WEEKLY PROGRESS REPORT #1 (01/09/2024 )
Summary
Talked with Sponsor Aaron and Prof. Gillett about both design ideas and project progress. We understand that the project progress is behind schedule. To catch up to our expectations, we need to:
Determine the design track direction
Get tools on hand
Start testing
Current Status
Sorting
We realized the DIY feeder bowl track does not align with the project timeline.
DIY feeder bowl halted
New track is to focus on bowl design
Purchase order done for a used drive unit and a new control unit
Material selection currently focus on UHMW polyethylene study
Reading instructions for simulation
Conveying/transporting
X-Y gantry, place on pan with holes
Aaron doubt, could test and give a try
Capillary tube with timing belt
Aaron relucted spending money on this, could test and give a try
Force Sensing
DFG arrived on campus this week.
Will be doing a force analysis on springs with a custom fixture made in our machine shop.
We will sample the spring in one orientation and then flip it 180 degrees to determine if orientation impacts reading of force.
Our current plan is to test 40 pins 5 times in each orientation. Giving us 200 points of data for each orientation.
Inspection
Met with Keyence to get a quote on a camera/lens system
Quoted at $5000 pretax
Seems to do everything we would want it to do, however it seems to be overkill for the goal of the project.
The software provided can measure critical dimensions and check for imperfections.
Will be meeting with a representative at COHU with camera selection.
Todo Before Next Week
Component research on all needed parts for prototype
Organize a purchase list and send to Roxanne & Gillett
Determine design track direction
WEEKLY PROGRESS REPORT #2 (01/16/2024)
Summary
Talked with Sponsor Aaron about both design ideas and project progress. Our purchasing is still behind schedule. We have been sending out purchasing orders gradually throughout the past week. We need to:
Get tools on hand
Start testing
Current Status
Sorting
Working on bowl design CAD
Talked to Machine Shop staff Tom & Steve for bowl manufacturability
Manually-machined test jig
Realized static force between pins, looking for ESd UHMW polyethylene.
Waiting for the used drive unit and a new control unit
Conveying/transporting
X-Y gantry, place on pan with holes
Parts order submitted and approved by Aaron, waiting for UCSD
Capillary tube with timing belt
Parts order submitted and approved by Aaron, waiting for UCSD
The capillary tubes are not viable, however, we can seriously try to manufacture them ourselves with laser cuter and glass-grade acrylic.
Vacuum transportation
Vacuums ordered- waiting on Roxanne ( orders through Amazon- should be quick)
Vacuum tip design done - need an opinion on manufacturability
3D printing
Machining
Pre-ordered vacuum tips usability TBD
Magnetic transportation.
The pins are found to be highly magnetic, a property that can be useful, but may also possess potential risk.
Force Sensing
DFG arrived on campus this week.
Will be doing a force analysis on springs with a custom fixture made in our machine shop.
We will sample the spring in one orientation and then flip it 180 degrees to determine if orientation impacts reading of force.
Our current plan is to test 40 pins 5 times in each orientation. Giving us 200 points of data for each orientation.
Inspection
-
Todo Before Next Week
Submit a major list of purchase order
Manufacture prototypes
WEEKLY PROGRESS REPORT #3 (01/23/2024)
Summary
Talked with Sponsor Aaron about both design ideas and project progress. In short, we are behind schedule and need to work on a prototype ASAP. We need to:
Get tools on hand
Prototyping
Current Status
Operation
Team decided to meet more often as a whole.
Formed 2 focus teams which meets more often than the group
Vibratory feeder bowl with (after feeder bowl) conveying/transporting.
Force sensing with camera inspecting.
Sorting
Working on static elimination
Placing order for ESd grade UHMW polyethylene from Boedeker Plastics.
Placing order for Static Eliminator Bar without air blower from Exair.
Working on feeder bowl
CADing in progress.
Advised by Daniel’s engineer friend who is working on a feeder bowl, got advised for a 10°-15° helix track incline angle.
Verifying the angle with research paper.
Will machine the current bowl for prototyping uses before UHMW material arrives.
Accessibility
Placing order for digital camera for easier visualization of pin movement in operation.
Conveying/transporting
X-Y gantry, place on pan with holes
Aaron doubt, could test and give it a try. (Parts order submitted and approved by Aaron, waiting for UCSD)
THIS IDEA IS NOW ABANDONED.
