Planning

content incomplete - content last updated June 2021 except for  April 2023 update.


Contents of this page 

2023 update

GWH put on hold: costs outweight the benefits

Infrastructure NSW does not currently support the planned duplication

"At present, NSW and other jurisdictions have several megaprojects on foot creating high levels of demand. At the same time, construction industry capacity, supply chains and skills have all been stretched by COVID-19 and other worldevents. It would be especially challenging to deliver additional megaprojects in a cost-efficient manner in coming years.

Faced with these realities, Infrastructure NSW recommends reconsidering the timing and sequence of a number of large, complex projects that are not yet in procurement. These include – Beaches Link, Parramatta Light Rail Stage 2, the M6 Motorway Stage 2, the central tunnel for the Great Western Highway Katoomba to Lithgow upgrade, "
Source current at April 2023 (emphasis added and see further down for recent examples)


Neither does does Infrastructure Australia
(Note: this is just for the east and west sections. The central section - a tunnel of 11km - is likely to lead to an even higher economic cost to society)

"The proponent’s economic analysis states the net present value (NPV) of the East and West sections to be -$579.5 million with a benefit-cost ratio (BCR) of 0.575, representing a net economic cost to society. 

The business case demonstrates that the project will enable improved travel reliability and improved local amenity. However, the largest economic benefit (28% of total benefits5) is derived from avoided routine maintenance of the existing roads and the basis of this contains some assumptions and methodological issues which could overstate the quantum of benefits in the Cost Benefit Analysis (CBA).

The project is expected to generate a cost to society, with a NPV of -$579.5 million. With wider economic benefits and land use benefits included, the NPV is -$431.5 million. The CBA shows little sensitivity to the level of demand, with many of the benefits being fixed, including avoided maintenance costs and residual value (collectively 33.4% of core benefits). There is potential for additional benefits related to travel time savings outside the corridor and unforeseen population growth that would increase demand, however these have not been able to be quantified. There is also a risk that costs could be higher than anticipated, further decreasing value for money. (p.5)

Cost estimates for the base case have not been peer reviewed, as recommended by Infrastructure Australia. ... we consider the base case estimates of O&M costs to be disproportionate relative to the O&M cost estimates in the project case. This will have the effect of overestimating the benefits and the BCR of the project".(p.6 emphasis added and see list of recent examples next section)


The Grattan Institute says "The rise of megaprojects: counting the costs"


A list of recent NSW mega-project cost blowouts


Earlier content


 Somehow, this project has morphed into a mega project with no sense of being staged to deliver early benefits addressing the real problem, not occasional holiday congestion. Alex W.

The majority of Australians would like to see freight hauled by real trains, not road trains. Countless studies and reports – many commissioned by government agencies – have highlighted the growing negative impact of allowing too many trucks on roads. More trucks mean increased severity of road accidents, heightened pressure on already overstretched maintenance budgets and a rise in vehicle emissions.”

(Dean Dalla Valle, CEO Pacific National,Rail Express, 15/3/19)


NSW on a slow track to fast trains: promised regional rail upgrades are long overdue (Source, June 2021)


Opportunity Cost Completely Ignored     


Definition of Opportunity Cost

This road tunnel / duplication proposal is supposed to save 10 minutes of travel time and cost billions of dollars. The NSW Gov't is spending a lot of time and money investigating it (the technicalities, not the cost)

A minimal realignment of the rail line between Lithgow and Blayney is estimated to reduce travel time by about 25 minutes. Why isn't the NSW government investigating this??
Source: SPEEDING UP NSW MAIN WEST TRANSIT TIMES by Max Michell and Philip Laird Freelance Rail Operations Analyst / University of Wollongong, 2019.

 

Current transport policy  in NSW focusses on providing for anticipated demand (especially for roads).
There is almost no emphasis on demand management  (except in inner-city contexts).

This is the core of the problem in planning land transport.

A long stretch of land about 5m wide created for use  by 

Or in the case of the latter freight equal to between about 50 to 100 trucks (depending of various factors).

We have decided to focus most of our attention on the first mentioned: we have decided to opt for the more expensive, less productive mode.

That is the main reason we have congestion on our roads. We have made that choice. 

The idea of a dual road carriageway from Lithgow to Katoomba has been on the cards for a long time.

Planning for it has not. It is (as of late July 2020) still underway, even though a decision has already been made to build it. The final construction cost is not known, the state government will only commit to $2.5 billion. The other costs are not known. There is a lot of guesswork going on.

What is wrong with this idea?

You cannot build your way out of road congestion: you can only move it from one place to another, or worse still add to it.

This is a classic case of 

The Sunk-Cost Fallacy

which is our our tendency to throw good money after bad. Because we have already spent money on something that only encourages us to keep doing it. Sometimes it is better to do something different or the opposite. (Definition)

The more we spend on something, the less  willing we are to change.

Isn't making a decision to build a road without knowing all the costs and benefits a roundabout way of doing things? What if there are other ways?

Where is the research?

Shouldn't all the options be costed first, then a decision made?

What about consultation? Shouldn't all the stakeholders be asked first?

