NSTX-U Recovery Independent Basis of Estimate Review
The review committee is asked to address these charge questions:
1. Is there sufficient detailed information available and documented to support the cost estimates?
2. Are the estimates accurate, credible, comprehensive, and do they follow the GAO 12 Steps for Cost Estimating Best Practices?
3. Are project risks identified reasonable and included in the project cost?
4. Is the schedule resource loaded, identify a critical path, and include sufficient details to successfully achieve CD-4 on time?
5. Can you positively affirm the NSTX-U Recovery Project cost estimate is well documented, comprehensive, accurate and credible as defined by GAO-09-3SP and DOE Order 413.3B?
Charge Letter
Draft Charge Memo for PPPL BOER.pdf
DOE PSO Letter
NSTX-U Recovery Basis of Estimate Review Letter.pdf