AMF / Complett Hand Stitching
By Hand Stitch Machine - 60 Stitches per minute.
= 5 minutes per Jacket
= 64 per person per day @ 75% efficiency
= 16 people to do 1000 per day
= Sewing at 2.0 minute per Jacket
= 160 per person per day @ 75% efficiency
= 7 people to do 1000 per day.
Factory Capacity – Effect of Extra Work Content
Effect of Overall Efficiency on Factory Capacity
Tailored Jacket Cloth Parts - 22 pieces
Lining - 14 pieces
Interlining - 31 pieces
Sleeve Head - 2 pieces
Pads - 2 pieces
Buttons - 9 pieces
Labels - 3 pieces
Hanger - 1 piece
Total - 85 pieces
Tailored Trouser Cloth Parts - 7 pieces
Interlinings - 5 pieces
Zip - 1 pieces
Buttons - 2 pieces
Hanger - 1 Piece
Total - 16 pieces
Tailored Skirt Cloth Parts - 6 pieces
Interlinings - 2 pieces
Zip - 1 piece
Buttons - 2 pieces
Hanger - 1 piece
Total - 12 pieces
5. Estimated Annual Materials Consumption
Tailored Jackets Cloth - 966000 meters
Lining - 830000 meters
Interlining - 600000 meters
Shoulder Pads- 690000 pairs
Buttons - 6000000 singles
Tailored Trousers Cloth - 684000 meters
Lining - 25000 meters
Zips - 600000 singles
Buttons - 1200000 singles
Tailored Skirts Cloth - 300000 meters
Lining - 300000 meters
Zips - 600000 singles
Buttons - 1200000 singles
Total Estimated Annual Cloth - 2500000 meters
Lining - 1150000 meters
Types Used Main Sewing 100’s Poly / Cotton
Over Locking 180’s Poly / Cotton
Button Holes 75’s Poly / Cotton
Lashing 300’s Poly
AMF/Comp. 75’s Poly / Cotton
Whipping Ascolite Heat Seal Elasto.
7. Sewing Thread Consumption
Tailored Jacket Total 17 Meters per garment
690000 Garments per year
11730000 Meters of Thread per year
Tailored Skirt Total 13 Meters per garment
621000 Garments per year
8070000 Meters of Thread per year
Tailored Trouser Total 15 Meters per garment
500000 Garments per year
6580000 Meters of Thread per year
Total Thread used per Year 26380000 Meters
Cutting by Hand – Jacket Pieces Approx. time = c. 30 minutes each
Gerber Gutting – Same Jacket Single Ply cutting = c. 2.0 minutes each
Deep Cutting 55 plies of jackets = c. 5.0 minutes a Lay
Per Jacket = c. 5 seconds each