Pipeline Pre-Lay Survey – Project Manager
07/04/25 to 19/09/25 N-Sea, Netherlands and remote working
Duties: Project Manager responsible for overseeing all aspects of multiple vessel geophysical, geotechnical and ROV inspection surveys to support the lay of 28” Carbon Capture gas pipeline.
Equipment: Full geophysical spread (including UXO gradiometer wings), full geotechnical spread (CPT/vibrocore) and full ROV UXO inspection/identification spread.
Windfarm Export and Inter-Array Cable Installation – Senior Project Surveyor
20/02/24 to 27/03/25 Seaway7, Taipei, Taiwan.
Duties: Senior Project Surveyor, responsible for overseeing all aspects of in-house and contracted provision of survey services to support pre-lay, installation and post-lay of multiple inter-array cables and four export cables from Hai Long 2 & 3 Windfarms to their landfalls in Taiwan. Managing the survey spreads on survey, lay and burial vessels. Overseeing the survey aspects of support vessels (rock-placement, mattress installation, mass-flow excavation etc). Overseeing all data-processing, personnel and equipment provision and final reporting.
Equipment: Global Mapper, Navimodel & overseeing provision of full spread of geophys and cable lay (MBES / SSS / SBP / Sparker etc.)
Geophysical Survey – “Ocean Fortune”
17/04/23 to 13/09/23 OWC Ltd
Bellrock Wind Farm Consenting Survey – North Sea
Duties: Offshore Client Representative (monthly rotations)
Equipment: Global Mapper, Navimodel & overseeing provision of full spread of geophys (MBES / SSS / SBP / Sparker)
Pipeline Inspection – Project Preparation
27/11/23 to 22/12/23 Wood Group plc
Enagas 2023 Pipeline Inspection Campaign – Mediterranean
Duties: Project Surveyor – Project Preparation
Equipment: Document preparation for ROV pipeline inspection campaign (TSS 440 pipetracker, R2Sonic MBES, SSS, video eventing, cathodic protection)
Geophysical and UXO Survey – “Valkyrie”
08/03/23 to 19/03/23 OWC Ltd
Erebus Wind Farm Export Cable – Irish Sea
Duties: Offshore Client Representative
Equipment: Global Mapper, Navimodel & overseeing provision of full spread of geophys and UXO equipment.
Course Tutor – OMPA “Offshore Client Representative” Course
17/01/23 to 16/02/23 Offshore Marine People & Academy
Online learning course tutor
Duties: Course Tutor presenting five-day and three-day “Offshore Client Representative” courses to classes of 7 to 9 delegates
Rock-Placement Operations - Chief Surveyor
15/09/22 to 15/11/22 Deme, Avonmouth, UK
HPC Project - Bristol Channel
Duties: Office-based project management and QA/QC. Including production of rock-placement designs, volume-calculations and data-management.
Equipment: Global Mapper, Eiva Navimodel, & overseeing provision of full spread of survey equipment (survey vessels, tugs and hopper-barges).
Cable Route Survey - "Geo Ocean V"
07/06/22 to 11/08/22 HydroFix Ltd.
Greenlink Power Interconnector Cable - Irish Sea
Duties: Offshore Purchaser's Representative (including project preparation work)
Equipment: Global Mapper, Eiva Navimodel, & overseeing provision of full spread of geophys and UXO equipment.
Windfarm Export Cable Installation – Project Surveyor
17/09/19 to 04/05/22 Boskalis Subsea Cables, Papendrecht, Netherlands & Grimsby, UK.
Hornsea 02 Windfarm - North Sea
Duties: Responsible for overseeing all aspects of in-house and contracted provision of survey services to support pre-lay, installation and post-lay of three export cables from Hornsea 02 Windfarm to their landfall in the UK. Managing the survey spreads on survey, lay, trenching, burial and dredging vessels. Overseeing the survey aspects of support vessels (rock-placement, mattress installation, mass-flow excavation etc). Overseeing all data-processing, personnel and equipment provision and final reporting.