Capillary tube with timing belt
Aaron reluct spend money on this but could test it and give it a try (Parts order submitted and approved by Aaron, waiting for UCSD)
The capillary tubes are not viable, however, we can seriously try to manufacture them ourselves with laser cuter and glass-grade acrylic.
THIS IDEA IS BEING PERSUED FOR THE FOLLOWING REASONS:
304 SS TUBES WERE FOUND ON McMasterCarr and ordered. Tubes will satisfy the desired dimension of 0.33mm ID.
This does require adjustments on timing belt selection and thus also requires pulley and motor adjustment.
Parts will be ordered by Jan 24.
Aluminum extrusion for the system structure will also be ordered. (5ft 1” extrusion with 20 corner brackets and sliders.)
Vacuum transportation
Vacuums ordered- waiting on Roxanne ( orders through Amazon- should be quick)
Vacuum tip design done - need an opinion on manufacturability
3D printing
Machining
Pre-ordered vacuum tips usability TBD
Force Sensing
DFG arrived on campus this week.
Will be doing a force analysis on springs with a custom fixture made in our machine shop.
We will sample the spring in one orientation and then flip it 180 degrees to determine if orientation impacts reading of force.
Our current plan is to test 40 pins 5 times in each orientation. Giving us 200 points of data for each orientation.
Inspection
-
Sponsor Meeting Note
Summary: Need actual prototype ASAP.
Advisor Meeting Note
Discussed tube pin holder.
Suggested SU-8 to create stencil for pins.
Discussed inspection mechanism.
Suggested research on manifold.
Todo Before Next Week
Submit a major list of purchase order
Team decided to meet more often
We actually have no time left
Manufacture PROTOTYPES!
WEEKLY PROGRESS REPORT #4 (01/29/2024)
Summary
Talked with Sponsor Aaron about both design ideas and project progress. In short, we are behind schedule and need to work on a prototype ASAP. We need to:
Get tools on hand
Prototyping
Current Status
Operation
Team decided to meet in-person during Tuesday & Thursday from 2pm - 5:30pm.
Sorting
Static elimination
Talked with Steve and built a set up to find air pressure that causes pins to move.
Finding if air jet style static eliminator is a valid method.
Emailed Roxanne to confirm the order of ESd grade UHMW polyethylene from Boedeker Plastics.
Discussing with engineers at Exair to reduce the price of Static Eliminator.
Feeder bowl
Bowl CAD finished, CAM 90% finished. Tom will check on 01/30/2024.
Tested trap designs on the current bowl.
Realized trap design might have to be manual & will high precision
Designing CAD for pin exit variations.
First bowl prototype will be machined on 01/30/2024.
Accessibility
Designing and CAD a Camera system to view processes.
Conveying/transporting
X-Y gantry, place on pan with holes
Aaron doubt, could test and give it a try. (Parts order submitted and approved by Aaron, waiting for UCSD)
THIS IDEA IS NOW ABANDONED.
Capillary tube with timing belt
Aaron reluct spend money on this but could test it and give it a try (Parts order submitted and approved by Aaron, waiting for UCSD)
The capillary tubes are not viable, however, we can seriously try to manufacture them ourselves with laser cuter and glass-grade acrylic.
THIS IDEA IS BEING PERSUED FOR THE FOLLOWING REASONS:
304 SS TUBES WERE FOUND ON McMasterCarr and ordered. Tubes will satisfy the desired dimension of 0.33mm ID.
This does require adjustments on timing belt selection and thus also requires pulley and motor adjustment.
Parts will be ordered by Jan 24.
Aluminum extrusion for the system structure will also be ordered. (5ft 1” extrusion with 20 corner brackets and sliders.)
Vacuum transportation
Vacuums ordered- waiting on Roxanne ( orders through Amazon- should be quick)
Vacuum tip design done - need an opinion on manufacturability
3D printing
Machining
Pre-ordered vacuum tips usability TBD
Force Sensing
Data collected showed that the pin orientation does not matter in force testing.
Found a suitable load cell to inspect the pins.
CAD model will be made this week.
Inspection
Had a meeting with Michel a camera expert, pointed us in the right direction for camera and lens selection.
Aaron has told us that we no longer need to purchase the camera and only spec out the camera for the ECE team.
