Solar and Battery Backup for Chernihiv Hospital No. 2
Rotary Global Grant #2567312
Project Managers
Local Project Host: Rotary Club of Kyiv-Capital International Fundraising Host: Rotary Club of Babcock Ranch, FL
Team includes Ukrainian solar industry leaders, a German NGO (BGK- verein.de), Canadian and US Rotary clubs, and former US Dept of Energy staffers and contractors.
Project Dates Start Date: Jul 1, 2025 Estimated End Date: Apr 1, 2026
Background:
Due to the full-scale Russian invasion, continuing damage to the Ukraine power grid has been devastating for hospitals nationwide.
Annual Electricity use is 1,462 (MWh) at this 600-bed hospital. The two Rotary Clubs are leading an effort to install a 284 kW-DC PV
system with a 60 kW/300 kWh battery. Private investment is sought. Approximate cost: USD$400,000. Simple payback period - 7.3 years.
Objectives:
Support Ukraine government’s goal to transition to 25% renewable energy by 2030
Give hospital the ability to operate as an “island” during power outages
Provide reliable hospital care to city of 250,000 and area veterans.
Target Audience The hospital had 230,000 visitors in 2023. It is a regional hub for rehabilitation of wounded veterans. The ER sees 20,000 people/year.
WATCH: Wounded warrier rehab at Chernihiv Hospital No. 2
Project Scope:
3rd Rotary Global Grant for this team. A solar installation is now underway at Chernihiv Maternity Hospital, thanks to USD$244,000 raised from a total of 14 Rotary Club partners in the U.S. and Canada. A Chernihiv solar installer was selected in a competitive bid using a USDOE-based Request for Proposals. Responses were scored by Ukrainian and U.S. solar experts.
Project Constraints:
The Rotary Club of Babcock Ranch must raise USD$220,000 in order to qualify for a $180,000 match from the Rotary Foundation. An additional $15,000 must be raised to supplement an existing solar workforce development project at the Lyceum of Railway Transport, as required by Rotary International. Our partner, the German NGO Blau-Gelbes Kreuz, has pledged 40,000 Euros.
Deliverables:
Rooftop engineering study
Electrical room modifications
Solar modules, battery, inverters, rack mounting system
Job training program at Lyceum of Railway Transport
Explorations & Decisions
It is imperative that this project be started before or after the harsh Ukrainian winter. This limits the installation “window.”
Project Timeline
Fundraising 12/31/25
Engineering Study 2/28/26
Request for Proposals 3/31/26
Bid award and construction commences 4/30/26
Installation and commissioning 5/31/26
NREL Analysis
U.S. National Renewable Energy Laboratory (NREL) PreFeasibility Analysis was completed 10/2024
During 2023-2024, the National Renewable Energy Laboratory (NREL) contributed a prefeasibility analysis to this project, funded by USAID.
Read it here: https://www.nrel.gov/docs/fy25osti/91296.pdf Further information: pat.strong.rotaryclub@gmail.com