Cable Route Survey – “EGS Surveyor”
04/08/19 to 30/08/19 Engineering Technology Applications Ltd
Bay to Bay Express Cable System (B2BE) – Malaysian Waters
Duties: Offshore Purchaser’s Representative
Rig Site Survey – Project Management
13/05/19 to 03/07/19 GEOxyz, Zwevegem, Belgium
Glengorm Site survey
Duties: Responsible for overseeing all aspects of offshore geophysical rig site survey
Equipment: Eiva Navimodel, & managing provision of full spread of geophys and geotech
Rig Site Survey and Pre-Installation Cable/Pipe Survey – Project Management
27/03/19 to 16/04/19 GEOxyz, Zwevegem, Belgium
N5A Site survey and cable/pipe pre-lay surveys
Duties: Responsible for overseeing all aspects of offshore geophysical and geotechnical surveys for pre-lay pipe/cable and rig-site surveys
Equipment: Eiva Navimodel, & managing provision of full spread of geophys and geotech
Rig Site Survey and Pipeline Inspection – Project Management
04/03/19 to 26/03/19 GEOxyz, Zwevegem, Belgium
Hanze, Unity and De Ruyter Site Surveys and Annual Inspections
Duties: Responsible for overseeing all aspects of offshore geophysical and geotechnical surveys for pipeline inspection and rig-site survey
Equipment: Eiva Navimodel, & managing provision of full spread of geophys and geotech
Windfarm Export Cable Installation – Project Management
Aug.2017 to Nov.2018 Tideway Offshore BV, Breda, Netherlands
Hornsea 01 Windfarm
Duties: Responsible for overseeing all aspects of in-house and contracted provision of survey services to support pre-lay, installation and post-lay of three export cables from Hornsea Windfarm to their landfall in the UK. Managing the survey spreads on survey, lay, trenching, burial and dredging vessels. Overseeing the survey aspects of support vessels (rock-placement, mattress installation, mass-flow excavation etc). Overseeing all data-processing, personnel and equipment provision and final reporting.
Associate Consultant – Red Penguin Associates Ltd (Freelance)
Dec.2016 to Aug.2017 Red Penguin Associates Ltd, Fareham, UK
Based in Fareham, UK.
Duties: Responsible for advising and assisting clients in the submarine cables and renewables industries on various offshore projects. Specific duties involve adding value to projects by controlling and minimising risk and providing specialist advice regarding bathymetric/geophysical and UXO survey, project management and QHSE.
Technical Director – Bibby HydroMap Ltd
02/11/15 to 11/11/16 Bibby HydroMap Ltd, Bromborough, UK
Based in Bromborough, UK.
Duties: Technical Director, Bibby HydroMap Ltd overseeing all project and operational aspects of the survey arm of the company (80 staff) including offshore data gathering (geophys/geotech), processing/reporting, innovation (new markets/techniques) and sub-contractor management. Responsible for setting and maintaining the operational budget, scheduling/resourcing/delivering operational projects, managing R&D projects, managing processing projects and managing the company’s vessels.
Group Manager, Geosurvey – Fugro EMU Ltd
08/11/10 to 29/10/15 Fugro EMU Ltd, Portchester, UK
Based in Portchester, UK.
Duties: Group Manager, Geosurvey, Fugro EMU Ltd. Leading and managing all aspects of an active and successful geophysical survey department of 50 staff and 3 vessels with a multi-million pound budget. Responsible for departmental strategy, P&L, marketing, team composition and motivation, leading technical innovation etc. Building the department to a stage where it exceeded its profit plan in 2014 by over 200%.
Hydrography Manager - Maritime & Coastguard Agency
28/07/03 to 08/11/10 Maritime & Coastguard Agency – Southampton, UK
Based in Southampton, UK.
Duties: Overall management of the “Civil Hydrography Programme”. The programme delivers all UK government-funded civilian hydrographic surveys for incorporation in national nautical charts and publications. Programme budget is £5.4 million. Responsible for ensuring that the programme is delivered at best value for money, by the intelligent use of appropriate technologies and specifications. Also responsible for providing advice and guidance to the Agency on all aspects of hydrography and hydrographic information systems.
Bathymetry Advisor – United Kingdom Hydrographic Office
11/02/02 to 25/07/03 United Kingdom Hydrographic Office – Taunton, UK
Based in Taunton, UK.