Pixels needed > 3100.
Sponsor Meeting Note
Discussed conveyor belt design & its manufacturability.
Glue might fail on turning points, doubt about glue idea.
Suggested glue on one side only.
Discussed arm type inspection idea
Doubt about arm idea.
Leaning toward simple push & pull or other mechanisms.
Advisor Meeting Note
Discussed conveyor belt design & its manufacturability.
Suggested research on stainless steel vacuum conveyor belt system.
Suggested a kind of plastic film for outer wrap to constrain the tubes
Agreed rubber band is a good proof of concept.
Discussed tube pin holder.
Liked the protection holder for crown tip of the pin.
Will think about possible ways for
Discussed inspection mechanism.
Worried about vacuum mechanism.
Suggested convex mirror.
Todo Before Next Week
Manufacture PROTOTYPES!
Order Load Cell
CAD for vacuum, servo motor and linear slider. Also orders for these parts
WEEKLY PROGRESS REPORT #5 (02/06/2024)
Summary
3/4 individual prototypes are done. Testing assembling and design modifications. First assembly in progress.
Current Status
Operation
Team decided to meet in-person during Tuesday & Thursday from 2pm - 5:30pm.
Team will have at least 2 practices for Proof-of-Concept presentation.
Sorting
Static elimination
Secured a 15% off from the Exair air-jet style static eliminator.
Exair air-jet style static eliminator purchase request done.
Need to confirm with Roxanne about the order of ESd grade UHMW polyethylene from Boedeker Plastics and the Exair Static Eliminators.
Feeder bowl
Finished 1 testing bowl and 1 UHMW bowl.
Function properly with minor flaws.
Testing vibration characteristics of the bowl.
Designing pin exit variations.
Bowl design refining based on current model.
REORIENTATION: Talked to an CV engineer student for possible solution
Assessing time/effort required for this solution
Accessibility
Designing and CAD a Camera system to view processes.
Conveying/transporting
Capillary tube with timing belt
Aaron reluct spend money on this but could test it and give it a try (Parts order submitted and approved by Aaron, waiting for UCSD)
The capillary tubes are not viable, however, we can seriously try to manufacture them ourselves with laser cuter and glass-grade acrylic.
THIS IDEA IS BEING PERSUED FOR THE FOLLOWING REASONS:
304 SS TUBES WERE FOUND ON McMasterCarr and ordered. Tubes will satisfy the desired dimension of 0.33mm ID.
This does require adjustments on timing belt selection and thus also requires pulley and motor adjustment.
Parts will be ordered by Jan 24.
Aluminum extrusion for the system structure will also be ordered. (5ft 1” extrusion with 20 corner brackets and sliders.)
Vacuum transportation
-
Force Sensing
Received 4 different quotes from different companies. Need to ask Aaron for approval.
Using an amazon load cell to make a prototype. Wiring and testing in progress.
Cad model completed.
Inspection
-
Sponsor Meeting Note
TBD
Advisor Meeting Note
TBD
Todo Before Next Week
Manufacture PROTOTYPES!
WEEKLY PROGRESS REPORT #6 (02/13/2024)
Summary
Most individual proof of concept done. Working on connecting individual parts together.
Current Status
Operation
Team will now collaborate and concentrate team effort on individual tasks.
Sorting
Static elimination
Waiting on static eliminators.
Feeder bowl
New design of feeder bowl done, ready to be manufactured Tuesday.
Designing pin exit variations.
REORIENTATION: Waiting on Jetson Nano, studying openCV.
Accessibility
Designing and CAD a Camera system to view processes.
Conveying/transporting
Capillary tube with timing belt
Aaron reluct spend money on this but could test it and give it a try (Parts order submitted and approved by Aaron, waiting for UCSD)
The capillary tubes are not viable, however, we can seriously try to manufacture them ourselves with laser cuter and glass-grade acrylic.
THIS IDEA IS BEING PERSUED FOR THE FOLLOWING REASONS:
304 SS TUBES WERE FOUND ON McMasterCarr and ordered. Tubes will satisfy the desired dimension of 0.33mm ID.
This does require adjustments on timing belt selection and thus also requires pulley and motor adjustment.
Parts will be ordered by Jan 24.
Aluminum extrusion for the system structure will also be ordered. (5ft 1” extrusion with 20 corner brackets and sliders.)
