Start Date: 5/16/24 Estimated Completion Date: 9/30/24
Project Overview: The existing boilers and hot water heater will be removed, and new equipment will be installed. The project includes improvements to the west parking lot, including the relocation of the Handicapped parking spaces, which will require some reconfiguring of the sidewalk, and additional paving. There is also work that will be completed on the public restroom in the main lobby.
Before Pictures
Project Photos and Videos
5/29/2024
5/29/2024
5/29/2024
5/29/2024
6/10/2024
06/10/2024
06/10/2024
06/10/2024
7/31/2024
7/31/2024
7/31/24
Complete Project Photos