Timelines

REVISED TIMELINE:
Here is the new timeline for the JSHS Renovation Project:

March 2023 Act 34 Hearing 

June 2023 Prepare Bid Documents & Authorization of Bidding Process

July 1, 2023 Junior Senior High School split into Tulpehocken Area Middle School and Tulpehocken Area High School

July 2023 Bids open & awarded

August 2023 Begin construction 

December 2025 Substantial Completion of Building

Fall 2026 6th Grade moves into middle school