Start Date: 5/01/24 Estimated Completion Date: 9/30/24
Project Overview: The existing track and turf field will be removed, and underground drainage will be evaluated and upgraded as needed. The drainage issues behind the storage sheds (near memorial park entrance) will be addressed. A new set of bleachers will be added on the west end of the Home Side, taking up nine (9) existing parking spaces. The new track and field will be installed, with the addition of all new fencing, and a new video scoreboard. The area around the track will be improved, with asphalt, and additional turf.
Before Pictures
Time Lapse Project Videos
Project Photos
The turf/carpet has been removed
Look at all the stone
Bulldozer ready to work
Things are happening
Perimeter drain installation
Drainage work
Track removal started this morning
Final grading is almost done
Electrical work being completed
More electrical work
New Lights being installed
Forms for bleachers
New Bleachers