(Last updated 2/27/26)
Installation of new curbs, sidewalks, and paving of the large parking lot are complete
Phase I roofing work is complete; Phase II roofing upgrades will begin in summer 2026
Updates to the gym HVAC system are complete
Restroom ADA accessibility upgrades are complete
Auditorium site assessment has been completed; work is scheduled to begin in June
MEMS Addition:
Steel structure and metal decking installation are complete
Second floor concrete slab placement is complete
Masonry block wall installation at stairwells and elevator shaft is ongoing
Temporary lighting has been installed
HVAC work is underway
Electrical panel back boxes and in-wall conduit installation is underway
Fire alarm sprinkler system piping installation for the addition is underway
Groundbreaking for the addition took place on Aug. 6. Click here to view a video of the event.
New classroom HVAC units have been installed
Rooftop HVAC support rails and HVAC units have been installed
New sidewalks, stairs and curbs have been installed
Back parking lot paving is complete
Emergency generator pad has been installed; electrical upgrades are underway
Fire alarm system upgrades will begin soon
Interior electrical upgrades: lighting circuit and emergency light installation are complete; panel back box installation will begin soon
Roofing upgrades will begin in summer 2026
Restroom ADA accessibility upgrades are scheduled to take place in summer 2026
Phase II paving will begin in summer 2026
Roofing replacement is complete
Restroom ADA accessibility upgrades are complete
HVAC upgrades are underway
Staff parking lot is scheduled to be repaved in summer 2026
Roofing work is complete
Classroom HVAC units have been replaced
Rooftop HVAC support rails have been installed
Rooftop HVAC units and ground-level HVAC units have been installed
New sidewalks, stairs and curbs have been installed
Parking lot paving is complete
Fire alarm system upgrades are nearly complete
Interior electrical upgrades: lighting circuits and emergency lights have been installed
Emergency generator pad installation and electrical upgrades are underway
Window replacements will begin in summer 2026
Restroom ADA accessibility upgrades are scheduled to take place in summer 2026
Classroom HVAC units have been replaced, including new A/C
Rooftop HVAC support rails have been installed
Rooftop HVAC units and ground-level HVAC units have been installed
Emergency generator pad has been installed; emergency lighting for future generator is nearly complete
HVAC electrical upgrades are complete
Interior electrical upgrades: emergency lighting, lighting circuits, and panel back boxes have been installed
Roofing upgrades will begin in summer 2026
Restroom ADA accessibility upgrades are scheduled to take place in summer 2026
Phase II paving is scheduled to begin in summer 2026
Front parking lot paving is complete
Fire alarm system upgrades are complete and ready for final inspection
HVAC upgrades have begun and will continue through summer 2026
Emergency generator pad installation is complete
Window replacements are scheduled to take place in summer 2026
Roofing upgrades will begin in summer 2026
Roofing replacement is complete
Emergency generator pad has been installed, electrical upgrades are underway
HVAC upgrades have begun and will continue through summer 2026
Restroom ADA accessibility upgrades are scheduled to take place in summer 2026
Parking lot paving is scheduled to begin in summer 2026
HVAC upgrades are complete
Emergency generator pad has been installed, electrical upgrades are underway
Interior electrical upgrades: lighting circuits and emergency lights have been installed; new transformers are being installed
Fire alarm systen upgrades are underway
Interior door and door hardware replacements will begin soon
Classroom casework replacement will begin during summer 2026