Procedure
Submission of appointment order/joining report/LPC to the Finance Section before the 20th of every month.
Updating new employee details and increments/promotions/ deductions in the e-PEMS system.
Sending e-payslips through registered email addresses for confirmation one day before the disbursement of salary.
Correct pay & allowances and deductions if there are any issues/errors.
Proceed with the disbursement of salary after resolving issues/complaints, if any.
Mandatory documents/Information required
Appointment Order(DoB/TPN/email addresses of the recruits/bank account number) *Transfer orders
Joining Report
Last Pay Certificate(transfer case)
The documents of the new employee should be submitted before the 20th of every month.
Estimated TAT
Within the last three working days of the month.
Procedures
E-Playslip will be sent to the respective employees for verification and confirmation after pay finalization and before disbursement of salary via registered email addresses.
If it's required for other purposes, EID/CID number of the employee and working agency should be submitted.
Will issue the system generated payslip duly signed and sealed by the head of the CFS.
Payslip will be not issued to the third party. Exception; the employee should consent the third party to view his/her payslip by submittng the prescribed authourization form availiable at Dzongkhag Website.
Mandatory documents/Information required
Email address of the employee
Estimated TAT
E-pay slip will be sent after disbursing the salary via registered email addresses.
The hard copy pay-slip will be issued immediately.
Procedures
Submission of realistic BRF from sectors/gewogs/agencies before the 10th and 25th of every month to the CFS for fortnightly forecast submission.
Submission of BRF as submitted by the concerned sectors/gewogs/agencies within the stipulated dateline through e-PEMS.
BR Request daily basis as per requirement based on fortnightly BRF submission. *If BRF is not submitted, we cannot process any payments.
Mandatory Documents/ Information Required
Submission before the due date through the shared spreadsheet.
On or before the 10th and 25th of every month.
Estimated TAT
Submission of the BRF every fortnightly.
Submission of BR daily.
Procedures
Submission of complete Salary Advance form by the concerned officials. (form available at the dzongkhag website)
Cross-checked by the concerned accountant regarding outstanding advances of the employees, verified and approved by the head of CFS.
Process the payment if the form is duly verified and approved.
Mandatory Documents/ Information
Submission of completed salary advance form in hard copy by the concerned employees requesting salary advance
Estimated TAT
Procedures
Remittance posting after successful e-payment of salary voucher.
Remittance of TDS & Non-TDS based on deduction made twice in a month.
Mandatory Documents/ Information
System generated report attached both for Pay Remittances, Non TDS & TDS.
Estimated TAT
After the disbursement of salary.
Procedures
Issuance of system-generated TDS Certificate.
The officials can either request for hard copy from the office or a soft copy via email address.
Concern accounts personnel will share the document via a shared email address.
Mandatory Documents/ Information Required
TPN, CID no, Working Agency & email address
Estimated TAT
Immediately
Procedures
Upon receipt of the separation order/relieving order from the HR section, system system-generated LPC will be issued.
Before issuing LPC, verify that the employees have no financial outstanding advances against his/her name.
Mandatory documents/Information required
Separation order for Resignation/Deceased * Relieving Order for Transfer
Estimated TAT
Within 2 to 3 days after issuance of separation order.
Procedures
Cross-check and verify that all the required documents are submitted.
Request for supplementary budget and budget release.
Inform the financial institution of the separation of the employee if they have any outstanding loans(refer to CIB form issued by RMA) before processing the payment
Process payment based on the Approved Gratuity working sheet with completed documents. (ensure that there is no outstanding financial advances)
Mandatory Documents/Information Required
Separation order
Approved gratuity working sheet
No due certificate
Tax Clearance
Audit Clearance
LPC
CIB (Consumer Credit Outstanding Report)
Death Certificate (Deceased)
Estimated TAT
Within 5 working days depending on availability of fund release and approval for supplementary budget.
Procedures
Ensure that the attached tour reports and pictorial evidence ( if possible attach pictures with GPS coordinates) are realistic and as per the prescribed format(develop and share a prescribed format).
Ensure that the office order is issued by the competent and designated travel admin and ensure that the travel claims are within one month of the tour. (those claims beyond one month will be considered as void and will reject the claims)
Verify the travel claims are in accordance with the travel rules (entitlements, dates, mode of travel, route) 2024 before posting.
Process the payment if all the requirements are fulfilled.
Mandatory Documents/Information Required
Digital order/Travel authorization, Tour Report, Movement order, Pictorial Evidence
The claims should be made within one month of the tour.
