We have discussed the different categories that make up the budget and reiterated that costs must be reasonable and directly related to the project. This introduces the concept of “cost principles.” These are guidelines from NIH about what funds can be spent on and how they can be determined. You will need to ensure that all requested funds and justifications in the Budget Justification meet these cost principles. Submitting a request for costs that do not meet these may lead to a proposal being rejected or additional clarification or budget changes that would either delay the notice of award or reduce the amount of the budget that is awarded.
The cost principles are four tests that will help you to guide the PI and ensure that all the requested funds are for allowable costs.
Reasonableness (and Necessity)
Costs should reflect a reasonable amount for the line item and be comparable to the amount a typical person would spend on that item. It should also be necessary for the project. For example, if a typical flight between Lagos and Atlanta costs $1,600 in economy class, it would not be reasonable to request $5,000 for travel for this expense.
Allocability
Each cost should be associated with a specific activity, proposal, or component of the study. If the item, person-time, or equipment will mostly be used for other projects or is not clearly related to the proposal, it is not allocable.
Example:
Dr. Adebayo has 3 projects underway that all use the same lab equipment equally. One of the centrifuges needs to be replaced so she allocates this cost to a new proposal. Under that new proposal, only a few samples will need this equipment. However, the other ongoing projects will continue to use it >95% of the time. This cost would not be allocable to Dr. Adebayo’s new grant proposal as the equipment is not primarily used by the proposed new project. On the other hand, Dr. Adebayo's program director will spend 30% of his time on the new project and split the remaining 70% across other projects. Since his time is necessary to run the new proposal, 30% of his salary is an allocable expense.
Consistency
This aspect of the cost principles concerns how costs are listed and requested across projects at a particular institution, whether as direct or indirect costs. For example, if certain types of lab space normally fall under indirect costs but, for one project, they are included as direct costs, this would be an issue of consistency. You should review your institution’s policies to be sure that any proposal you manage follows this principle.
Conformance (or Allowability)
This governs whether individual costs are within the scope of what NIH considers “allowable” in general or for the current funding opportunity. There are very detailed lists that can be consulted to make sure that all costs are allowable and under what circumstances. In some cases, the overall cost category is not allowable; for example, alcoholic beverages as part of a meeting. In others, the item may be allowable under certain circumstances or following prior approval by NIH. Lastly, some costs, like office supplies and administrative support, should be covered by the indirect costs that are paid to the institution.