Duties: Responsible for providing advice relating to all aspects of receipt, processing, quality appraisal and storage of bathymetric data. Responsible for specifying the bathymetry handling requirements for a computerised office-wide production system. Contributed to the set-to-work trials for the Royal Navy’s first multibeam echosounder vessel HMS Echo by representing the UKHO on planning groups and also providing advice and support onboard the vessel during set-to-work trials.
Rig-Move – Atwood Southern Cross
09/01/02 to 11/01/02 Isramco (Israel)
Nordan 1 Well – Israel
Duties: Client Representative
Pipe-Lay Support Survey – DSND Surveyor
09/12/01 to 23/12/01 Mærsk Oil & Gas (Denmark)
Tyra, Kraka & Halfdan Fields – North Sea (Danish Sector)
Duties: Client Representative
Rig-Move – Mærsk Exerter
04/12/01 to 08/12/01 Mærsk Oil & Gas (Denmark)
Tyra Field – North Sea (Danish Sector)
Duties: Client Representative
Rig-Move – Rigmar 301
15/11/01 to 22/11/01 Mærsk Oil & Gas (Denmark)
Gorm Field – North Sea (Danish Sector)
Duties: Client Representative
Pipe-Lay Support Survey – DSND Surveyor
02/10/01 to 30/10/01 Mærsk Oil & Gas (Denmark)
Tyra, Kraka & Halfdan Fields – North Sea (Danish Sector)
Duties: Client Representative
Hydrographic Survey Advisor – Land Information New Zealand (LINZ)
23/08/99 to 08/08/01 Land Information New Zealand – Wellington, New Zealand
Based in Wellington, New Zealand.
Duties: Employed for two years as the New Zealand government advisor responsible for producing the programme and specifications for New Zealand’s national hydrographic surveys. Represented LINZ on a number of government advisory groups. Performed audits of sub-contracting companies and quality assurance of final survey products. Involved in numerous nautical charting surveys around New Zealand and in the Ross Dependency, Antarctica.
Rock-Dumping Operations – FPRD Rollingstone
19/06/99 to 26/06/99 Statoil (Norway)
Loke Field – North Sea (Norwegian Sector)
Duties: Client Representative
Rock-Dumping Operations – FPRD Rollingstone
29/05/99 to 19/06/99 Amerada Hess (Holland)
South Arne Development – North Sea (Dutch & Danish Sectors)
Duties: Client Representative
Rock-Dumping Operations - FFPV Trollness
20/05/99 to 23/05/99 Statoil (Norway)
Asgard 42” Pipeline – North Sea (Norwegian Sector)
Duties: Client Representative
Trenching Support & Post-Trench Survey – Geopotes 14
24/04/99 to 12/05/99 Statoil (Norway)
Europipe II Pipeline – North Sea (Danish & German Sectors)
Duties: Client Representative
1:2000 Pipe-Lay Support Survey - STM Atria
16/03/99 to 26/03/99 Seateam (Holland)
Europipe II Survey Support – North Sea (German Sector)
Duties: Client Representative overseeing performance of survey / ROV subcontractor (team of 22). QC of all survey operations including ROV, geophysical and positioning data and production of charts / reports
1:2000 Pipe-Lay Support Survey - STM Atria
26/01/99 to 16/02/99 Seateam (Holland)
Europipe II Survey Support – North Sea (Danish / German Sectors)
Duties: Client Representative overseeing performance of survey / ROV subcontractor (team of 22). QC of all survey operations including ROV, geophysical and positioning data and production of charts / reports
1:10000 Cable-Route Survey - mv Markab
25/11/98 to 03/12/98 Seateam (Holland)
Delta Radio 10kV Cable Route – North Sea (Dutch Sector)
Duties: Party Chief in charge of team of eight. Gathering of bathymetry, magnetometer, side-scan, boomer and pinger data. Production of preliminary report, QC of charts and data & liasing with client.
1:10000 Pipe-Route Survey - mv Inspector
13/11/98 to 24/11/98 Seateam (Holland)
Wintershall L-8 Field – North Sea (Dutch Sector)
Duties: Party Chief in charge of team of eight. Gathering of bathymetry, magnetometer, side-scan, boomer and pinger data. Production of preliminary report, QC of charts and data & liasing with client.
Anchor Positioning - sv Smit Lenga
01/10/98 to 23/10/98 Stolt Comex Seaway (Argentina)
“Hydra Centro” Platform – Total Hydra Field, Argentina
Duties: Sole Surveyor responsible for surface positioning, navigation, and positioning of four-point moorings.
