(Last updated 12/12/25)
New curbs and sidewalks have been installed
Large parking lot paving has been completed
Roofing work is complete
Gym HVAC has been updated
ADA grab bars in the bathrooms will be installed over winter break
MEMS Addition:
Footings and foundation are installed
Elevator shaft slab installed
Underground plumbing has begun
Steel joists and metal decking have been delivered
Structure will begin to go up on Feb.
Groundbreaking for the addition took place on Aug. 6. Click here to view a video of the event.
New classroom HVAC units have been installed
Rooftop HVAC support rails have been installed
Rooftop HVAC unit installation is complete
New sidewalks, stairs and curbs have been installed
Back parking lot paving is complete
Emergency generator pad installation is underway
Roofing replacement is complete
ADA grab bars in the bathrooms will be installed over winter break
Roofing work is complete
Classroom HVAC units have been replaced
Rooftop HVAC support rails have been installed
Rooftop HVAC units and ground-level HVAC units have been installed
New sidewalks and curbs have been installed
Parking lot paving is complete
Fire alarm system upgrades are in progress
Classroom HVAC units have been replaced, including new A/C
Rooftop HVAC support rails have been installed
Rooftop HVAC units and ground-level HVAC units have been installed
Emergency generator pad has been installed, wiring is underway
Parking lot paving is complete
Interior electrical work is nearly complete
Front parking lot paving is complete
Fire alarm system upgrades are complete and testing is in progress
Roofing replacement is complete
Emergency generator pad installation is underway
HVAC upgrades are complete
Emergency generator pad installation is complete