping in high bay continued (eg. BN1 Booster Qund3 section, started 5 January 21, completed 12 Jan 21)
Test nosecone rig work continued
SN16 mid-lox section stacking in mid bay
GSE2 pipes added in mid bay
GSE3 MID #1, 4-ring section with lead-ins spotted [weld control shown]
Odd column structure delivered to launch site
OLS, IT: concrete forms removed
Roll-Lift 12000-1 crane near OLS tank farm (behind Bluto)
Tent 3 expanison work continued
Domes at prop prod site stacked on rings [diameter?]
Chick-fil-A delivery
SN15 work continued
NSF
Mary
LabPadre
13.04.2021
BN1 cut in half in the middle, bridge crane used (first time?)
BN1 scrapping continued throughout the day, stackes moved to scrapyard
Test nosecone work continued, hexagon added at the top
BN2? aft dome sleeved
OLS, PB: concrete forms added
GSE1 work continued
Blute/Tankzilla near OLS tank farm
SN15 more TPS heat shield tiles added
Stainless steel single ring moved inside prop prod site
GSE2 work in mid bay continued
Deliveries at building site (I beams)
LR11350: more parts arrived
New RC: prim 15 April ( 12-8pm), sec 16-17 April (12-8pm/7am-12pm)
RC today extended to 10pm
SN15 cryo test #2
NSF
Mary
LabPadre
12.04.2021
SN15 cryo test #1
SN16 section spotted with approx 960 heat shield tiles, biggest part covered yet
Test nosecone: work on rig continued
Tent 3: heat shield tiles attached to a nosecone barrel section
Tent 3 there are three 4-ring nc barrel sections in the tent
OLS work continued; piling east of OLM
OLS, PB: work continued
Work on wall between OLS and landing pad continued
OLS, tank farm: work at the base of GSE1
Tankzilla/Bluto moved around launch site
SN11 debris still being cleand up
New 3-ring dome sleeve spotted infront tent 1 and moved towards tent 3
LR1300 SX at the prop prod site
BN grid fins loaded onto a trailer
FCC application for 20km flight, refreshing permit for 11 April to 11 October 2021
NSF
Mary
LabPadre
11.04.2021
GSE2 final stack
OLS, IT: concrete forms removed
SN15 starlink antenna visible at the left side at the top of the tank section part
SN15 aft flaps opened
Tent 3: assembly of a new nosecone began
COPV delivery
OL Platform work continued
OLS, PB: rebar tied, first concrete forms removed
Work on wall between OLS farm and landing pad continued
SN11 debris still all over the place
Nosecone test rig: new poles added (delivered yesterday, see video), flap structure attached to pole
Cranes moved around at prop prod site (now two yellow and two red crawler cranes there)
SN20 leg skirt spotted
BN[2?] aft dome (with many holes) placed on sleeving stnad
LabPadre
NSF
Mary
10.04.2021
SN22 aft skirt spotted [Carter Goode]
BN2 [?] fwd dome sleeved
GSE2 tank moved into mid bay at 10:30
SN15 single user terminal request: SpaceX installed a Starlink antenna (dish) on SN15 and wants to use it on a flight NET April 20 for a flight test no higher than 12.5 km.
New info: recovery vessels
Dome pedestal delivered
Large ring section moved at the prop prod site
Work on GSE at prop prod site
Pieces for new LR1300 SX crane arrive [crane to build the big crane? - no, seems to be placed at prop site] [[429]]
Large propellant storage tanks now at prop prod site [see April 07]
Test nosecone work continued; lines attached to the black cap
OLS, PB: work continued (rebar), new structures between PB and tank farm
OLS, tank farm: preparation of second concrete stand for GSE2 tank (west of first stand)
OLS, IT: work continued on the tower foundation
SN15 work on aft section; hydraulic ram to be used for simulating Raptor engine thrust during a proof test
White beams delivered (522 and 523)
Tent 3 wall work continued
LabPadre
NSF
Mary
Carter Goode
09.04.2021
SN15 ambient pressure test
GSE2 tank attached to crane New SN and BN forward domes spotted [?], BN [2?] fwd dome on sleeving stand
Unknown GSE on SPMT
Prop prod plant progressed, two red l cranes and one yellow crane in the area (Liebherr)
Test nosecone work continued
SN15 no raptors installed, detached from crane, most heat tiles installled up to now
OLS, PB: building work progressed
OLS: cranes moved
Launch site: fencing delivered
Launch site: rebar placed for for a new earth wall between landing pad and OLS [?] [old wall has been upgraded]
Downcomer pipes loaded on truck
OL platform work continued
SN15 launch not yet approved by FAA [C. Davenport]
Hexagram spotted next to stress test nosecone
LabPadre
NSF
Mary
RGV
08.04.2021
SN15 rolled out to suborbital pad A
GSE2 tank onto another 4-ring section (now 12 rings)
GSE1 unhooked from crane
Blunt nosecone hydraulic ram lowered into it and it received a black tip (hat): stress test structure
OLS, IT: FAA info
OLS work continued
OLS, tank farm: smaller tank painted
LabPadre
NSF
Mary
07.04.2021
SN20 fwd dome spotted
A dome leeved with 2-ring stack [see 06 April]
BN thrust dome spotted with 40 holes on the outside (for 20 engines) and holes for 8 enginesin the middle, possibly for BN2/3
SN (higher) thrust dome with many holes (from earlyer testing) but fewer pipes spotted, with access ports for vacuum Raptor engines [433]§
OL platform work continued
OLS, power bay [PB]: work continued (rebar and concrete plates), red crane at this building
OLS, IT: concrete plates installed; yellow crane near it [LR1300]
OLS: more drilling near blast berm, rebar moved
GSE1 still attached to crane
LOX distiller work continued
White horizontal propellant tank delivered
New nosecone spotted behind tent 3
RC: prim April 08 (11-1.30)
LabPadre
NSF
Mary
RGV
WAI
06.04.2021
GSE1 lifted by Bluto/Tankzilla and placed on concrete stand
SN15 work
I-Beams delivered
Tent 3 work on outer wall continued
Dome inside tent 1, methane header tank outside tent 1 [?]
OL platform work continued
"Bigge" crane and tread parts delivered [LR11350?]
New GSE tank is called GSE2 [?]
Concrete foundation built at the restaurant (near intersection)
OLS: work continued
SN11 wreckage cleanup continued, suborbital pads seem cleared
New 2-ring stack spoted
New permits provided info about other sites
New RCs for SN15 roll out: Prim April 9 (7-12), sec April 12/13 (12-8pm)
OLS, IT: LR11350 assembly commenced
LabPadre
NSF
Mary
05.04.2021
Bluto/Tankzilla moved to launch site
SN15 not rolled out as originally planned [?]
SN15 work platform removed
SN16 nosecone barrel section "Nose Quad" with work platform spotted
Large domes at prop prod site outfited with pipes
OL platform work continued
SN11 still alot of debris lying around
GSE1 tank rolled out of mid bay, moved to new OL tank farm
RVAC 2 on horizontal test stand at McGregor
OLS, IT: concrete poured
LabPadre
NSF
Mary
04.04.2021
Tent 3 extention: new wall construction
SN16 [?] nosecone spotted in tent 3 SN15 still attached to crane, detached late in the evening
OLS tank farm: third concrete stand to be prepared
Thrust simulation ram installed on pad A, likely for testing SN15's new thrust puck design before raptor installing
SN15 slated to roll out on April 5
OLM last pillar trimmed
LabPadre
NSF
Mary
Anthony
03.04.2021
Tent 3 old wall removed
Work on new nosecone inside tent 3 continued
New GSE dome flipped (3-ring)
SN15 welding continued, work near aft flaps, aft flaps moved
BN3 aft tank #5 ring section (4-ring, with lead ins) spotted
New GSE tank: pipes attached (3 external pipes)
OLS, power bay building work continued
OLS, IT: work continued
OLM 5 out of 6 poles trimmed
New crane erected
Thrust simulation ram work conitued
High bay top: work continued
OL platform work continued
SN11 wreckage cleanup continued
RC for April 5, 7am to 12pm, Hwy 4 traffic, near Boca Chica Beach, may be intermittently delayed.
Thrust simulation ram moved to the launch site
LabPadre
NSF
Mary
02.04.2021
OLM: legs trimmed for OL platform
SN15 nosecone sections moved into high bay, while employees still worked on welding platform
SN15 aft flaps folded prior to stacking
SN15 nosecone work platform removed
SN15 nosecone sections stacked on tank sections (using external crane)
OLS, IT: new concrete plates placed
New GSE tank section stacked [see April 1]
New GSE fwd dome section (3-ring) moved [the one spotted on March 31?]