Vacuum transportation
-
Force Sensing
-
Inspection
-
Sponsor Meeting Note
TBD
Advisor Meeting Note
Conveying ideas explored
All agreed that tubing no longer needed due to the perfect fit of pin in groves.
Todo Before Next Week
Manufacture PROTOTYPES!
WEEKLY PROGRESS REPORT #7 (02/19/2024)
Summary
Need working on connecting individual parts together. Behind project progress.
Current Status
Operation
Aaron advises the team to not have everyone working on the same part, but return to the 2-person-team strategy due to the lack of time.
Sorting
Static eliminators arrived. Ordering pump supplies.
Feeder bowl
Version 2 bowl manufactured.
Designing exit track.
REORIENTATION: Jetson Nano arrived, studying openCV.
Accessibility
Designing and CAD a Camera system to view processes.
Conveying/transporting
Capillary tube with timing belt
THIS IDEA IS BEING PURSUED FOR THE FOLLOWING REASONS:
Aluminum extrusion for the system structure delivered.
The belt and pulley work together.
Glue idea is changed. Rubber band purchased and tested. Doesn’t work so well. Structure integrity affected by large tension force. Will need reinforcement.
Connect with Feeder Bowl.
Vacuum transportation
-
Force Sensing
-
Inspection
-
Sponsor Meeting Note
Team changing working strategy
Tasking replanning needed
Advisor Meeting Note
TBD
Todo Before Next Week
Manufacture PROTOTYPES!
WEEKLY PROGRESS REPORT #8 (02/27/2024)
Summary
Replanned project.
Split back to 2 small groups to tackle problems. Collaborating as a whole team for critical issues.
Replanned and determined priorities.
Static eliminators arrived. Ordering pump supplies.
Feeder bowl detailing
Exit track manufactured.
REORIENTATION: Jetson Nano arrived, studying openCV.
Accessibility (good to have, not priority for now)
Designing and CAD a Camera system to view processes.
Capillary tube with timing belt
Main structure finished, programmed to move a step each 2 second.
Vacuum transportation
Support and mount for vacuum tip, linear actuator and motor built.
Works, with some shortcomings
Need to remanufacture the vacuum tip mount
The current one leaks air
Motor connection needs to be better, possibly use bearing
To Do:
Controller for motor, actuator and pump/vacuum
-
-
Test - redesign - repeat
WEEKLY PROGRESS REPORT #9 (03/04/2024)
Summary
Connecting components & testing assembly. Report & presentation is now another priority.
Please check out our WIP Final report.
Current Status
Operation
The team is now focusing on the main deliverables.
The final report and poster are being constantly updated.
Sorting
Working on a pump ESd elimination system.
Feeder bowl
New exit track track designed.
Connection with conveyor belt first success achieved -> updating the design for improvement
REORIENTATION -> now a Good-to-have functionality.
Conveying/transporting
Stepper Motor Driven Timing Belt
The main structure is finished, and programmed to move a step each 2 seconds.
Will Make things more shiny and fancy looking.
Force Sensing
The Futek load cell arrived, however, it did not work with the current setup for reading load cells. Will have to order their ecosystem.
The final design of force inspection is nearly finalized.
Alignment and calibration are needed.
Inspection
-
Sponsor Meeting Note
TBD
Advisor Meeting Note
TBD
Todo Before Next Week
Test - redesign - repeat
Final report & poster constant update
Schedule final presentation with Aaron
WEEKLY PROGRESS REPORT #10 (03/11/2024)
Summary
Final Assembling.
Current Status
Operation
-
Sorting
No testable result from the ESd elimination system.
Decided to pause progress to focus on Main Assembly.
Feeder bowl
ESD bowl machined and mounted.
Connection with conveyor belt achieved with Exit track & Exit block pair.
Conveying/transporting
Stepper Motor Driven Timing Belt
Cleaned up with electronics mounted.
Maintained precision with 30 minutes continuous testing.
Force Sensing
The Futek load cell data read success.
The final design of force inspection finalized.
Alignment and calibration.
Inspection
3D printed parts, assembled.
Sponsor Meeting Note
TBD
Advisor Meeting Note
TBD
Todo Before Next Week
Test & Tuning.
Final report & poster constant update
Final presentation scheduled with Aaron