At this stage, a PF5 or UF5 proposal will be separated into linked PF5/RF2 or UF5/UL2 components and each component, both primary and international, will receive their own code.
Just-in-Time Information
If the proposal has been identified as fundable after the two rounds of review, researchers might be asked to submit additional documents. This does not mean that the proposal will definitely be funded but it does indicate that the review was positive. A Just-in-Time request may be made for some or all the components of an application. The PD/PI for that component will be contacted with this request.
Just-in-Time requests may be for updated Other Support documents (to be covered in the Pre-Award Module), evidence of ethics board approvals, or updated human-subjects training certification for key personnel. An award will not be issued without a completed response to a Just-in-Time request.
Notice of Award
A Notice of Award (or NoA) is the official documentation that shows approval for funding the proposal. This document lists conditions of the award, the amount being allocated for the first budget period and, if appropriate, for additional budget periods. You should carefully review any terms and conditions for the award before the award is accepted to ensure that all parties are fully aware of any specific conditions of the award.
Accepting the Award
Once an NoA has been issued and a payment management system for the award is set up, your organization will accept the award by requesting or drawing down funds from the funding institute. This will be covered in more detail in Module 5.
Monitoring the Award
Post-Award Monitoring and Reporting
Monitoring of the award and ensuring that all the terms and conditions of the award are being met is an ongoing process that requires collaboration between research administrators and researchers. The NoA and the NIH Grants Policy Statement provide the reporting requirements. Any organization receiving NIH funding for the first time should also review these additional resources for new recipients.
Grant payments are made through advance payment methods or on a reimbursement basis. The details for each specific award are listed as part of the NoA. The Grants Policy Statement provides additional guidance. This will also be covered in more detail in the Financial Management module (Module 5).
Reporting requirements
Specific types of reports are required at specific times during the life of the award. These include progress reports, invention reports, final invention statements, and federal financial reports (FFR). All grant recipients are required to submit annual (or more frequent) research performance progress reports (RPPR). These reports provide updates on researchers’ progress towards their stated aims and allow them to identify changes, delays, and other issues as they occur. Planned budgetary needs and human subjects updates are also submitted as part of these RPPRs.
Inventions, such as patents, are reported and, prior to award closeout, a final invention statement is submitted to report on any newly developed product emerging from the award.
Federal Financial Reports are submitted at least annually and report back financial information about the award at prespecified times.
Audit requirements
Some recipients of federal funds may be subject to an audit, which is a review of internal accounting and systems at an organization to ensure that federal funds are being appropriately managed in line with the appropriate laws and conditions of the awards. The module on Audit Readiness and Documentation will provide more detail on the process and preparation for this.
Closeout
The end of an award involves a process referred to as “closeout”. This requires submission of final progress reports and financial reports (FRPPR and FFFR), the final invention statement, and, for certain grants, termination notices.
These reports are due 120 days after the project end date and ensure that all required work for the award has been completed and reported on. These are all submitted via eRA Commons and require collaboration between the researchers and the administrative team. This is covered in more detail in Module 9.