BN3 aft dome (3-ring) barrel section spotted
New stand moved by SPMT
Blunt nosecone, work continued on the top
New small dome structures delivered
Work on thrust simulator ram continued
14.3t counterweight delivered
RC due to bad weather (unrelated to SpaceX)
LabPadre
NSF
Mary
01.04.2021
OLS east building: confirmed to be Power Bay/Comms Building
Installing of the new cranes at launch site: yellow crane LR1300 rising, arriving parts of LR11350
RC for Friday cancelled
GSE 4-ring fwd dome section moved and later stacked onto another 4-ring section
Blunt nosecone has very special structures attached at the flap location
New aft flaps delivered
OL platform work continued
Parts for new crawler crane delivered
SN15 nosecone welding and work continued
SN15 work platform installed on top of tank section
Tankzilla/Bluto prepared for moving
New nosecone out of tent [?]
LabPadre
NSF
Mary
RGV
Date
Description
Source
Link
31.03.2021
BN3 common dome spotted
SN11 wreckage inspected and clean up; raptors landed near SH, legs spotted damaging the roof of an ATV
SN15 nosecone has been stacked on its barrel section
SN15 tank section moved out of mid bay
SN15 aft flaps installed
SN15 moved into high bay, many heat shield tiles installed
Road work between fence and hwy4 at prod site, new sun panels
New cranes delivered to launch site (yellow LR1300 max 300t, red LRT1220)
OLS, IT: concrete pouring
Blunt nosecone in structure received flap root addons [?]
New fwd dome spotted in tent, possibly for GSE
Road: opened at 5pm, but only for beach access until further notice
LabPadre
NSF
Mary
SPadre
RGV
30.03.2021
SN11 flight and RUD
Work on new nosecone in tent 3
OL Platform work continued
Tent 3 expansion: only front wall missing
RC: extended to March 31, 5pm
LabPadre
NSF
Mary
SpaceX
29.03.2021
SN11 scrubbed flight attempt
Blunt nosecone lifted into mystery structure
RC: primary March 30 (7am-3pm), Secondary April 2 (7am-12pm)
28.03.2021
TFR unl added for March 31
GSE1 moved into mid bay
SN15 nosecone prepared for stacking on barrel section
Blunt nosecone near mystery structure
BN3 fwd dome barrel section spotted
BN1 work in high bay continued, work plattform still up
Tent 3 expansion work continued
Small bridge crane infront tent 2 still worked on
OLS: east building work continued (rebar and concrete plates), earth work between landing pad and new tank farm
OLS, IT: work continued
Work on 4-ring barrel section with lead-ins
New TFR unl for Friday March 31
RC for March 29, 12-5pm, NOTMAR added until Thursday
Robotic arms delivered to the tent 3
LabPadre
NSF
27.03.2021
New GSE equipment spotted near huge domes
Crane detached from GSE 1 tank
Tent 3 extension work continued, now as long as other tents
New spot welder delivered
BN2 [?] aft dome with 8 raptor ports spotted in tent
OLS, Integration Tower: Concrete forms placed for the wall, rebar work continued
OLS, east building: Work continued with rebar and concrete forms
4-ring barrel section moved into tent
High bay work continued
Thrust ram work
Work on a fwd dome infront of tent 2
Gantry crane infront of tent 2
BN2 fwd dome moved
New TFR unl for Monday, March 29 and Tuesday March 30
LabPadre
NSF
Mary
26.03.2021
SN11 single enginge static fire
SN11 scrubbed flight attempt
GSE1 tank has been stacked onto GSE1 aft dome; still attached to crane
Blute/Tankzilla into old configuration
Scrap GSE dome section spotted
OL Platform work continued
SPMTs (blue) stacked with counterweights and connected, possibly for BN1 transport; other configuration than for SN transport
SpaceX, Musk: Monday next SN11 flight attempt
LabPadre
NSF
Mary
25.03.2021
SN11: RSN46 delivered and installed
SPMT moved Newly sleeved GSE dome moved
New nosecone infront of tent 3 now two flaps installed, assumed now for SN15, barrel section right aside
GSE1 aft dome flipped and moved, ring added like on SN7.2 [!?]
2 ring sectiono with fwd dome spotted [?]
Tent 3 expansion continued
Bridge crane installed
OLS work continued, vehicle integration tower beginning to grow with rebar being placed
Delivery of black structures
New forward dome with two rings stacked on another two ring stack that was seen yesterday right aside
GSE 1 tank attached to crane
Work on SN11 near access hatch
New TFR for Sunday (unl.)
Long term TFR shifted from 7200ft to 5000ft
RC for March 26 from 7am to 7.30pm, sf and flight indicated
Mary received alert notice
LabPadre
Mary
NSF
24.03.2021
SN11: Raptor removed and moved to the build site at 5am for repairs
Tent 3 expansion continued Work on new nosecone outside tent 3 continued, second flap installed
Work on new nosecone inside tent 3 continued
GSE 1 fuel aft dome spotted infront of SN16 aft section (including leg skirt)
SN16 aft section moved into tent 1
Bridge crane installing continued
OL platform work continued
GSE tank dome on sleeving stand and sleeved later
Pipe stands delivered
High bay and bridge crane work continued
Concrete work on driveway entrance at the launch site
OLS new building work continued
OLS tower construction started
New TFR for Saturday
LabPadre
Mary
NSF
23.03.2021
New TFR for Fr 26 March
New noseone with one flap moved out of tent 3
BN1 disconnected from crane, moved inside the high bay, possibly to make place for bridge crane installing
Delivery of white structures
Tent expansion continued
OL platform work continued
SN11 pressure test, vents
OLS: building in the east continued
Section of bridge crane lifted and lowered again, installing continued
New platform delivered
New nosecone attached to crane, second flap not yet installed
NOTMAR for March 24-26
RC for tomorrow cancelled
Now there are 6 of the huge domes
New foundations at the gas well site
OLS: integration tower stated to go up
RC for Thursday removed, TFR for Wednesday and Thursday removed
LabPadre
Mary
NSF
RGV
22.03.2021
SN11 Static fire #2, some TPS tiles damaged
SN11 FTS installed, work in skirt area
GSE 1 LOX/fuel work continued, piping installed
"Mystery" structure: work continued
Delivery of green hardware
4 Flap aerocovers (where the flaps are attached) delivered
Tent 3 expansion progressed
OLS: work continued, especially in the very east
SoLS: More concrete work near ramp and landing pad
New nosecone barrel section infront of tent 3: work plattform added
TFR added for Thu 25 (unl.)
RC and TFR for 23.03. cancelled, Thursday rc changed from possible to scheduled
RC added for 23.03. from 12pm to 1pm
LabPadre
Mary
NSF
21.03.2021
TFR added for Wednesday 24 (unl.)
Blunt nosecone stacked on additional 4-ring section, now 8 rings (first time procedure!!!)
Progress on OLT (OL tower): fundament seems ready, berm around landing pad moved?
Mary received alert notice
BN1 still attached to crane
SN11 RCS thrusters tested, excess pressure vented
OLS: work continued (rebar...), piling machine now west of new tank farm
SoLS: ramp looking finished
Tent 3 expansion progressed
Pad prepared for concrete (no rebar yet) at the northeastern end of the construction site
LabPadre
Mary
NSF
SpaceX Updates, Spaceport3D
20.03.2021
Smoke at production site, fire?
SN11 flaps/fins tested
Nosecone in tent 3 has both fins installed
GSE 1 LOX/fuel tank work continued
OL platform work continued
Tent 3 expansion work continued
OLS: new building started to grow in far east corner
New "mystery" structure: wokr coninued
GSE 2 tank midsection (MID #2) spotted (4-ring stack)
Blunt nosecone attached to crane
TFR for Tuesday 23 (unl)
NASA astronauts visited SN11
LabPadre
NSF
Mary
19.03.2021
GSE 1 LOX/fuel tank moved out of midbay and stacked (8 rings + dome onto 4 ring stack)
New "mystery" structure: cross bars installed between white poles
Flap installed on nosecone in tent
Work on tent 3 expansion continued
Nosecone barrel section infront of tent 3 has heat tiles installed
Sn2 on concrete stand: water tower?
