(Last updated 6/18/26)
Installation of new curbs and sidewalks, along with paving of the large parking lot, is complete
Phase I roofing work is complete; Phase II roofing upgrades will begin this summer
Updates to the gym HVAC system are complete
Restroom ADA accessibility upgrades are complete
Concrete for the emergency generator pad has been poured
Auditorium site assessment has been completed and lighting and sound upgrades have begun
Fire alarm system upgrades are scheduled to begin in July
Boiler replacements will begin in late summer
MEMS Addition:
Steel structure and metal decking installation are complete
Exterior brick and sheathing installation are complete
Second floor concrete slab placement is complete
Masonry block installation at stairwells, the elevator shaft and interior walls is complete
First floor interior drywall installation is complete; wall priming and metal door frame installation have begun
Temporary lighting has been installed
Electrical rough-ins are underway
Fire alarm sprinkler system piping installation for the addition is underway
Installation of HVAC rooftop equipment curbs is complete, and installation of first floor HVAC ductwork and equipment is complete
Second-floor HVAC ductwork is being installed
HVAC piping and updates are nearly complete
Parapet (protective barrier wall above the roof) and exterior wall framing and wood blocking is complete
Installation of the exterior insulation and finishing system, which protects the building from the elements has begun
Interior wall framing is underway
Ceramic tile installation in the restrooms is underway
Acoustical ceiling grid installation is underway
Insulation is being installed to enclose the building
Roofing system installation will begin soon
Groundbreaking for the addition took place on Aug. 6. Click here to view a video of the event.
New classroom HVAC units have been installed
Rooftop HVAC support rails and HVAC units have been installed
Roof gravel removal is complete; roofing work will begin this summer
New sidewalks, stairs, ramps and curbs have been installed
Back parking lot base coat paving is complete; top coat will be added in summer 2026
Emergency generator pad and gas line have been installed; electrical upgrades and piping installation are underway
Interior and exterior emergency lighting installation is complete
Classroom storage cabinetry updates are underway
Interior electrical upgrades are nearly complete
Fire alarm system upgrades have been completed; awaiting initial testing
Roofing upgrades will begin this summer
Restroom ADA accessibility upgrades are scheduled to take place this summer
Phase II paving will begin this summer
Roofing replacement is complete
Restroom ADA accessibility upgrades are complete
Fire alarm system upgrades are underway
HVAC upgrades will begin this summer
Staff parking lot is scheduled to be repaved this summer
Roofing work is complete
Classroom HVAC units have been replaced
Rooftop HVAC support rails have been installed
Rooftop HVAC units and ground-level HVAC units have been installed
New sidewalks, stairs and curbs have been installed
Parking lot paving is complete
Interior and exterior emergency lighting installation is complete
Interior electrical upgrades are underway
Fire alarm system upgrades and initial testing are complete; awaiting final inspection
Classroom storage cabinetry updates are underway
Emergency generator has been installed
Window replacements will begin this summer
Restroom ADA accessibility upgrades are scheduled to take place this summer
Classroom HVAC units have been replaced, including new A/C
Rooftop HVAC support rails have been installed
Rooftop HVAC units and ground-level HVAC units have been installed
Roof gravel removal is complete; roofing work will begin this summer
Emergency generator pad has been installed and electrical updates are underway
Interior and exterior emergency lighting installation is complete
HVAC electrical upgrades are complete
Interior electrical upgrades are nearly complete
Classroom storage cabinetry updates are underway
Fire alarm system upgrades are scheduled to begin this summer
Restroom ADA accessibility upgrades are scheduled to take place this summer
Phase II paving is scheduled to begin this summer
Front parking lot paving is complete
Fire alarm system upgrades are activated; removal of the old system is nearly complete
Roof gravel removal is complete; roofing work will begin this summer
HVAC upgrades have begun and will continue throughout this summer
New rooftop HVAC condensers have been installed above the B Wing
Emergency generator pad installation is complete and electrical upgrades will begin soon
Interior electrical upgrades are nearly complete
Transformer has been installed
Classroom storage cabinetry updates are underway
Window replacements are scheduled to take place this summer
Roofing replacement is complete, including new roof ladders
Emergency generator pad has been installed, electrical upgrades are complete
Interior electrical upgrades are complete
HVAC upgrades have begun and will continue through this summer
New rooftop HVAC condensers have been installed
Fire alarm system upgrades are scheduled to begin this summer
Restroom ADA accessibility upgrades are scheduled to take place this summer
Parking lot paving is scheduled to begin this summer
HVAC upgrades are complete
Interior and exterior emergency lighting installation is complete
Interior electrical upgrades are complete
Emergency generator has been installed
Public address system upgrades are underway
Fire alarm system upgrades and initial testing are complete; awaiting final inspection
Door and hardware upgrades are underway