Rig-Move - Jack-up Glomar Labrador 1
22/09/98 to 30/09/98 Stolt Comex Seaway (Argentina)
Argo-2 Wellhead – Total Hydra Field, Argentina
Duties: Senior Reporting Surveyor responsible for surface positioning, navigation, calibration & final position analysis.
ROV As-Built Pipeline Survey - MV Geofjord
22/07/98 to 11/08/98 Norsk Hydro
TOGP ROV As-built Survey
Duties: Offshore Client Representative responsible for overseeing performance of survey sub-contractor (team of 15). QC of all survey operations including gathering of ROV geophysical and positioning data, installation of acoustic arrays for jacket / template installation and production of preliminary survey charts.
ISU Umbilical Installation - DSV Rockwater 1
18/06/98 to 01/07/98 Norsk Hydro
TOGP Static ISU Installation
Duties: Offshore Client Representative responsible for overseeing performance of survey sub-contractor (team of 7). QC of all survey operations including gathering of as-laid data and production of preliminary survey charts.
Pre-Installation Survey- MV Markab & DSV Lowland Cavalier
27/04/98 to 24/05/98 Norsk Hydro
Oseberg Ost Pipeline Burial Survey
Duties: Offshore Client Representative responsible for overseeing performance of survey sub-contractor (team of 10). QC of all survey operations including gathering “stabber” depth-of-burial data and production of preliminary survey charts.
Pre-Installation Survey- MV Northern Horizon
06/04/98 to 23/04/98 Norsk Hydro
Oseberg Ost & Oseberg Sor Jacket & Template Pre-Installation Survey
Duties: Offshore Client Representative responsible for overseeing performance of survey sub-contractor (team of 10). QC of all survey operations including gathering of side-scan data, installation of acoustic arrays for jacket / template installation and production of preliminary survey charts.
1:2500 Rock-Dumping Operations - FPRD Rollingstone
17/03/98 to 25/03/98 Norsk Hydro
Gamma Nord & Visund Mattress Installation
Duties: Offshore Client Representative responsible for overseeing performance of rock dumping operations & associated survey sub-contractor (team of 8). QC of all survey operations from gathering of swathe bathymetry to production of preliminary survey charts and acceptance of rock-dumping to specifications.
1:2500 Rock-Dumping Operations - FPRD Rollingstone
30/01/98 to 17/02/98 Allseas Engineering
NAM L9 Gas Development Project & Texaco Galley Development
Duties: Offshore Client Representative responsible for overseeing performance of rock dumping operations & associated survey sub-contractor (team of 8). QC of all survey operations from gathering of swathe bathymetry to production of preliminary survey charts and acceptance of rock-dumping to specifications.
1:5000 Cable Route Survey - r/v Pelagia
23/11/97 to 16/12/97 Tyco USA
“Atlantic Crossing” Cable Segment B2
Duties: Offshore Client Representative responsible for overseeing performance of survey sub-contractor (team of 15). QC of all survey operations from gathering of swathe bathymetry, SSS, SBP and magnetometer data to production of preliminary survey charts.
1:500 Post Sand-Slide Survey - MV Bossanova
27/08/97 to 18/11/97 Alcatel Norge
Gulf of Aqaba Submarine Power Cable Crossing
Duties: Offshore Client Representative responsible for overseeing performance of survey sub-contractor (team of 8). QC of all survey operations from gathering of swathe bathymetry data to production of final survey charts and report.
1:5000 Pre-Lay Survey - MV Famco Express
06/06/97 to 18/07/97 PT Rinjanisakti Jayatama
Conoco West Natuna Gas Transportation System Feasibility Study
Duties: Offshore Party Chief responsible for team of 10. Preparation, QC and undertaking of all survey operations from gathering of swathe bathymetry and geophysical data to production of final survey charts.
1:2000 Post-Dredge Survey - MV Claes Compaen
27/01/97 to 07/05/97 Jan De Nul Dredging - Aalst, Belgium
Bacton - Zeebrugge Pipeline Route & NORFRA Pipeline Route (Southern North Sea)
Duties: Offshore Client Representative responsible for overseeing performance of survey sub-contractor (team of 6). QC of all survey operations from gathering of swathe bathymetry data to production of final survey charts.