BN1 work continued
New rc: Mon&Wed primary 7-15; Tues&Thurs secondary 7-15
LabPadre
NSF
Mary
Jack Beyer
18.03.2021
Tankzilla/Bluto upright
BN1: LOX tank stacked on CH4 tank (full height now visible), LOX tank previously was cut off from its bottom ring, thus BN1 now one ring short [?]
Nosecone barrel section with platform and lead-ins infront tent 3, nosecone moved into tent 3
New 4-ring barrel section with lead-ins on stand infront of mid bay
OLS: formwork removed from second concrete stand, piling continued, SoLP ramp work continued
Domes moved, 3-ring stack moved into tent 1
More beams attached to white poles structure
TFR added for Sunday
FAA on environmental review: "A total of 231 comments were received," with concerns including impacts on protected species, closure of public areas, & more
TFRs later removed
LabPadre
NSF
Mary
Michael Sheetz
17.03.2021
Unknown parts delivered
White poles connected on the top
Repair work on Hwy 4
OLS: work on the far east area taking up with rebar preparation, as well as piling; formwork removed from first concrete stand
Concrete work at SoLP ramp
Stainless steel rolls delivered
Tankzilla/Bluto extension installation finished
High bay work continued
Bridge [overhead] crane (not gantry crane) arrived for high bay, capacity 180 tons, unloaded
Prod prod site work continued, scaffolding around some side tanks
Oil cooled transformer delivered
TFR added for Saturday
LabPadre
NSF
Mary
16.03.2021
SN18 aft skirt and engine section now mated (5-ring stack)
Tent 3 expansion continued, insulation installed
White poles (6) attached to the new stand structure, unclear what this is for
BN1 work platform and lead-ins attached for stacking LOX tank on CH4 section
High bay work continued
Robotic welder working inside tent
OLS work continued, piling machine now east of the new tank farm, earth work in the south of the landing pad, work on SoLP ramp continued
Tankzilla/Bluto extension installed, crane mats moved
FAA license modification: now requiring a safety inspector to be present for launches
TFR added for Friday
Phobos: removing the tower and large section of the accommodations started
LabPadre
NSF
Mary
Michael Baylor
BigBoatDriver
15.03.2021
SN11 static fire attempt, assumed abort
Bluto/Tankzilla moved from pad to high bay, probably for BN1 stacking, laid down; extension for the crane moved
SN11 FAA aproved SN11 flight
TFR added for Wednesday 17th and Thursday 18th
Closure extended to 3pm, but not used
Mary received alert notice for tomorrow SF testing
OLS tank farm: concrete poured in circular forms
Huge pipes and rings with holes delivered to production site
H-Beams welded to the OL platform
SN7.2 moved back to production site, status unclear
Work between road and fence at production site continued
Argon delivered (for welding)
Beams liftet on top of the high bay
LabPadre
NSF
Mary
14.03.2021
SN11 venting at 03:47:30 am
New piling spotted, 2 rows of totally 9 piles, south of landing pad
Work on ramp to pad A continued
SN7.2 work continued
Work on prop prod site continue
BN1 work platform installed for stacking LOX sections on CH4 sections
[SN15] nosecone has flap actuators, but no flaps yet
Aft dome spotted, unclear if new or old practice dome; appeares to have raptor vacuum engine mounts
Work on OLM table continued
Mary received alert notice for tomorrow SF testing
GSE tank section moved into mid bay
LabPadre
RGV
NSF
Mary
Jack Beyer
13.03.2021
New rc for Mon 15 March 6-12, unlim. TFR for Tues 16, TFR for Mon cancelled
SN11 work on aft section and other parts, access hatches opened
Work on starhopper camera equipment
OLS work continued
Panels: GN2 recharge (gaseous nitrogen), probably stored at 200 bar; GCH4 recharge (gaseous methane), probably stored at 400 bar
X ray inspection of new tank farm plumbing at OLS stand
BN1 work continued
Aft skirt section in tent 1, unknown SN, with many TPS tiles
Forward dome cap delivered
LabPadre
NSF
Mary
Jack Beyer
12.03.2021
SN11 scrubbed static fire attempt
Mary received overpressure notice, 7-12
BN1: methane tank sections (lower part) including common dome section stacked on engine section
Bluto moved away from SN11
Tent 3 expansion began
New three ring stack spotted in tent
GSE 1 LOX forward dome spotted (dome and 4 ring stack)
Crane mats moved to high bay
Condenser like equipment delivered
Work on prop prod site continued
GSE tank (dome+3 ring stack) flipped
Tankzilla/Bluto put on SPMTs
Loud venting warning:
SN11 vents from LOX and CH4 tanks
LabPadre
NSF
Mary
11.03.2021
SN11 cryo proof test
Mary received a overpressure notice, but seemed wrong
Work on huge domes continued
BN1 Booster double section moved into high bay, stacking imminent
New stand under construction
Bulkhead moved to scrap yard
Launch table work continued
New nosecone spotted in tent 3
New barrel section outside tent 2
OLS: much work, also in the very eastern part, two stands nearly ready for concrete
SN10 cleanup continued
Concrete work near suborbital pad A
New white propellant tanks at gas well
SN16 4 ring section now spotted in mid bay
LabPadre
NSF
Mary
RGV
10.03.2021
SN11 testing: aborted
SN11 work at the base
Baker industries delivery
OLS: Two vertical ropellant storage tanks erected at the launch site, right west of the bunker (white tank and black tank)
OLS: Control panels installed on roof of bunker (400 bar storage, GCH4 Recharge)
Concrete work near landing pad continued
Firework: SpaceX festive activities at build site
LabPadre
NSF
Mary
09.03.2021
SN11 Ambient temp pressure testing
SN11 now mounted on pad B, crane disconnected at 11:54 am
Work on top of the high bay coninued, rail sections installe
Thrust rams installed, probably for testing BN1
Raptor SN59 delivered
OLS work continued
Huge black ground piles placed [near launch mount, where piling work has been going on for some weeks]??
Tankzilla lowered
Flap delivered [in video of 10 March]
LabPadre
NSF
Mary
08.03.2021
SN11 roll out to pad B
New road closures: Primary March 9 (12-8pm), Primary&Secondary March 10-12 (12-8pm/7am-12pm)
Concrete at landing pad??
SN10 wreckage almost cleared
OLS: Piling work near the OLM, possibly for tower?
LabPadre
NSF
Mary
07.03.2021
BN1 section "Booster double" (Aft dome sections+ 2 ring stack) moved onto new heavy stand
SN20 Leg skirt spotted
SN11 and BN1 changed places in high bay
New dome still on sleeving stand
SN18 Leg skirt spotted
SN10 wreckage cleanup continued
OLS-Pad A, rebar for a pad at the far east side prepared
OLS work continued, earth wall (blast berm) extended between landing pad and new tank farm
LabPadre
NSF
Mary
06.03.2021
New dome now sleeved
New section to be lifted into mid bay
OLS work (tank farm) continued
SN10 wreckage scrapped
Bluto/Tankzilla moved next to pad B
Raptor SN58 delivered, message "Much Land Where Box"
Earth work between road and fence at build site
GSE-1 fule fwd dome moved out of tent
New heavy stand moved by SPMT towards high/mid bay
Job posting for Superheavy catch arm development
New site development plans
NSF
Mary
LabPadre
05.03.2021
SN15 tank section now stacked on the skirt
Another huge dome spotted
Phobos renovation has started with deconstruction of the tower
Parts for new Puck Shucker arrived
[SN15?] nosecone moved, possibly not anymore slated for SN15
GSE-1 forward dome placed on a cart and moved into tent 1
New 2-ring sections moved
GSE-2 LOX aft dome moved from sleeving stand
Delivery of long white piles[?]
Raptor engine 5? delivered
SN11 prepared for rollout
New dome [fwd?] placed on stand
[SN17/18] Scrap aft skirt with leg deployed
SPMT rolled to build site
LabPadre
NSF
Mary
RGV
04.03.2021
Crane weights moved to pad
Access stairs moved to pad B, sign for SN11 roll out soon
Bluto/Tankzilla moved to launch pad (9:24 am, arrived at noon), SPMTs later returned
Closure cancelled for Friday 05 March, then back on, later moved to Monday, March 8, 9:00 am to 11:30 am
[SN15?] nosecone work continued
SN10 wreckage inspected, cleanup began
SN10 leg pulled from the dunes
SN7.2 work continued, new layer of welding put on the bottom ring
GSE-2 LOX aft dome ready for sleeving, sleeved later on
Work on OLM table continued
LabPadre
NSF
Mary
03.03.2021
SN10 flight, landing, RUD
Closure extended until March 04 at 8:59 am
SN15 aft skirt moved into mid bay
New nosecone at the other side of the tent (SN15?)
