On-going Constructions

Phase 0 (completed)

After acquiring a 6 Bigha land in a rural area in Jambady, Purulia with the help of Dr.  Arun Banerjee,  son of Kanka and Ganga Banerjee, our goal was to get the land ready for construction.

Getting  electricity connection,  leveling the land and installing two submersible pumps are all done by the end of May 2023

Our goal was to raise Rs. 3 Lacs
We did raise about Rs. 2 Lacs as of July 28, 2023

Phase I - (on-going)

Estimated total cost about Rs 1 Crore

This section was last updated on Sep 2023:
Construction work of 5,000 sq. ft. ground floor work has started around May 23, 2023.

With the endowment from Dr.  Arun Banerjee, we started the Phase I work. It is estimated the total cost for Phase I is going to exceed Rs 1 Crore. 

Dr. Banerjee believes in the participation of many people who are well wishers of this project.

He would like to see outside all the different rooms and facilities to have names of many people who contributed towards the hospital, so it does not look like it was done by just one person - it should a collaborative effort.

Our goal is to raise at least Rs. 20 Lacs

KGCH Construction Milestones

The dream to construct a 5,000 sq. ft. ground floor (Phase I)  has started. 

Dec 16, 2022 >> Kanak Ganga Charitable Hospital land registration.

Jan 04, 2023 >> Hospital land mutation.

Feb 14, 2023 >> Application submitted to the district with panchayat permission for land conversion.

Feb 28, 2023 >> Electricity connection was established. 

Apr 26, 2023 >> Hospital land conversion took place.

May 08, 2023 >> Hospital land was leveled, and two submersible pumps were installed.

May 23, 2023 >> Laying of foundation stone ceremony and starting the construction work. 

June 29, 2023 >> Foundation work is almost done.

July 28, 2023 >> Construction of 4 walls of the building started.

August 28, 203 >> Construction of all 4 walls of the building is almost done.

October 22, 2023 >> Roof and more constructions are done.

Work in progress

Roof was finished by October 22, 2023

Construction of the roof in progress - September 28, 2023

Construction for the 4 walls are done around August 28, 2023

Construction for the 4 walls started around July 20, 2023

Construction for the Hospital started around June 29, 2023

Construction for the Hospital started around May 8, 2023

Construction of 5,000 sq. ft. ground floor started on May 23, 2023

Laying of foundation stone ceremony - May 23, 2023

WhatsApp Video 2023-05-09 at 1.32.28 PM.mp4

Installation of Submersible Pump - A short video, May 8, 2023

Installation of Submersible Pump, May 8, 2023

Started leveling of the Land - May 8, 2023