Estimated TAT
Within 5 working days after it has been approved by the approving authority.
Procedures
Process for payment by cross-checking the required documents. (No fuel overdraft shall be entertained without prior approval from the MTO).
Issue Payment Instructions after successful payment.
Mandatory Documents/Information Required
Vehicle Fuel Requisition form & original supply memo duly verified by the MTO *Vehicle log book duly verified by MTO * Attached approved OD Requisition form duly signed by MTO/Head of Agency
Vehicle Fuel Requisition form & original supply memo duly verified by the MTO *Vehicle log book duly verified by MTO * Attached approved OD Requisition form duly signed by MTO/Head of Agency
Estimated TAT
Within 1 working day.
Procedures
Ensure the bill is submitted along with all the required documents and verify the submitted documents.
Process the Payment if all documents are submitted as required and ensure that the wage rate is as per the prescribed wage rates.
Mandatory Documents/Information Required
Note of Sanction Approved by the Competent Authority with Muster Roll sheet signed by the Site Engineer, Supervisor & Head of Agency * Attendance Sheet duly signed by Supervisor * Thumbprint/sign of labor in muster roll sheet
Within one week of the completion of the work. If the employee is on a regular muster roll, the mandatory documents should be submitted by the first week of next month.
Estimated TAT
Within 1 working day
Procedures
Verify and ensure that there is no penalty imposed for late payment. (if any, it shall be borne by the concerned person who failed to submit the bills on time.)
Process for payment by cross-checking bill amount auto-fetched in ePEMS.
Mandatory Documents/Information Required
Telephone/ Postpaid Bills, Electricity Bills
Estimated TAT
Within 1 to 2 working days
Procedures
Issue revenue receipts based on a form issued and verified by the competent authority and the form shall mention the amount imposed. (Concern Authorities (land, environment, census) should maintain a record of those forms issued)
Mandatory Documents/ Information Required
Census Registration form, Environment clearance request form verified by Environment officer mentioning the actual fee collection, Land Transaction fee(Lagthram, Lease Rent, Property Tax Transfer fee) verified by Land Record Section.
Estimated TAT
Within one hour.
Procedures
Verify and ensure that the original bills are supported by supply order and approved note sheet if it's procured from market rate.
The bills related to meetings and celebrations shall consist of the attendance sheet
The reimbursement of bills for a activity/programs/occasion/meetings should be up to Nu.20,000 only
Mandatory Documents/Information Required
Original bills duly verified by concerned sector heads/regional heads with a forwarding letter
Supply order for stationeries & other bills
Attendance sheet for the meetings.
Within one week
Estimated TAT
Within 1 to 2 days depending on the availability of budget release.
Procedures
Verify and ensure that the original bills are supported by supply order and approved note sheet if it's procured from market rate.
The bills related to meetings and celebrations shall consist of the attendance sheet
The reimbursement of bills for a activity/programs/occasion/meetings should be up to Nu.20,000 only
Submission of system-generated memorandum report to the concerned sector for the subsequent submission to the funding agencies.
Mandatory Documents/ Information Required
Original bills and other relevant documents.
Attendance sheet for the meetings
Supply order
Within one week.
Estimated TAT
Within 1 to 2 days subject to budget release availability.
Procedures
Updation of the employee in the payroll system in e-PEMS.
Accessed for self-registration for e-DATS.
The employees can update their self-bio data as and when required
Mandatory Documents/Information Required
Name, CID no, EID no, TPN, DoB, Position Title, Position Level, Payroll Department, Account No.
Within one month of joining the office/agency
Estimated TAT
within 1 day
Procedures
Cross-check that the travel authorizations/notesheets are approved by the competent authorities. ( mention the mode of travel and monitor carpooling)
Process issuance of digital travel orders in the e-DATS.
Mandatory Documents/Information Required
Approved Travel Authorization note sheet mentioning the clear travel purpose, source of funds, mode of travel, travel date, Travel place
Within 2 to 3 days after issuance of relieving order
Estimated TAT
Within one week
Procedures
Ensure that the bill is supported by required documents and duly verified by the relevant parties
Verify the hiring rate is as per the dzongkhag quotation rate and if there are no quotation rates, ensure that the rate is based on standard approved rates by the competent authorities. Logbook to cross-check meter reading and time.
Non-hiring license holders are liable for 5% TDS and 2% TDS for license holders.
