Kick Off Meeting: July 25, 2025
Evaluation of 2006 Plan & Data Collection: September 23, 2025
Public Meeting 1: September 25, 2025 - Deaconess Foundation, 5:30-8:30pm
Public Meeting 2: October 2025 - Time & Place TBD
Draft Revised Master Plan: January 13, 2026
Draft Revised Master Plan Approval: February 13, 2026
Final Master Plan: March 13, 2026
Public Meeting 3: April 2026 - Time & Place TBD
Anticipated Adoption: Mid July 2026