What should be done?

All the costs and benefits must be carefully calculated, discussed and debated.
Only then should a decision be made, and that choice must be "mode agnostic".
We should not be trying to "pick winners and losers".

The Nationals say they are committed to rail: "Deputy Premier John Barilaro reiterated the state government’s commitment to a major rail spending programme as part of its A$55bn transport investment programme over the next five years." 

Back in 2010 the then Opposition Leader urged the Labor to get freight on to rail. At the time he said

What is government policy with regard to project planning?

This is an extract from the Transport for NSW Cost-Benefit Analysis Guide , which recommends how planning decisions like this should be made:

5.3.2 Specify the project options

As a general guide, there should be a minimum of three alternatives to the base case considered for major investments (≥$10 million) at the strategic business case stage, and two to three alternatives at the final business case stage. For smaller projects, at least two alternatives, preferably more, should be considered. It is recommended that a range of alternatives are represented in terms of technology, mode, demand, or timing. Only technically and economically feasible options should be considered in the analysis. 

For major projects, a long list of potential options should be developed in the strategic business case. 

poor specification of project options will compromise the analysis and distort the investment decision being made.

 A CBA should consider a range of realistic options.

and from Section 6 on Optimism bias

"A common cognitive bias for project proponents is optimism bias which unintentionally advantages a preferred option over credible alternatives. The most appropriate way of addressing this issue, particularly for projects that have not been undertaken before, is to ensure that the cost and benefit assumptions and data used are reasonable by comparing them with actual data from similar, recently completed projects.

Ways to avoid cognitive bias when developing transport initiatives include: thinking in terms of outcomes, exploring a wide range of option early in development, and avoiding the preferring of an option without the necessary evidence."   (emphases added) 

At the  federal level a 2020 report by the Productivity Commission recommended that "There are significant opportunities for COAG (to improve] infrastructure provision and management by :...ensuring that investment decisions on major freight corridors are based on transparent cost-benefit analysis, which includes consideration of intermodal options"   (National Transport Regulatory Reform - Inquiry Report no. 94)
 

Failing the newspaper and pub test: TfNSW acting against its own advice.

more from Transport for NSW Cost-Benefit Analysis Guide section 6 

"When doing or reviewing a CBA would you be willing to defend your decision, to family, friends or media if it appeared in a local paper? This includes: the choice of preferred option; cost and benefits of the preferred option compared to alternatives; the process used to make the decision; and the cost of developing the CBA, the business case and making the decision".

In the case  of the GWH the government has not followed its own advice.

 It has NOT considered

There is a danger that the "decision" already made will lead to poor outcomes.

Why is it being fast tracked?

In the 2018  TfNSW document called  "Regional NSW Services and Infrastructure Plan" the  'Great Dividing Range long term solution corridor preservation' was for scheduled for investigation by 2028 and for delivery 20+ years away, and the "Electrification of intercity to Bathurst" was supposed to be investigated in the next 10-20 years. (see pp 272-3).

Why the turnaround? What has changed in two years?  

Congestion and Reliability Review: Full Report Austroads 2015 p.99

"Benefit-cost analysis is particularly important for large infrastructure projects because their total capital commitment, benefits and risks are all significant and are typically only marginally above the acceptable benefit-cost threshold of 1. Indeed, there are likely to be a large number of small projects with higher benefit-cost ratios that could be completed instead, for the same cost as a larger project."

Missing evidence base for big calls on infrastructure costs us all. "When the case for big transport projects is made without due analysis, we risk building the wrong projects. The result is we waste billions of dollars and rob ourselves of the infrastructure our booming cities need to be more liveable. Given how fast our big cities are growing, we simply can’t afford to make decisions based on limited or misleading information. Yet this keeps happening."


"It would be better to spend the $40billion on 80 projects worth $500 million than two mega-projects" (Terry Rawnsley, SGE Economics and Planning. Source: SMH 24 Aug2020)

Grattan and SGS also question big projects (SMH, 9 September20, page 6)

“The Grattan Institute’s transport and cities program director Marion Terrill said two changes out of the coronavirus recession could affect the usage of planned infrastructure projects for years if not decades….. ‘‘We know that these big road projects for instance were based upon big increases in population, but that’s not going to happen,’’ she said. ‘‘All of these big projects should be halted, with their business cases reviewed to make sure they stack up."

SGS Economics principal and partner Terry Rawnsley said governments had to look at the relative economic benefit of projects.

He said social housing, which the federal government has been reluctant to support as it believes it is a state responsibility, would provide a substantial economic boost because it was spread across the country and required small scale contractors. ‘‘If you’re going to spend $50 billion, is it better to have two projects worth $25 billion each or a thousand worth $50 million each?’’ he said."


In December 2018 a Parliamentary Inquiry [2] found that for future large scale infrastructure projects, the government should:

Why hasn't this happened?
Is planning so much improved now that we don't need oversight? 

Social Licence to Operate

(What follows is from TfNSW's own documents: Enhancing transport project implementation and community acceptance through ‘social licence to operate’)

" This is especially the case for communities that are heavily impacted through construction and/or operation, but directly gain little benefit, for example, the asset is servicing an upstream community or deliverable significantly removed from the main area of impact.