FLAG Sub-Sea Cable Post-Lay-Burial - MV British Magnus
19/11/96 to 23/12/96 Cable & Wireless (Marine) - Chelmsford
Various locations in S.E. Mediterranean and the Red Sea
Duties: Senior Reporting Surveyor responsible for positioning vessel and trenching vehicle using surface and sub-surface positioning. Performed all calibrations, QC. etc. and produced final report for operation.
United States Department of Defence Operations - CS Cable Installer
20/10/96 to 02/11/96 Cable & Wireless (Marine) - Southampton
Location Restricted
Duties: Senior Reporting Surveyor responsible for positioning vessel etc. Performed all calibrations, QC. etc. and produced final report for restricted operation.
Survey Manager - BT(Marine)
29/11/93 to 13/09/96 BT(Marine) - Southampton
Based in Southampton, UK and later Chelmsford UK under employment of Cable & Wireless (Marine).
Duties: Survey Manager with sole Responsibility for establishing the capability within BT(Marine) and Cable & Wireless (Marine) for performing all survey operations onboard cable installation and support vessels on an in-house basis (i.e. not relying on outside survey contract companies). Duties included hiring all free-lance surveyors, specifying and supervising the purchasing of all survey equipment and software, negotiating contracts with sub-contractors, Day-to-day running of all survey operations (up to eight vessels and sixteen off-shore staff), QC of all data and charts, meeting with clients to discuss requirements, planning and supervising mob / demob of vessels etc. etc.
Shell, Conoco & BP Annual Pipeline Inspections - MV Kommander SubSea
18/08/93 to 22/09/93 SubSea Survey (Aberdeen)
Various locations in Southern & Northern North Sea
Duties: Party chief in charge of team of 5. Overall responsibility for all positioning, calibrations, QC, and production of 1:5000 charts.
Statoil Annual Pipeline Inspection - MV Kommander SubSea
22/06/93 to 22/07/93 SubSea Survey (Aberdeen)
Zeepipe, Statpipe etc. - Northern & Southern North Sea
Duties: Party chief in charge of a team of up to 12. Overall responsibility for all positioning, calibrations, QC., production of 1:2000 charts etc. for 500Km of pipeline survey. Involved in planning of job and final reporting.
Statoil Annual Pipeline Inspection - MV Kommander SubSea
23/04/93 to 27/05/93 SubSea Survey (Aberdeen)
Zeepipe, Statpipe etc. - Northern & Southern North Sea
Duties: Party chief in charge of a team of up to 12. Overall responsibility for all positioning, calibrations, QC., production of 1:2000 charts etc. for 500Km of pipeline survey. Involved in planning of job and final reporting.
Protection Mattress Installation - DSV Bar Protector
01/03/93 to 13/03/93 Brown & Root (Aberdeen)
Block 16/11 - Norwegian Sector North Sea
Duties: Senior reporting surveyor in charge of positioning vessel and protection mattresses and conducting sea-bed survey producing bathymetry plots, profiles etc.
Power & Communication Umbilical Laying - CLDSV Discovery
08/01/93 to 31/01/93 Brown & Root (Aberdeen)
Brae Field - North Sea
Duties: On-line surveyor positioning vessel and umbilicals using surface and sub-surface positioning. Calibrations, QC. etc.
Spool-Piece installation - MSV Regalia
24/11/92 to 16/12/92 Brown & Root (Aberdeen)
Scott Field - North Sea
Duties: On-line surveyor positioning vessel and spool pieces using surface and sub-surface positioning. Calibrations, QC. etc.
CDTM Bundles Lay-Down - DSV Rockwater Semi 2
10/08/92 to 23/08/92 Brown & Root (Aberdeen)
Embla & Eldfisk Platforms - North Sea (Norwegian Sector)
Duties: On-line surveyor positioning vessel & anchor blocks and monitoring bundle location using surface and sub-surface systems.
Installation & Repair of ESV Frames - DSV Rockwater Semi 1
16/06/92 to 26/06/92 Brown & Root (Aberdeen)
Sean & Leman Fields - North Sea
Duties: Sole surveyor in charge of surface positioning and depth measurement of sub-sea structures.
