(Last updated 7/20/26)
Get a bird's eye view of the roofing projects that were completed at Clark Mills and Taylor Mills Elementary Schools during the summer of 2025.
Phase I paving (new curbs and sidewalks, large parking lot) is complete, Phase II paving (around the addition) is expected to be completed in late summer/early fall 2026
Phase I roofing work is complete; Phase II roofing upgrades will begin in late July 2026
Updates to the gym HVAC system are complete
Classroom HVAC replacement is underway
Rooftop HVAC unit setting is underway
Boiler and water pump installation will be begin in mid-August 2026
Restroom ADA accessibility upgrades are complete
Emergency generator installation is complete
Auditorium lighting and sound upgrades are underway; expected completion by late July 2026; testing and final inspections scheduled for August 2026
MEMS Addition:
Steel structure and metal decking installation are complete
Exterior brick and sheathing installation are complete
Second floor concrete slab placement is complete
Masonry block installation at stairwells, the elevator shaft and interior walls is complete
First floor interior drywall installation is complete; wall priming and metal door frame installation are underway
Temporary lighting has been installed
Electrical rough-in is underway; permanent power expected by the end of July 2026
Fire alarm sprinkler system piping installation for the addition is underway
Public address system upgrades are underway
Installation of HVAC rooftop equipment curbs is complete, and installation of HVAC ductwork and piping is complete
Parapet (protective barrier wall above the roof) and exterior wall framing and wood blocking is complete
Installation of the exterior insulation and finishing system, which protects the building from the elements, expected completion in late July 2026
Interior wall framing is underway
Ceramic tile installation in the restrooms is complete
Acoustical ceiling grid installation expected completion in late July 2026
Insulation installation is underway
Roofing system installation will begin soon
Sprinkler piping installation has been completed
Retention basin storm piping and grading are underway
Groundbreaking for the addition took place on Aug. 6. Click here to view a video of the event.
New classroom HVAC units have been installed
Rooftop HVAC support rails and HVAC units have been installed
Roof gravel removal is complete; roofing work is underway
Phase I paving (new sidewalks, stairs, ramps and curbs) is complete; Phase II paving (back parking lot) is underway; awaiting top coat
Emergency generator installation is complete
Interior and exterior emergency lighting installation is complete
Classroom storage cabinetry has been installed
Interior electrical upgrades are nearly complete
Fire alarm system installation and programming are complete
Public address system upgrades are underway; expected completion in late July 2026
Restroom ADA accessibility upgrades are underway
Interior door and hardware upgrades will begin in late July 2026
Roofing replacement is complete
Restroom ADA accessibility upgrades are complete
Fire alarm system upgrades are underway
HVAC upgrades are underway
Paving of the staff parking lot is nearly complete; awaiting top coat
Roofing work is complete
Classroom HVAC units have been replaced
Rooftop HVAC support rails have been installed
Rooftop HVAC units and ground-level HVAC units have been installed
New sidewalks, stairs and curbs have been installed
Phase I parking lot paving is complete; Phase II paving (bus loop) will begin in August 2026
Interior and exterior emergency lighting installation is complete
Interior electrical upgrades are underway
Interior doors and hardware upgrades are nearly complete
Fire alarm system installation complete; awaiting final inspections
Public address system upgrades are underway; expected completion in late July 2026
Classroom storage cabinetry updates are underway
Emergency generator and pad-mounted electrical equipment have been installed; awaiting start-up and testing
Window replacement is underway; expected completion in August 2026
Restroom ADA accessibility upgrades are scheduled to take place this summer
Restroom asbestos abatement is complete; underground plumbing is nearly complete
Final gas piping terminations expected completion in late July 2026
Classroom HVAC units have been replaced, including new A/C
Rooftop HVAC support rails have been installed
Rooftop HVAC units and ground-level HVAC units have been installed
Roof gravel removal is complete; roofing work is underway
Emergency generator start-up complete; awaiting final inspection
Interior and exterior emergency lighting installation is complete
Interior doors and hardware upgrades are nearly complete
HVAC electrical upgrades are complete
Interior electrical upgrades are nearly complete
Classroom storage cabinetry updates are underway
Fire alarm system upgrades are underway
Restroom ADA accessibility upgrades are scheduled to take place in summer 2026
Phase I paving (side and rear parking lots) is complete; Phase II paving (front parking lot and bus loop) is nearly complete; awaiting top coat
Phase I paving (front parking lot) is complete; Phase II paving (side parking lot) is nearly complete; awaiting top coat
Fire alarm system is complete; awaiting final inspections
Roof gravel removal is complete; roofing work is underway
HVAC upgrades are underway including classroom and roof-top units
New rooftop HVAC condensers have been installed above the B Wing.
Emergency generator pad and pad-mounted electrical equipment installation are complete
Interior electrical upgrades are nearly complete
Transformer has been installed
Classroom storage cabinetry updates are expected to be completed in late July
Restroom asbestos abatement is complete; plumbing excavation is underway
Window replacement will begin in late July 2026
Roofing replacement is complete, including new roof ladders
Emergency generator pad has been installed, electrical upgrades are complete
Interior electrical upgrades are complete
HVAC upgrades are underway including main office, classroom and roof-top units
Fire alarm system upgrades will begin in late July 2026
Restroom ADA accessibility upgrades are scheduled to take place in summer 2026
Restroom asbestos abatement is underway
Parking lot paving is scheduled to begin this summer
Electrical panels are installed; electrical start-up and testing will begin in late July 2026
New gas meter has been installed
New curbing along front driveway has been installed; milling is underway
New curbing, sidewalks, dumpster pads, milling, stone and paving are expected to be complete by late July 2026
HVAC upgrades are complete
Interior and exterior emergency lighting installation is complete
Interior electrical upgrades are complete
Interior doors and hardware upgrades are complete
Emergency generator has been installed and start-up testing has begun
Public address system upgrades are complete; phone integration is underway
Fire alarm system installation is complete; awaiting final inspection
Phase I parking lot paving is complete; Phase II paving (bus loop) will begin in August 2026