Lighthouse Recovery Center for Women


Tiyan, Guam


Bid Date: 11/14/2019
Bid Award: $2,350,000.00
Contractors: I
nland Builders

Estimated Completion date: 320 Days



April 2021


Project held ground breaking. Construction barrier fabrication and installation ongoing. Permit is awaiting DPW director signature prior to release and pending performance bond is expected.


May 2021


Received Permit, Proof of Payment & Performance Bond


June 2021

  • Salvation Army provided Inland builders with support letter to obtain employees.

  • Solicited proposals from subcontractors.

  • Obtaining builders insurance.

  • Creating a walkway for the rainy season to ensure a safe entryway for employees.

July 2021


  • Setting up barricades this week. (07/02/2021)

  • Bond will be in GHURA's hands by end of next week (07/09/2021)



August 2021

  • A/E Team met with Contractor Inland Builders on 08/17/2021

  • Contractor submitted Performance Bond on 08/12/2021

September 2021

  • Salvation Army Requested a change of materials; Epoxy Flooring for easier maintenance.

      • Contractor is researching and will make recommendations on flooring next meeting.

  • Contractor acquired the labor to start.

  • Contractor to submit Labor Documents to GHURA.

October 2021

  • On-site office

  • Sidewalks, construction fence.

  • Inland obtained a warehouse container.

  • Workforce is ready however Inland Builders is contacting Suveryors for the site.

  • November they will start foundation.

january 2022

  • Ponding basin 1 done.

  • Preparation for shallow ponding basin done.

  • Compaction test for foundation done. Contractor to submit result by this week.

  • Installation of formworks 30%.

  • Contractors submitted RFI-1 and 2 on discrepancies of the size of sewerline and slope.