Updated: Sept. 5 @ 3 p.m.
Several separate construction projects will impact roads, gates, and parking at the Lab’s hill site in September. The Projects & Infrastructure Modernization Division is committed to providing the Lab community with timely and comprehensive information on construction disruptions.
The map below provides a snapshot of the closures, and complete details are listed below the map. Please review the details and plan your hill site visits accordingly.
PIM's primary goal is to ensure the safety of everyone working at the Lab. Thank you for your patience as we improve the Lab for the future.
Below are the shuttle impacts related to the current September construction projects. Always check Tripshot ((lbnl.tripshot.com) for real-time current shuttle impacts.
Updated on Sept. 5 at 3 p.m.
When: Selected days in September, evenings only
Impacts:
Bertozzi Road will be closed from Lee Road to Strawberry Gate to shuttle, vehicular, and bicycle access starting at 7:30 p.m. each night through 6 a.m. the next morning on:
Tuesday, Sept. 5
Wednesday, Sept. 6
Thursday, Sept. 7
See above for expected shuttle impacts, and check Tripshot (lbnl.tripshot.com) for current shuttle schedules.
Why: UC Berkeley's contractor will be constructing a new bridge falsework spanning Bertozzi Road as part of the replacement of Centennial Bridge. The closure is a safety precaution.
Contact: Steven Filippoff (Centennial-Bridge-Lab-PM@lbl.gov, 510-486-5646)
When: Thursday, Sept. 7, from 5 a.m. to 2 p.m.
Impacts:
Lawrence Road will be reduced to one lane in front of B37.
There will be short vehicle, bicycle, and pedestrian delays due to one-way traffic. Flaggers will direct all traffic.
Six parking spots along Lawrence Road will be blocked.
See above for expected shuttle impacts, and check Tripshot (lbnl.tripshot.com) for current shuttle schedules.
Why: A crane is needed to lift a pump for the B34 chiller upgrade project. The lane reduction is a safety measure.
Contact: Quang Tran (qqtran@lbl.gov, 510-541-1739)
When: Monday, August 28 through Friday, Sept. 29
Impacts:
Lee Road in front of B66 and B62 will be closed. The parking spaces in front of B66 on both sides of Lee Road will also be closed.
Parking Lot T2 will remain open, with access along the maintenance road behind B62, which can be accessed near B31.
The work will be done generally M-F from 6 a.m. to 3 p.m., and trench plates will be placed after 3 p.m. to allow Lee Road to reopen from 3 p.m. to 6 a.m. This may change based on work needs.
The shuttle stop at B62/66 will be closed. See above for expected shuttle impacts, and check Tripshot (lbnl.tripshot.com) for current shuttle schedules.
Why: A new duct bank is needed alongside B62 to support work being done on B73. The work will be done generally M-F from 6 a.m. to 3 p.m. The work will be done in phases from August through the end of September.
Phase 4 takes place Aug. 28 - Sept. 29.
The other three phases will not impact the use of Buildings 62/66 or the shuttle stop, but will affect available parking.
Contact: Carlos Guerrero (cguerrero@lbl.gov, 341-203-0589)
When: Sunday, September 17 from 9 a.m. to approximately 6 p.m.
Impacts:
Blackberry Gate and Cyclotron Road will be closed to all vehicle, bicycle, and pedestrian traffic from 9 a.m. to 6 p.m. to allow for road restriping. Parking Lot F will also be closed that day.
Blackberry Gate will be locked, including the pedestrian gate.
Strawberry Gate will be open on Sunday as the primary gate for entering and exiting the Lab.
Grizzly Gate will be open all weekend for exiting vehicles. Pedestrian and bike users should call the Site Operations Center at 1-510-486-6999 to exit.
Why: Cyclotron Road is being restriped after it was repaved to repair potholes and patches in the roadway that present risks to cyclists and motorists.
Contact: Joe Morgan (JoeMorgan@lbl.gov, 510-486-4906)
Directions to Strawberry Gate from Blackberry Gate
Head southeast onto Cyclotron Rd
Continue onto Hearst Ave
Turn left onto Gayley Rd
Turn left onto Stadium Rim Way
Turn left onto Centennial Dr and continue for 1.7 miles
Turn right just past the Botanical Gardens parking lot into Strawberry Gate