LabPadre
NSF
Mary
Others
Many other videos
02.03.2021
Mars landing sites downselected to 3-4 locations with 3 backup locations
Mary asked to evacuate for tomorrow flight attempt
Road closures set up for Wednesday, 2 backup closures
New starship renders for dearmoon mission released
Concrete work between road and container wall at the suborbital launch site
OLS work continued: rebar laid north of new tank pad
Crane weights moved to launch site by SPMTs, transferred to onto a trailer
Idea of city of Starbase rised by Elon Musk
LabPadre
NSF
Mary
01.03.2021
TFRs now for Wednesday-Friday
SpaceX received a contract for thermal protection system manufacturing
Tomorrows closure cancelled
Red SPMT headed for SN5
Delivery at production site
SN5 scrapping continued, remains moved to scrapyard
Assembly of OLM table continued, welding the parts together
New stand being built
Highway 4 roadwork in front of tent
New nosecone section stacking started [not yet with new parts]
Highbay elevator now operational
SN10 RCS Test at 02:31 am
LabPadre
NSF
Mary
When it is written about the OLS tank farm, some suggested that it also could be a starship stacking site. Diameter of foundations would match and plans released earlier would also indicated so. Furthermore, pipes go round this structure.[2] However, local workers confirmed a tank farm, matching newer plans by SpaceX.[3]
Date
Description
Source
Link
28.02.2021
Concrete next to nose cone assembly tent removed, perhaps for tent extension
Mary been noticed to evacuate tomorrow for possible SN10 launch attempt
NOTMAR published for 1-5 March
Later, SN10 flight delayed to NET Wednesday, March 3 (perhaps due to weather)
SN10 FTS installed
Raptor SN47 delivered, message "Wen Hop? Much Wow."
OLS work continued with both eastward and westward extension (in reference to circular structures north to the bunker); rebars being tied
New flap delivered
Unknown dome moved
BN1 stacking continued
SN15 nosecone stacking continued, still attached to crane
Piling continued in the south of the launch site, near OLM
SN10 methane vent
New ring section spotted in the tent
Roadclosure for tomorrow cancelled
RGV
Jack Beyer
NSF
Mary
27.02.2021
Pavement expansion at the high bay
OLS work continued, tank farm taking shape
SpaceX logo painted on landing pad; hopefully not to be destroyed soon...
Work on BN1 in high bay
SN10 upper flap testing
NSF
Mary
LabPadre
26.02.2021
New unlimited TFRs for Monday-Wednesday March 1-3
Raptor "Under Doge" delivered
Pipes delivered
OL Table work continued
GSE 1 forward dome sleeved [for OLS tank farm?]
Raptor SN56 left the build site
Possible aerocovers delivered
[SN17?] thrust section moved
OLS work continued
30% completion of south port connector road
LabPadre
NSF
25.02.2021
SN10 static fire #2
TFR for today removed, one added for Sunday
SN15 nosecone being stacked, nose section still without its head
OLS work continued
New barrel section moved
Additional ring pieces for supposed launch table moved
New? thrust puck spotted
Alert notice given to Mary for Feb 26, but road closure cancelled
LabPadre
NSF
Mary
24.02.2021
SN10: One Raptor removed and a new raptor
SN51 installed
New elements added to orbital launch table
Dome work continued at old gas well, solar panels being installed nearby
New forward dome sleeved, unknown SN
Forward flap delivered
OLS work continued, concrete foundation to be extended eastwards
SN18 forward dome barrel section moved around
Concrete poured near production site
Zeus, SpaceX robotic dog by Boston Dynamics, walking around
Closure of today cancelled
Alert notice given to Mary for Feb 25
3 engine tests at McGregor within 45 minutes
NSF
Mary
LabPadre
23.02.2021
SN10 static fire #1
New unlimited TFRs for Thur-Sat Feb 25-27
New road closures for Friday, Moday and Tuesday
Elevator being added to high bay
SN5 dismantling continued
Raptor engine SN52 delivered
Raptor engine SN43 sent back
BN1 4-ring section "Booster #2" ready infront of high bay
SN17 thrust dome sleeved
New forward dome placed on stand
LabPadre
NSF
22.02.2021
SN10 scrubbed static fire attempt
SN10 got approved for flight by FAA (launch license modification granted)
OLS: more concrete poured
SN12 common dome scrapped
SN17 thrust/common? dome ready for sleeving
SN5 dismantling continued
New TFRs for Tuesday-Thursday, different TFR shape
Closure for Thursday added
At least 3 engine tests at McGregor on low throttle
Alert notice given to Mary for Feb 23
NSF
Mary
LabPadre
21.02.2021
SN15 nosecone barrel section attached on crane
Concrete poured on landing pad
Domes built at the prop production site, bigger diameter than usual, usage unclear
OLS: rebar work
SN10 aft fins inspected and tested
New thrust puck spotted
MK2 stand coming down
Alert notice given to Mary for Feb 22
NSF
Mary
20.02.2021
SN15 nosecone has fin jigs attached, top cone part removed
OLS: concrete being poured at an outer wall and more dirt wirk
SN10 work on engine section and near the hatch
High bay stairs continued to be removed
Thermal protection tiles being installed on the whole barrel section of a future prototype
Concrete work at the production site
NSF
19.02.2021
SN18 potential forward dome on stand ready for sleeving
OLS work continued
SN10 venting
Several parts in storage: common, forward and aft domes and methane header tanks
SN19 methane header tank spotted (now 3 mht ready)
BN1 section rolled out for stacking, scaffolding errected, moved into high bay
BN1 pipe dome (common dome) ready for stacking
Aft dome moved onto sleeving stand
Work on high bay with crane, security stair deconstruction
SN9 final parts removed
New closures for Mo-Wed Feb 22-24
FAA closed the investigation of SN9 mishap
NSF
LabPadre
Jackie Wattles
18.02.2021
OLS work continued despite bad weather conditions
SN10 static fire not before Monday 22
High bay crane horizontal again
NSF
17.02.2021
SN15 nosecone section attached to crane, moved out of tent and later detached
SN10 static fire delayed, probably due to bad weather, aft flaps moved
SN9 wreckage cleanup
OLS work continued
Sections spotted: SN18 Nosecone barrel section, SN17 aft dome
New OLM structure supposed to be a Superheavy launch table (Support structure baseplate, NASA term, WAI)
New unlimited TFRs for Feb 19-21, but later removed
NSF
LabPadre
16.02.2021
SN11 second aft fin installed
OLS work continued, dirt work, rebar work continued in circular shape for new tank farm
Black steel section spotted at the build site, unclear application
Work on prop plant continued
New crane waiting for work on high bay
Stands being moved around
Alert notice given to Mary for 17.02.
NSF
Mary
15.02.2021
Cold weather in Texas, SN10 currently in a hold
Aft fin delivered, probably for SN15
SN11 second aft fin awaiting to be installed
More parts delivered for possible OLM structure
NSF
14.02.2021
Work on OLS continued (new tank farm and GSE bunker)
SN7.2 still on stand with scaffolding
SN9 cleanup continued
New crane assembled at build side near high bay
Grid fins delivered, possibly for Superheavy
Raptor SN27 returned (previously used for SN5 hop)
NSF
13.02.2021
Propellant prdouction site progress
Work on OLS and suborbital landing pad continued
NSF
LabPadre
12.02.2021
Closure cancelled early in the night - no SN10 static fire attempted
OLS: Circular concrete foundations started, probably for new fuel farm
OLS: Piling work southwest to the OLM, perhaps for stacking tower?
SN14 aft dome used as pathfinder
Parts supposedly attributed to the OLM moved
Flap related parts delivered
Repair on landing pad continued
LabPadre
NSF
11.02.2021
SN9 cleanup continued
Work on OLS
Work on widening the suborbital launch pad; new layer of concrete will be put ontop of it
SN11 has received one aft flap, removed from crane and then rotated
SN16 aft skirt and thrust section mated
Concrete work at the construction site near fence
Huge steel componoents deliverd, some suggested being for the OLM
Elon Musk interview
Closure cancelled: SN10 stood down from static fire attempt, new alert notice for 12.02. given to Mary
Interview with Elon Musk on the Joe Rogan Experience
NSF
LabPadre
Mary
Joe Rogan Exper.
10.02.2021
All unlimited TFRs cancelled
SN10 flaps folded
Repair work began at the landing pad after SN9 RUD
SN16 aft dome ahas been flipped and moved
SN16 leg skirt spotted
New nosecone barrel section ready for stacking [SN15?]