CDTM Bundles Tow-Out - MV Banckert
02/05/92 to 24/05/92 Brown & Root (Aberdeen)
Piper Field re-development - North Sea
Duties: Sole surveyor onboard monitoring bundle tow-out and final lay-down position utilising surface and sub-sea positioning.
Positioning and Repair of ESV Frames - DSV Rockwater Semi 1
17/04/92 to 01/05/92 Brown & Root (Aberdeen)
Sean & Leman Fields - North Sea
Duties: Assistant surveyor utilising surface and sub-sea positioning for navigation of tracked dredging vehicle. Also positioning of divers and ESV frames utilising LBL EHF array & Digiquartz and operation of "Sonargraphics" 3-d Sonar.
Positioning of ESV Frames - DSV Uncle John
25/02/92 to 24/03/92 Brown & Root (Aberdeen)
Bruce Development - North Sea
Duties: Assistant surveyor utilising surface and sub-sea positioning for navigation of tracked dredging vehicle. Also positioning of divers and ESV frames utilising LBL EHF array & Digiquartz and operation of "Sonargraphics" 3-d Sonar.
Positioning of ESV Frames - MSV Amethyst
10/12/91 to 29/12/91 Brown & Root (Aberdeen)
Bruce Development - North Sea
Duties: Assistant surveyor utilising surface and sub-sea positioning for navigation of tracked dredging vehicle. Also positioning of divers and ESV frames utilising LBL EHF array & Digiquartz and operation of "Sonargraphics" 3-d Sonar.
DSV Positioning - DSV British Argyll
27/08/91 to 18/09/91 Wimpol Ltd. (Gt. Yarmouth)
Thames, Yare, Bure & Welland Fields - Southern North Sea
Duties: Sole surveyor in charge of surface positioning, calibrations, QC. and final reporting for client.
Anchor-Handling Vessel Positioning - MV Toisa Intrepid
19/07/91 to 09/08/91 Wimpol Ltd. (Aberdeen)
Balmoral FPV - North Sea
Duties: Sole surveyor in charge of vessel positioning for semi-sub anchor chain maintenance and replacement. QC. and reporting.
Rig Move - Glomar Baltic 1
08/07/91 to 15/07/91 Wimpol Ltd. (Aberdeen)
Block 43/13 to Amethyst B1D Platform - North Sea
Duties: On-line surveyor responsible for surface positioning of jack-up next to existing platform to +/- 3m.
ROV Debris Survey - MV Oil Chancellor
01/07/91 to 07/07/91 Wimpol Ltd. (Aberdeen)
Amethyst B1D, Amethyst C1D and West Sole WA platforms - North Sea
Duties: Assistant surveyor responsible for surface and sub-sea positioning, quality control & calibrations.
Rig Move - Borgny Dolphin
26/06/91 to 01/07/91 Wimpol Ltd. (Aberdeen)
Block 14/20 to 21/24 - North Sea
Duties: On-line surveyor responsible for surface positioning, navigation, calibration & final position analysis.
Rig Move - Trident X
16/06/91 to 20/06/91 Wimpol Ltd. (Gt. Yarmouth)
Block 49/3 to 43/26 - Southern North Sea
Duties: Sole surveyor responsible for surface positioning, navigation, calibration, final position analysis & reporting.
Reel Barge Pipe-lay Operations - Apache
18/05/91 to 09/06/91 Brown & Root Survey (Aberdeen)
Block 42/30 to 43/26 (Ravenspurn) - Southern North Sea
Duties: On-line surveyor responsible for barge positioning, QC. checks, calibrations and monitoring of pipe lay-down.
Rig Move - Sedco 712
21/04/91 to 29/04/91 Wimpol (Aberdeen)
Block 21/6 to 30/7 - North Sea
Duties: On-line surveyor responsible for surface positioning, navigation, calibration & final position analysis.
Diver & De-gaussing Range Positioning - Support Barge HM3
15/04/91 to 20/04/91 Fathomer Diving (Mullion)
Rosneath (River Clyde) - West Scotland
Duties: Sole surveyor responsible for diver and structure positioning using total station r&b. Charting, calculations etc.
Rig Move - Galveston Key
15/12/90 to 21/12/90 Wimpol Ltd. (Gt. Yarmouth)
Block 47/20 to 48/22 - Southern North Sea
Duties: Sole surveyor responsible for surface positioning, navigation, calibration & final position analysis.
