Over the course of the project, the code and lens equipment have been set up. The 3D printed box and chip have also arrived.

Timeline:


Distribution of concepts: September 7th


Group/Advisor/Concept selection: September 21st


Project pitch: October 12th


Resource gathering/Component planning: October


Chip design: November


Security Clearance (NRC): November


Fund application process: November


Design Presentation: November 23rd


Peer evaluation (Fall): December 21st


Assembly: January


Testing: January


Review: January


Alpha presentation: February 8th


Promotional material: March 1st


Beta presentation: March 19th


Project fair: April 13th


Final report: April 28th


Peer evaluation (Winter): April 28th




Previous presentations:

Group Pitch Presentation:

Group pitch (Photonic Spectrometer)

Design Presentation: 

Design Presentation (Photonic Spectrometer)

Alpha Presentation:

Alpha Presentation (Photonic Spectrometer)

Beta Presentation:

Beta Presentation (Photonic Spectrometer)

Project Fair Presentation:

Project Fair Presentation (Photonic Spectrometer)