Process the payment if all requirements are fulfilled.
Mandatory Documents/Information Required
Note sheet approved by Competent authority Workorder
Original Bills duly verified by site engineers & Head of the agency
Machine Log book duly verified by Operator, supervisor/Tshogpa & Head of Agency
Within one week after the execution of the work.
Estimated TAT
Within one week subject to budget release availability
Procedures
Verify that the bills are supported by the required documents
Ensure that the bills are as per the dzongkhag quotation rates and if there are no quotation rates, an approved note sheet to procure on market rate should be attached.
Ensure that the goods are supplied within the prescribed time mentioned in the supply order. If delayed, impose LD.
Process the payment if it fulfills all the requirements.
Mandatory Documents/Information Required
Note sheet approved by Competent authority
Supply Order placed by Procurement Unit
Original bills with stock entry, Verified good receipt note signed by Procurement unit/ Good Receipt committee
Within one week after receipt of the goods.
Estimated TAT
Within 1 to 2 days subject to availability of fund release.
Procedures
Verify that the bills are supported by the required documents
Ensure that the bills are as per the dzongkhag quotation rates and if there are no quotation rates, an approved note sheet to procure on market rate should be attached.
Non-hiring license holders are liable for 5% TDS and 2% TDS for license holders.
Process the payment if it fulfills all the requirements.
Mandatory Documents/Information Required
Note sheet approved & Orginal bills by the competent authority
Work order
Challan/List of material transported
Comparative statements
Within one week after the execution of the work.
Estimated TAT
Within 1 to 2 days subject to availability of fund release.
Updating of the contractors' details in the e-PEMS.
Review and verify that the request for the advance is supported by the required documents and information.
Process the payment if it fulfills all the requirements.
Mandatory Documents/Information Required
Original Valid bank guarantee
Advance Amount entered in MB by engineering sector with Work order
License No, TPN & Bank account of Contractor
Request letter for MA from the Contractor
Estimated TAT
Within 1 to 2 days subject to availability of fund release.
Procedures
Review and verify that the advance request is supported by the required documents.
Ensure the submitted original bills of the materials reached at sites are duly verifed by the site engineer
Process the payment if all requirements are fulfilled
Mandatory Documents/Information Required
Original Bills & Challan for material at site verified by site engineer entered in MB
Documents for Royalties & Taxes
License No, TPN & Bank account of Contractor
Estimated TAT
Within 5 working days including verification process by site engineer and accounts personnel subject to release availability.
Procedures
Review and verify that the running bills are supported by the required documents
Verify BoQ for quantity & rate.
Ensure deduction of TDS and retention money, liquidation of Mobilization Advance and material advances
Process the payment if all requirements are fulfilled
Mandatory Documents/Information Required
Contractor Bills with forwarding duly verified by Head of Agency*
Detail work done verified by the site engineer & DE entered in MB
Work Order
BOQ for Qty & Rate verification.
Estimated TAT
Within 5 days subject to availability of fund release
Procedures
Review and verify that the final bills are supported by the required documents and ensure that all advances are liquidated.
Verify BoQ for quantity & rate.
The mobilization advance should be liquidated when 80% of the work is done and material advance should be liquidated as and when materials are used at the sites
Ensure deduction of TDS and retention money.
Verify that the rectification report is also submitted duly signed and verified by the site engineer if any and Additional Work Order if any
Process the payment after fulfillment of all the requirement
Mandatory Documents/Information Required
Contractor Bills with forwarding duly verified by the Head of Agency
Detail final work done and verified by the site engineer & DE entered in MB
Work Order
BoQ for Qty & Rate verification
Work Completion Report, Handing Taking Note duly signed by Committee
Time Extension approval if any
Deviation statement duly approved by DLTC/GLTC if any variation of qty
Rectification report signed by the site engineer if submitted.
Within one month of handing over the site after completion.
Estimated TAT
Within 10 days subject to fund release availability.
Procedures
Review and verify that the request is supported by the required documents
Process the payments after fulfillment of all the requirement
Mandatory Documents/Information Required
Contractor Forwarding verified by Head of Agency & Enigneer entered in MB
Handing Taking Note
Original Valid Bank Guarantee verified by the Engineer
No objection letter by Head of Agency/Gewog
Estimated TAT
Contractor Forwarding verified by Head of Agency & Enigneer entered in MB
Handing Taking Note
Original Valid Bank Guarantee verified by the Engineer
No objection letter by Head of Agency/Gewog