Aanganwaadi, Garbage Collection, Community Toilet & Pathology Lab
Trombay Public Primary School & Community Ground
14
Site Preparation
&
GFC Drawings
Cleaning of boulders, debris, shrubs, weeds etc from the site. Putting a signage board indicating that it is a construction site. Issuing GFC drawing with basic dimensions and offsets from the neighbouring structures. Preparation of site office. Instructions, specifications and material testing samples to kept in the site office.
15
On-Site Construction Activities Scheduling
A scheduling chart for each activity and their stages at which the event will take place to be made. Each activity and overlapping of activity is diagrammatically shown with calender.
16-32
On Site Construction Processes & Observations
16 Line-out on Site Line-out on Site
17 Shoring and Excavation Work
18 Foundation Work
19 Plinth Work
20 First Slab Formwork & Concreting
21 Second Slab shuttering & Concreting First Slab Curing and Deshuttering
22 Second Slab Curing and Deshuttering Ground floor masonry work upto lintel
23 First floor masonry work Ground floor masonry work abv lintel
24 First floor Masonry work above lintel Ground floor internal plaster.
25 First Floor Internal Plaster and Ground floor WC bath water proofing
26 External Plaster and First Floor Water proofing
27 External Plaster and First Floor Tiling
28 Electrical & Plumbing Works Terrace water proofing .
29 Fixing Windows and Doors
30 External Painting
31 Finishing and Oil Painting
32 Cleaning & Preparation for Handover
this work was produced during the building making course conducted in the third year of bachelor of architecture programme
at the School of Environment and Architecture(SEA) for the academic year 2022-23.