Over the course of the project, the code and lens equipment have been set up. The 3D printed box and chip have also arrived.
Timeline:
Timeline:
Distribution of concepts: September 7th
Group/Advisor/Concept selection: September 21st
Project pitch: October 12th
Resource gathering/Component planning: October
Chip design: November
Security Clearance (NRC): November
Fund application process: November
Design Presentation: November 23rd
Peer evaluation (Fall): December 21st
Assembly: January
Testing: January
Review: January
Alpha presentation: February 8th
Promotional material: March 1st
Beta presentation: March 19th
Project fair: April 13th
Final report: April 28th
Peer evaluation (Winter): April 28th