Simple roof installed at the OLS bunker
Closure for 11.02. extended, alert notice given to Mary
FAA
Mary
LabPadre
NSF
9.02.2021
OLS: Concrete work between the shelter and the road
OLS: Steel added to the bunker/shelter to protect Ground supply equipment
BN1 aft dome sleeved
SN7.2 still being worked on
SN9 wreckage not yet removed
Build up of container wall at the test site continued
Work progress on the propellant production plant
Wednesday closure cancelled
NSF
CC
8.02.2021
TFRs added for Wednesday, 10 February (up to 7200ft) and Thursday 11 to Saturday 13 Feb (unlimited); deleted; Thursday TFR reinstalled
TFR (standing) moved up to 7200 ft (until March 31)
SN10 Cryo proof test
SN11 crane still attached
BN1 aft dome sections ready for sleeving
FAA
NSF
7.02.2021
SN11 nosecone section moved to highbay and stacked later
SN17 forward dome sleeved
SN10 flap movement, FTS installed and removed again (fit check)
New pipes at the OLS
Delivery at the construction site
New rings in tent
BN1 practice thrust dome moved around
BN1 aft dome lifted on sleeving stand
LabPadre
NSF
6.02.2021
Third Raptor (SN39, removed from SN8) installed on SN10
More ground equipment for the OLS shelters deliverd (piping)
SN9 wreckage cleanup continued
SN7.2 inspection
Work on Starhopper systems
FTR added for Monday, 08 February up to 7200ft
LabPadre
NSF
5.02.2021
SN11 rolled out of Mid Bay at 10:46; arrived at 11:20; big area covered with heat shield tiles, no aft fins yet
Second? Raptor (SN50) delivered for SN10 at 08:21, later installed
Road Closures for 8.2. and 10.-12.2. announced
Work at the OLS continued after a break due to SN9 launch
BN1 aft dome sleeve spotted (aft dome spotted on January 25)
Ground equipment delivered for OLS shelters (pipes)
Scaffolding around SN7.2 and inspection
New nosecone spotted with fin mounting jig installed (top missing)
LabPadre
Mary
NSF
4.02.2021
SN7.2 Second preassure test: SN7.2
SN5 top section removed
SN11 both nosecone sections welded together (fins already attached)
BN2 forward dome spotted
SN18 forward dome spotted
LabPadre
Mary
NSF
3.02.2021
New thrust dome sleeved
SN16 leg skirt moved
SN5 dismantling begins
Metal ring flipped
SN11 nosecone welding continued
SN5 mass simulator removed
SN5 battery pack removed
SN9 wreckage inspected and cleanup began
New forward dome on sleeving stand (probably SN 17)
NSF
2.02.2021
SN9 launch
SN15 top dome section stacked in Mid Bay
SN16? thrust dome sleeved
LabPadre wiki
other
1.02.2021
SN16 Nosecone Barrel Section spotted
New Nosecone Section spotted
New Crane positioned near OLS
Concrete work on OLS
BN1 Common Dome flipped
Raptor delivered for SN10
NSF
Date
Description
Source
Link
07.01.2021
[457 - 18.04.]
NSF 2020 recap (video here)
SN15 common dome section with a row of TPS tiles on each ring attached to crane; moved for further stacking in mid bay
RSN45 delivered to production site
OLS work continued: earth work between bunker and hwy 4 for future pad [add: OLS tank farm]
SoLS Pad A: concrete being removed
Helium truck trailer at launch site [NSF: SpaceX uses helium to pressurize the tanks, but works towards autogenous pressurisation]
SN6 dismantling continued, it won't be the HLS mockup; likely the space will be needed for something else; rings cut off and removed
Mk1 disassembly continued, upper part attached to crane and moved away
Stainless steel delivered
Driveway work behind mid bay (towards hwy four) continued in order to enlarge the entrance to the production site
Sleeved dome section removed from sleeving stand (4-ring)
SN9 work continued after yesterday's static fire (thought to be off-nominal)
Propellant deliveries to tank farm
Work on a ring "Top porrel, Booster Dev, Do not scrap, Bevel Bottom"
NSF
Mary
06.01.2021
SN6 mass simluator removed, SN6 speculated to be used as future HLS prototype
Nosecone in tent 3 lost its tip [SN11 nosecone?]
OLS earth wrok continued, as well as concrete being poured; work on ground piping on the east end; pad being prepared between bunker and hwy 4
SN9 launch NET 8 January, preparation work continued
SN15 common dome spotted (3-ring with lead-ins) and worked on external pipes/walves
SN10: Crane detached from SN10 nosecone
Mk1 scrpping continued
New thrust dome (same as yesterday) seen
SN9 static fire (Video here); rather short static fire of about 1.5 secs, followed by double depress vents and nosceone vent, condensation on CH4 tank slowly disappearing; final depressurisation vents;
NSF
Mary
05.01.2021
Red/orange parts delivered to launch site
OLS earth work continued; ground piping work at the east end of tank farm
TFRs sheduled for SN9 launch
SN9 work continued on several areas
Sleeved starship fwd dome (1-ring) shown
New starship thrust section spotted [unknown SN]
Fwd dome has been sleeved with a f
SN11 nosecone moved back into tent 3
4-ring barrel section moved out of tent 3
Tapered section ready to be stacked
Barrel sections spotted: SN15 nose cone barrel, SN16 mid-LOX, SN17 fwd dome barrel (all 4-rings ?)
SN8 remains being broken up and removed
SN10 speculated to roll out as early as next week
Mk1 attached to crane and cut in half, upper part removed
NSF
Mary
04.01.2021
No video
03.01.2021
SN8 nosecone: fwd fin attached to crane and removed by crew; transported away
Landing pad: Rebar work on cut out section
Thrust dome section sleeved (3-ring), next to a 2-ring thrust dome section [SN12/SN13??]
Nosecone spotted in tent
SN10 nosecone welding work continued in high bay
OLP work continued
SN9 work continued on Pad B, four man lifts work at engine section
NSF
Mary
02.01.2021
Emmert international heavy transporter moved away
SN10 worked on in high bay; crane attached to nosecone, nosecone lifted and stacked onto tank section later
OLS work continued: around OLM
Shipping containers moved near OLP by crane
LN2 delivery to tank farm
SN9 worked on, LOX access hatch open
NSF
Mary
01.01.2021
Launch site work continued; SN8 nosecone wreckage lying around
OLS work continued, especially on ground and eargh work; excavators working near the landing pad
Pad B / SN9: work on engine section
Mobile office building moved on an SPMT, later offloaded near the tank farm, adjacent to the container building row
Equipment moved by SPMT at launch site
SN10 tank section in high bay, awaiting stacking of nosecone
SN11 tank section fully stackied in mid bay
NSF
Mary
Date
Description
Source
Link
30.12.202
Flaps delivered to producition site [SN10?] [vid 01 Jan 22]
Date
Description
Source
Link
29.03.2019
Starhopper testing
NSF (first youtube video)
https://www.youtube.com/watch?v=iOv34Tfabng
Date
Description
Source
Link
29.03.2019
Starhopper testing
NSF (first youtube video)
https://www.youtube.com/watch?v=iOv34Tfabng
Date
Description
Source
Link
29.03.2019
Starhopper testing
NSF (first youtube video)
https://www.youtube.com/watch?v=iOv34Tfabng
Date
Description
Source
Link
29.03.2019
Starhopper testing
NSF (first youtube video)
https://www.youtube.com/watch?v=iOv34Tfabng
Date
Description
Source
Link
29.03.2019
Starhopper testing
NSF (first youtube video)
https://www.youtube.com/watch?v=iOv34Tfabng
Date
Description
Source
Link
29.03.2019
Starhopper testing
NSF (first youtube video)
https://www.youtube.com/watch?v=iOv34Tfabng
Date
Description
Source
Link
29.03.2019
Starhopper testing
NSF (first youtube video)
https://www.youtube.com/watch?v=iOv34Tfabng
NOT DONE YET: [508]
Mk1 and Stack #1
[509] (Mks, Phase 2 orbital prototypes) - still to add
Date
Description
Source
Link
31.05.2019
More black beams added for new building
The other building [see May 19] now sealed up in white
Work on landing pad (LabPadre pad B)[510]
SH: Work under skirt
RC now June 4-6 (2-8pm)[511]
RCs changed again: RC now June 11-13 (2-8pm)[512]
Austin Barnard
Reagan Beck
Mary
below
30.05.2019
SH: Work under skirt
Close-up of Pad B [landing pad][513]
LabPadre: Elon Musk at launch site
Build site: beams for a new structure went up
Hurricane talk
NSF, Mary
LabPadre
below
29.05.2019
SH: Work under skirt
below
28.05.2019
NSF article
Testing now June 3-5, (2-8pm)[514]
NSF, Mary
Mark Reagan
below
27.05.2019
Refrigerated liquid natural gas delivered
Flare stack burning
NSF, Mary
below
26.05.2019
SH: Lower access port closed
NSF, Mary
below
25.05.2019
SH: Upper access port opened
SH: Upper access port closed, lower access port opened
NSF, Mary
below
24.05.2019
SH: Cryo pressure test with nitrogen venting [516] stream at 16:35 ablut 1.5 hours showing tank farm venting[517] ground vent (grass vent) observed ([518], [519], [520])
New RC for May 28-30 (2-10pm)
LabPadre on flooding issues