Rig Move - Borgny Dolphin
13/09/90 to 16/09/90 Racal Survey (Aberdeen)
Block 16/28 - North Sea
Duties: Sole surveyor responsible for surface positioning, navigation, calibration & final position analysis.
Rock-Dumping Positioning - Jack-up Rig Britannia
08/09/90 to 11/09/90 Racal Survey (Aberdeen)
Ravenspurn Field - Southern North Sea
Duties: Sole surveyor in charge of positioning rock-dumper "Rocky Giant" by laser r&b from jack-up rig.
Pipe Lay Operations - "DLB 1601"
10/07/90 to 16/06/90 Brown & Root Survey (Aberdeen)
Cruden Bay to Forties "C" - North Sea
Duties: On-line surveyor responsible for surface positioning of lay-barge and for provision of calibrations and QC.
Rig Move - Sea Explorer
04/06/90 to 09/06/90 Racal Survey (Aberdeen)
Crawford Field - North Sea
Duties: On-line surveyor responsible for surface positioning, navigation, calibration & final position analysis.
MOD Hyperfix Station Re-Co-ordination to +/- 20cm
01/06/90 to 03/06/90 Racal Survey (Aberdeen)
Ruah Reidh Hyperfix Station - Northwest Scotland
Duties: Sole surveyor responsible for obtaining co-ordinates for station by GPS carrier phase measurement.
MOD Hyperfix Chain Station Re-Co-ordination to +/- 20cm
01/06/90 to 30/05/90 Racal Survey (Aberdeen)
"Bell" Hyperfix Chain - Southeast Scotland
Duties: Assistant surveyor involved in all aspects of traditional land survey of five Hyperfix antennae to MOD specs.
Microfix Chain Co-ordination to +/- 20cm
22/04/90 to 28/04/90 Racal Survey (Aberdeen)
Beryl "A" & Beryl "B" platforms - North Sea
Duties: Chief surveyor in charge of deriving co-ordinates of beacons using offsets from existing control.
Hyperfix & Syledis Station Co-ordination to +/- 20cm
16/04/90 to 21/04/90 Racal Survey (Aberdeen)
West Coast of Shetland Islands - Scotland
Duties: Assistant surveyor for land survey utilising theodolite & EDM. Involved in all aspects including calculations etc.
Rig Move - Sedco 711
11/04/90 to 15/04/90 Racal Survey (Aberdeen)
Block 15/20 to 9/23 - North Sea
Duties: On-line surveyor responsible for surface positioning, navigation, calibration & final position analysis.
Differential GPS Receiver Operation - MV Baffin Seal
17/03/90 to 04/04/90 Racal Survey (Aberdeen)
Block 44/16 - North Sea
Duties: Sole surveyor responsible for demonstrating Racal DGPS system & instructing seismic company's surveyors in its operation.
Differential GPS Reference Station Installation
09/03/90 to 16/03/90 Racal Survey (Aberdeen)
Lizard Peninsula - Cornwall
Duties: Erecting differential GPS station & 80ft Hyperfix transmitter. Programming DNavR reference station software.
Rig Move - Ocean Valiant
15/02/90 to 18/02/90 Racal Survey (Aberdeen)
Crawford field - North Sea
Duties: On-line surveyor responsible for surface positioning, navigation, calibration & final position analysis.
Rig Move - Sedco 703
09/02/90 to 11/02/90 Racal Survey (Aberdeen)
Crawford field - North Sea
Duties: On-line surveyor responsible for surface positioning, navigation, calibration & final position analysis.
DSV Vessel & Anchor Positioning - MV Mansal 32
20/11/89 to 06/12/89 Racal Survey (Abu Dhabi)
Al Idd Sharqi, Maydan Mahzam, Bul Hanine fields - Qatar
Duties: Sole surveyor responsible for surface positioning.
1:5000 Pre-Lay Pipe-Route Survey - MV Grey Helm
28/10/89 to 14/11/89 Racal Survey (Abu Dhabi)
Heera & Panna fields - Bombay India
Duties: On-line surveyor responsible for erecting chains, operating navigational & sub-sea equipment and sole responsibility for charting & post-processing.