 According to the Australian Government Department of Industry, Innovation and Science, social licence to operate must be constantly renewed through active, broad-based community engagement for the entire lifespan of the project."

QUESTION: Does TfNSW have a social licence to operate in this case? Who gains? Who loses? Why weren't the community engaged before March 2019?

More detailed information and research

What are the 3 routes between the West and Sydney basin


Most of the freight for export from the Central West / Orana should be going to Newcastle. See map at bottom of the page, as it has been identified as the most suitable port (NSW Container and Port Policy March 2018 p.24)

A container port is being built at Newcastle (which will be a good thing when they wind up the coal export terminal).

 There is a catch. 

When the port of Newcastle was privatised several years ago it was conditional on a cap being put on the number of containers that could be shipped from it. Anything over a certain limit would be charged. So shippers will have to send their containers to Port Botany, probably by road. This will create more congestion. 

The ACCC has taken the government to court for anti-competitive behaviour and the decision is pending. [3]
June 2021 Update
Port Botany, Illawarra to gain ‘monopoly’ on transporting containers for 50 years
Federal Court finds against ACCC (SMH, 30June 2021, page 9)

The NSW government should drop its opposition to a Newcastle container terminal. The Nationals support the dropping of the restrictions.[1]


“In comments apparently designed to up the ante on the debate, Port of Newcastle chief executive Craig Carmody lashed out at the restrictions on the port, saying Australia was "an island nation that knows bugger-all about ships and ports". Feb 2020[2]

The government has already completed a feasibility study to reopen the Maryvale to Gulgong Corridor, which is the missing direct link between the Orana region and Newcastle. But it doesn't appear to have been published?  There was another one 40 years ago. But nothing happened as a result of it.

Excerpt from that report

"Within the context of the benefit-cost methodology adopted in this evaluation it is clear that the construction of both segments of the Sandy Hollow to Maryvale railway is economically warranted."

[1] http://mhdsupplychain.com.au/2019/07/05/container-terminal-a-step-closer-for-newcastle/

[2] https://www.newcastleherald.com.au/story/6645963/port-says-newcastle-container-restrictions-must-go-in-face-of-coal-downturn/

[3] https://www.dailyliberal.com.au/story/5827877/exporters-could-use-newcastle-option-if-accc-action-is-successful/

 

The Government is Creating Unnecessary Congestion through its policies

"Cargo owners north of Sydney have described the challenge of transporting goods to Port Botany by truck within the safe drive limits. In some cases, the travel distance, plus congestion near the port, exceed the windows allowed in regulations. This means that the cargo cannot be delivered in time and results in extra costs, as well as delays and inefficiencies. "( report for NSW Container and Port Policy March 2018 p.27)

The NSW government will be creating  congestion by making freight forwarders ship their containers through past the port of Newcastle, down the M1, through Sydney to Port Botany.

This could be changed at the stroke of a pen.

Would the freight forwarders support this? Yes!
Dubbo exporters could use Newcastle Port option if ACCC action is successful


[1] https://www.transport.nsw.gov.au/projects/project-delivery-requirements/evaluation-and-assurance/transport-for-nsw-cost-benefit/key

[2] New South Wales. Parliament. Legislative Council. Public Accountability Committee. "The impact of the WestConnex Project"

 

Further Reading

Transport infrastructure: our States biggest waste 

Newcastle port restriction – action not words please!

Tarana welcomes transport executive (Western Advocate Aug 19, 2020)

"It is important that we celebrate the history of the railway, which continues to play a valuable role in communities across the Central West, whether it be taking customers where they need to go, or moving vast amounts of freight around our state."


Toll Road bankruptcies - content coming

Extract from "Future Transport 2056"

Future directions to investigate p.44

Comment: No mention of rail

p. 46 "Heavy vehicle road reform will provide a basis for comparing road and rail freight pricing – a stepping stone towards the development of a market for freight where technology, data and analytics could support innovative ways of providing dynamic priority, and freight-as-a-service multimodal offerings."

Comment: Good to see planning for more equitable access to networks

p.79 "Improve multimodal interchanges, particularly in regional NSW, so customers can more easily connect to flexible services and experience seamless and reliable journeys."

p. 153 ""To be a leader in transport we need continuous innovation, new ways to solve problems and deliver value, and a culture that applies learnings from other industries

Comment: Yes, when is this going to happen?

p.87 "Encouraging more customers to use active and public transport"
Comment: See Congestion page this site: why aren't the suggestions outlined there being implemented?

p.88 "Incorporate multimodal network improvements and place based planning in the design of all major transport projects

Comment: Why aren't people of Blackheath and Medlow allowed to raise the issue of rail (ie intermodal)?

p. 96 "Access to the trade gateways of Newcastle Port and Port Kembla from inland NSW will continue to be important for the next 40 years"

Comment:So why the container restrictions on the Port of Newcastle

Net Zero Emissions???

HOW DOES THE DUAL CARRIAGEWAY HELP ACHIEVE THIS?