RCs canceled later: "Beach closures are no longer planned for the week of May 28. SpaceX is planning to proceed with spaceflight activities that will require closures the week of June 3. To support those closures, SpaceX will establish a safety zone perimeter in coordination with local law enforcement that will include temporary closures of Highway 4 and Boca Chica Beach. Cameron County has established a hotline for road closure updates (956-548-9541), and public notices will also be available on this page."[521]
NSF, Mary
LabPadre
Chanadian
below
23.05.2019
SH work continued under skirt
SH: Upper access port closed
Stack #1 work continued [Mk1]
NSF, Mary
below
22.05.2019
Dirt trucks have arrived again
Compressed Methane Tankers arrived at 9:31 am
SH: Thruster pods have been numbered (65 upper, 87 lower)[522]
NSF, Mary
below
21.05.2019
A lot of trucks at the site: at least 12 dump/gravel trucks, tankers, heavy equipment [523]
Dump trucks delivered gravel to the east of launch site [524], dirt work, according to LabPadre "Pad B" [Landing Pad future]; control panel "Stand GN2 & Pneumatics Isolation* spotted[525]
SH: New hole, pipe installed from it [see Plasma cutting, Friday, May 17]
FCC application for SH: "The vehicle will fly vertically from the ground to under 500 meters for its low-altitude tests and up to 5000m for its high altitude tests."[526]
SH: Black fuelling structure now connected with SH "Quick disconnect system"[527]
LapPadre (Luis) plans to make a camera feed
SH: Lower access hole closed
Elon Musk tweeted
Stack #1 full nosecone close up
NSF, Mary, Chanadian, FST
LabPadre
below
20.05.2019
SH: Roll-lift equipment gone under SH, shiny foot added; new parts attached to the left and above the upper access port
Stack #1: Nosecone tip stacked to the rest at build site [Mk1][529]
NSF, Mary
LabPadre
SPadre
below
19.05.2019
Build site: black beams now in place for a new tent
SH: raised higher
Concrete barriers were removed
LOX and LN2 delivered
New yellow crane on site (Howell crane & rigging, inc.)[530]
Work on black structure continued
Work on stack #1 continued [Mk1][531]
Label on white tanks farm tanks: Liquid Nitrogen 60,000 litres, Liquid Oxygen 60,000 litres [532]
One black metal structure moved under SH, under the plumbing shelf
NSF, Mary
Austin Barnard
LabPadre
below
18.05.2019
LN2 Delivery
Moon over Starhopper
SH: New parts attached to leg
Roll-lift equipment has been delivered to the launch site
SH: Lifted off the ground by roll-lift equipment
NSF, Mary
SPadre
[533]below
17.05.2019
Black metal structure now lifted to an upright position
SH: Work in the skirt; plasma cutting
SH: Metal plates with holes attached on the legs; tethers have been removed, [534]
SH: Acetylene torch cutting through SH from insede
NSF article on Starship construction in Florida, possible launches from Launch Complex 39A at Kennedy Space Center; Elon Tweet about suborbital launches (single stage to orbit question)
LabPadre stream
NSF, Mary
LabPadre
below
16.05.2019
NBC news report with LabPadre, Ramiro Gonzalez and others; mentioning tourism and Static fires. "Launch site was created in 2015 with nearly 300000 cubic yards of dirt that was brought in to build up this launch site."
LabPadre
NSF, Mary
below
15.05.2019
SH: tapes removed from the ACS pods, wiring
More work on SH
Elon Musk: Raptor updates and other tweets about Cidco Rd. Florida
New hardware attached to black metal structures
NSF, Mary
SPadre
14.05.2019
SH: New part spotted at the SH skirt
Round 2 of SpaceX tests at Boca Chica scheduled to begin May 28 - 2-10pm
New RC: May 28 2-10pm
Welding on stack #1 [l:Mk1][536]
Cidco: 4-ring stack under construction at 850 Cidco Road, Cocoa, Florida [Mk2][537]
NSF, Mary
Reagan Beck
LabPadre
below
13.05.2019
SH: work on thruster pods
John Randolph
12.05.2019
"Based on Florida Department of Environmental Protection (FDEP) public records, I think we have three possible locations. Here they are: Space Exploration Technologies DBA Starship Tile Facility 8550 Astronaut Blvd Ste E Cape Canaveral Space Exploration Technologies - Cidco Road 850 Cidco Rd Cocoa Space Exploration Technologies Inc 550 Cidco Rd #1 Cocoa"[539]
NSF, Mary
below
10.05.2019
SH: new plumbing on the fin
SH: lighitng bolt under skirt
NSF, Mary
LabPadre
below
09.05.2019
SH: work continued [540] [541]
Lower nosecone part now stacked on 8-ring section #1 on concrete stand upper part has received its tip[542][l:Mk1]
Work on one satellite dish
NSF, Mary
SPadre
below
08.05.2019
SH: COPVs attached to the dome
NSF, Mary
below
07.05.2019
SH: more stainless steel sections cut out, ACS pods attached (thrusters of the attitude control )
NSF, Mary
below
06.05.2019
SH: other section of scaffolding erected
Black structures delivered
NSF, Mary
below
04.05.2019
New tank moved and placed behind the other two white vertical tanks (behind black recondenser?)[543]
Other smaller tanks delivered
SH work continued with scaffolding erected
LabPadre
NSF, Mary
03.05.2019
SH stainless steel exterior sections cut out
NSF, Mary
below
02.05.2019
SH upper hatch still open
New white propellant tank delivered to launch site
NSF, Mary
01.05.2021
SH work under skirt, access hatch open
New GSE at the tank farm
New nosecone work progressed [l:Mk1]
Some sort of deluge system installed
LabPadre
Date
Description
Source
Link
30.04.2019
Concrete forms of the expanded pad removed
Some fencing and concrete barrier removed at launch site, possibly for new access gate
NSF, Mary
below
28.04.2019
Raptor SN3 tested at McGregor for 40 second
NSF, golosio, Reagan
below
27.04.2019
Elon Musk tweets
Concrete poured at launch site (near the pad)[547]
NSF, Mary
below
26.04.2019
SPadre installed live on Starship cam
Chanadian indicated the area where dirt has been dumped yesterday (in the east adjacent to the SH pad)[548], indicating a expansion of the pad area
NSF, Mary
FST
Chanadian
25.04.2019
Big delivery at the launch site, some 18+ trucks seen
Crane operation spotted behind SH launch pad, crane left at 11:45
Earth work east of hopper continued
Later, 21 more truck loads have been spotted
Police on Hwy 4 in front of Hopper with flashing lights
Long white objects arrived and unloaded by crane [550]
NSF, Mary
Chanadian
LabPadre
below
24.04.2019
Dirt moved around at the launch pad area, also some dirt work towards the east side of the site
NSF, Mary
below
23.04.2019
Dirt moved around at the launch pad area
Access hatch still open
NSF, Mary
below
22.04.2019
Flare stack burned
Dirt moved around at the launch pad area
Access hatch still open
NSF, Mary
below
20.04.2019
SH work continued, lift at upper access hatch (opened)[551]
Dirt work around the launch pad, near SH
NSF, Mary
below
19.04.2019
Much traffic
SH: scissor lift againt to skirt
Tank farm venting[?][552]
NSF, Chanadian
below
18.04.2019
Trucks and traffic at the launch site
Piles of dirt dumped
SH: scissor lif ascending into skirt at 2:22:30 CDT
Flare stack burning off and full moon
NSF, Chanadian
SPadre
below
16.04.2019
Some work around SH, at the launch site
TinyT Prepper
15.04.2019
LabPadre moved camera 0.4 miles closer to the pad, distance now 5.87 miles
NSF, Chanadian
below
14.04.2019
8-ring stack still on concrete jig
6-ring stack still on container
Nosecone nearly finished
Austin Barnard
below
13.04.2019
Work on SH, access hatch opened
LabPadre
11.04.2019
Nosecone moved outside, header still missing [then called "orbital prototype"][553]
NSF, Mary
Chanadian
below
10.04.2019
Build site: Extension to the north-east
Huge tanks waiting at the satellite area
Now three tapered sections ready for nosecone of OSP [Mk1][554]
Third assembly jig spotted near container jig
08.04.2019
SH work, raptor removed at ~09:30
Fuel tanking
Several tampered pieces for OSP lying around [Mk1?][556]
Work on OSP continued [Mk1][557]
NSF, Mary
LabPadre
Austin Barnard
below
FL
06.04.2019
TFR cancelled
SH inspected
New nosecone spotted in tent?[558]
SPadre
NSF, Mary
05.04.2019
New TFRs from April 5-6
SH testing: Static Fire #2
Florida: Job posting for manufacturing facility in Cape Canaveral, FL
SPadre
NSF, Mary
below
04.04.2019
Fuel delivery
RC cancelled
Brownsville Herald information
Work on stack #1 [Mk1] continued
NSF, Mary
SPadre
below
FL
03.04.2019
SH missing stainless steel section replaced
SH testing: Static Fire #1 [561]
Stack #2 still 6-rings tall [Mk1]
NSF, Mary
SPadre
LabPadre
below
02.04.2019
Elon Musk tweet
New FAA TFR for 2-4 April
New structure at launch site
SH testing
Nitrogen and Oxygen tankers to the pad
Work on OSP continued at build site [Mk1][562]
Two nosecone rings for OSP being worked on [Mk1][563]
NSF, Mary
LabPadre
SPadre
below
01.04.2019
SH testing: Preburner?
SH missing a section of stainless steel
NSF, Mary
LabPadre
Date
Description
Source
Link
31.03.2019
No testing today
NSF, Mary
below
30.03.2019
SH testing: Preburner
NSF, Mary
LabPadre
others
below
29.03.2019
SH venting
TFRs issued for Sat, Sun, Mon; road closures also issued, from 12-8pm
NSF, Mary
SPadre
DaveG
below
28.03.2019
SH testing
Road closure from 12-8pm
Work on tapered section continued and a new tapered section began assembly [both Mk1][566]
NSF, Mary (first youtube video)
SPadre
LabPadre
27.03.2019
SH testing
TFR for tomorrow
NSF, Mary
Nomadd
Others
below
26.03.2019
Road closure notice remained active
Test posponed perhaps due to broken LOX truck
New road closures for Wednesday-Friday from 10am-6pm
Work on the skirt of SH
Work on welds of stack #1 continued [Mk1][568]
Dave G
NSF, Mary
Austin Barnard
25.03.2019
SH test: preburner
diverse
below
24.03.2019
Road closure on Monday 25 from 10am-6pm, secondary closures on Tuesday and Wednesday
Work under the skirt of SH
Dave G
below
23.03.2019
Sign posted: Drones prohibited
Work on Starship Orbital Prototype (OSP) nosecone continued [Mk1][570]
NSF, Mary
below
FL[571]
22.03.2019
New FAA Notams for Monday-Wednesday up to 1000ft
SH tanking test
Jeff Foust
NSF, Mary
SPadre
21.03.2019
Closure at 10am
Farm venting at 10:18 am
SH WDR attempt scrubbed
FST
SPadre
NSF, Mary
RocketLover0119
below
20.03.2019
FAA Notam for today up to 1000ft
Scrub due to weather, posponed to tomorrow
New nosecone section started in front of tent [l:Mk1]
Raptor installing continued
Propellant delivery
FST
NSF, Mary
SPadre
below
19.03.2019
Methane delivery
Work on SH hatch
Hopper test announced for Wednesday, March 20, from 10am-4pm, road closure announced, alternatives on Thursday and Friday
Methane burnt off from flair stack
NSF, Mary
sonic314
docmordrid
18.03.2019
New container at ramp near launch pad
GSE delivered
Raptor installation progressed on SH
SH pressure and tanking tests [574] "kettle"
FST
NSF, Mary
SPadre
below
17.03.2019
Elon Tweeting a lot
Raptor installation continued [[575]]
Elon Musk [576]
below
16.03.2019
Stack #1 now eight rings tall [[577]] [l:Mk1]
Raptor installation continued on Starhopper [[578]]
Safety perimeter with road blocks NET next week for upcoming testing, possibly Static fire [[579]]
NSF, Mary
FutureSpaceTourist
Chris Bergin
15.03.2019
Raptor moved to the launch pad [[581]]
Raptor moved under the skirt [[582]]
LOX delivered [[583]] [Western tank now appears to be LOX, other still nitrogen]
NSF, Mary
FutureSpaceTourist
below
14.03.2019
More panels added to stack #1 on concrete jig [[584]] [l:Mk1]
Testing on Starhopper with some [LOX?] farm venting [[585]]
NSF, Mary
below
13.03.2019
Curved stiffeners lowered into second ring stack [[586]] [l:Mk1?]
NSF, Mary
12.03.2019
Upper and lower access hatch opened on SH [[588] ]
NSF, Mary
below
11.03.2019
Raptor engine has arrived [[589]]
More nitrogen tanks at the tank farm [[590]]
First tanking test of Starhopper
Work on nosecone continued [[591]] [l:Mk1]
NSF, Mary
SPadre
below
10.03.2019
Pipes connected to Starhopper [[593]]
Refrigerated nitrogen delivered [[594]]
Starhopper anchored to pad with Slingmax slings [[595]]
NSF, Mary
below
09.03.2019
Six ring stack on jig: hole spotted
6 ring stack #2 anchored to containers [[596]] [l:Mk1]
Work on new cone continued, more parts ready [[597]] [l:Mk1]
SPMTs moved the stand back, roll lifts then trucked out [[598]]
NSF, Mary
08.03.2019
Starhopper moved to the launch pad on the metal stands on the SPMTs [[600]]
More sections added to the second section next to the containers [l:Mk1]
Other section anchored to concrete jig [[601]] [l:Mk1]
Elon Tweet: raptor install next week [[602]]
NSF, Mary
SPadre and others
Elon Musk
below
07.03.2019
New nosecone parts delivered and welding work on them started [[604][605]] [l:Mk1]
Metal stand from yesterday moved under starhopper
Starhopper received a lot of new cables [[606]]
6 ring stack put on the concrete jig [[607]] [l:Mk1]
NSF, Mary
below
06.03.2019
Starhopper appeared to be sealed [[608]]
Second stack section now 4 ring stack [[609]] [l:Mk1]
Metal structure [stand?] welded on the two SPMTs [[610]]
NSF, Mary
05.03.2019
Scaffolding around Starhopper dome removed
Nitrogen delivery
SpaceX firetruck spotted [[612]]
Two blue SPMTs (self propelled modular transporter for heavy loads) delivered [[613]]
NSF, Mary
below
04.03.2019
New two ring stack with a crane at the north east extension at the shipping containers [l:Mk1?]
Tank farm taking shape with piping and horizontal nitrogen tanks, launch pad as well with new structures and containers built
03.03.2019
Ring stack polished
FutureSpaceTourist
02.03.2019
Upper and lower bulkhead access hatches closed [[615]]
Parts lowered into the ring stack [l:Mk1?]
New ancors attached to the top of cement jig [[616]]
NSF, Mary
below
01.03.2019
New two ring section started [[617]] [l:Mk1]
NSF, Mary
Date
Description
Source
Link
28.02.2019
Much work on Starhopper
Welding of new stack continued [[619]] [l:Mk1]
NSF, Mary
below
27.02.2019
More ring stack added, using smaller panels [[620]]
More reflective sheets added on dome of Starhopper [[621]]
NSF, Mary
below
26.02.2019
Welding of four ring stack progressed [[622]]
Compressed helium [nitrogen?] tanks moved from satellite area to launch site
NSF, Mary
below
25.02.2019
Welding machine used for welding a four ring stack [[623]] [l:Mk1]
Reflective sheets put on top of the dome of SH
Nitrogen tanks now again at build site [[624]]
New small, horizontal tanks arrived at tank farm, more piping has been laid recently
NSF, Mary
below
23.02.2019
Stainless steel panels moved [[625]] [l:Mk1]
Welding machine spotted [[626]]
NSF, Mary
below
22.02.2019
New metal plate with holes attached to the fins
Six shipping containers delivered, put at a northeastern extention of the building site [[627]]
Work on new barrel sections continued [l:Mk1]
NSF, Mary
SPadre
below
21.02.2019
Work on launch site progressed
Dirt work to continue eastwards
Work on mount on pad
Metal rods placed on concrete jig infront of tent [[629]]
Work started on new ring stacks, perhaps for new nosecone [[630]] [l:Mk1]
SPadre
NSF, Mary
below
20.02.2019
Last two lateral stiffeners installed [[632]]
NSF, Mary
below
19.02.2019
New cables appeared on a fin [[633]]
NSF, Mary
18.02.2019
Work on dome of SH continued [[635]]
NSF, DESpaceX
below
16.02.2019
Work on dome of SH continued [[636]]
Welding continued
NSF, Mary
below
15.02.2019
Property fence to be extended
Concrete pouring at the property entrance for th fiber cables
Welding below the skirt and weld checking on bulkhead of SH
Concrete poured at launch pad, with concrete structures on top of it [Suborbital launch mount parts?]
Nitrogen tanks earlier this month spotted at dish area now at launch site
Huge horizontal tanks seen at the satellite area
Austin Barnard
SPadre
14.02.2019
Pad east of earh wall covered with rebar for concrete pouring
Scaffolding around Starhopper removed
More work on SH dome
Austin Barnard
NSF, Mary
below
13.02.2019
Work on the dome of SH continued [[638]]
NSF, Mary
below
12.02.2019
New holes for plumbing and wiring, four lateral stiffeners attached [[639]]
NSF, Mary
below
11.02.2019
Pipes and cables now leading up to the top of the dome of Starhopper [[640]]
Pipes (Struts) attached from the bottom of the hopper to th fin on each side of the fins [[641]]
NSF, Mary
10.02.2019
Second external tank installed on top of Starhopper [[643]]
Holes east of earth wall filled, pad taking shape; south extension pipes to post [flair stack??] completed
Levelling east extention of build site, more dirt work
NSF, Mary
Austin Barnard
below
07.02.2019
Section of external plumbing installed at Starhopper [[645]]
Welding around the dome cap of SH [[646]]
External tank installed on top of the dome [[647]]
NSF, Mary
below
06.02.2019
More rectangles added to Starhopper [[648]]
NSF, Mary
below
05.02.2019
Lid placed on the dome of Starhopper [[649]]
First Raptor engine test at McGregor
Concrete poured at launch site
Pipe connections between Stargate (Ground control) and launch pad area being constructed
Road work at building site to connect to highway 4 continued
Public infrastructure for launch views built at South Padre Island
Rectangles added to Starhopper [[650]]
NSF, Mary
SPadre
see below
04.02.2019
Scaffolding removed from one Starhopper section [[652]]
Second GSE connection spotted on Starhopper [[653]]
Piping work (connecting the water tanks with the rest) at tank farm and dirt work, launch site slowly taking shape; Trio of pits with scaffolding inside east of the earthwall adjacent to the tank farm for a new pad area
NSF, Mary
Austin Barnard
see below
02.02.2019
Ladder lowered into the dome, pipe and toolbox brought out again [[655]]
NSF, Mary
01.02.2019
Overview video
Some scaffolding erected again
A GSE connection spotted on Starhopper [[657]]
NSF, Mary
FutureSpaceTourist
Date
Description
Source
Link
31.01.2019
Part lowered into Starhopper [[659]]
Flange installed at Starhopper [[660]]
Enclosing the tent continued with huge drapery [[661]]
More containters now on tank farm, earth wall finished, southward extention with pipes, hole dug east of earhwall
Mary, NSF
Austing Barnard
below
30.01.2019
First roller door installed at the tent [[662]]
Scaffolding parts being removed from Starhopper [[663]]
Launch Pad rampway paved
Roadway cleared at the build site
Mary, NSF
below
spadre.com
29.01.2019
Work on enclosing the tent continued [[664]]
Access road work to build site off from highway 4 [[665]]
Mary, NSF
below
28.01.2019
Work on enclosing the tent has begun [[666]]
Mary, NSF
below
27.01.2019
Scaffolding being erected around Starhopper [[667]]
Three water tanks now in place at the tank farm [[668]]
Mary, NSF
25.01.2019
More work on Starhopper with parts delivered and a hole cut [[670][671]], another hole used for ventilation [later a access hatch]
Head#2 lowered into Starhopper [[672]]
Mary, NSF
24.01.2019
Bulkhead moved and put ontop of Starhopper [[674][675]]
Three big tanks now at launch site, earth wall progressed [[676]]
Work on a new access gate off highway 4 to the build site, eastward extension of build site [[677]]
Mary, NSF
Austin Barnard
23.01.2019
Oxygen tank vaporizer has been installed at the launch site, adjacent to two tank towers
Nosecone fell over in high wind [[679][680]], later moved under the tent [[681]]
Big tank deliverd to dish area [[682][683]]
Mary, NSF
Roger Holt
22.01.2019
RGV update
SpaceX is using 301 stainless steal and plans to do transpiration cooling
Still no power at build site as they still work on lines from sola field
Nomadd
21.01.2019
Bulkhead section lowered into Starhopper [[686]]
Mary, NSF
20.01.2019
Earth wall construction east of tank farm began
Oxygen vaporizer ready for installation at tank farm
Austin Barnard
18.01.2019
New part added to surface of Starhopper [hatch?]
Mary, NSF
17.01.2019
Second tank installed at the launch site [[690]]
Box lowered into Starhopper and moved out again later [[691]]
Mary, NSF
16.01.2019
Delivery at the big dish area: Helium tanks
One of the smaller tanks stored at the big dish area was transported to the launch site area and installed later [[693][694]]
Parts of bulkhead #2 moved [[695]]
Mary, NSF
15.01.2019
Stainless steel panels covering the joint of lower and upper sections removed [[697]]
Some equipment moved
Mk1 nosecone and Starhopper again separated [[698]]
All three raptors removed from Starhopper [[699]]
Mary, NSF
14.01.2019
More parts for new dome/bulkhead spotted
NSF, other
13.01.2019
Aerial fotos by RGV, tank farm construction began
Low gradient ramp now levelled
12.01.2019
Building overview photo [[702][703]], second pad with starhopper on it now visible
Roger Holt, Alex Balderas
11.01.2019
Cement pouring to begin on launch site, much dirt work at launch site
Bulkhead spotted, which will be inserted in to the Starhopper fuel tank later
09.01.2019
Dome structure spotted and assembled ("Bulkhead") [probably for Starhopper] [[706][707][708]]
Nosecone and Starhopper put together again [[709][710][711]]
Starhopper: Third fin received stainless finish
John Randolph
Mary, NSF
Roger Holt
08.01.2019
Starhopper: More work on legs cover
Mk1 nosecone and Starhopper part put together, later taken apart again
Austin Barnard, NSF
Mary
06.01.2019
Starhopper: More Stainless Steel added to fins
Mary, NSF
05.01.2019
Elon tweet: pic of model of test vehicle
Elon tweet: Engines currently on Starship hopper are a blend of Raptor development & operational parts. First hopper engine to be fired is almost finished assembly in California. Probably fires next month.
Starhopper: stainless steel added to exterior
Mary, NSF
04.01.2019
Mk1: Nosecone and barrel section mated
Mary, NSF
03.01.2019
Starhopper: Grid like hull structure inserted between leg poles
Mary, NSF
01.01.2019
Much work on Starhopper and a nosecone [Mk1]
Two two ring stacks [for Mk1 nosecone barrel section] mated near tent
NSF
Date
Description
Source
Link
29.12.2018
Nosecone moved by crane [still named BFH 1, laterMk1] and mated with other nosecone part
Much work going on on starhopper
ChrisNSF
28.12.2018
Starship slowly taking shape [later Starhopper], work on Nosecone
NSF
Austing Barnard
see below
Christmas 2018
Work on Starhopper and a nosecone [later Mk1] near an open tent structure east of Stargate [pics: [736][737]] and one cement pad in front of tent
NSF
see below
22.12.2018
Elon Musk tweet: Test hopper is at full body diameter of 9m / 30ft, just not full height. Super heavy will be full height & diameter
EM tweet: We're building subsections of the Starship Mk 1 orbital design there
NSF
09.12.2018
Elon tweeting that pics of demo Starship that will fly suborbital hops coming in ~4 weeks
NSF