I-Learn Charter School
I-Learn Charter School Groundbreaking
I-Learn Charter School Groundbreaking
In partnership with GHURA
In partnership with GHURA
Community Development Block Grants_Section 108 Loan
$12,000,000.00 HUD LOAN
$23,000,000.00 Rich Loan (New Market Tax)
Estimated Completion date: August 2022
Meeting: July 08, 2021 @ 9AM
Meeting: July 08, 2021 @ 9AM
GWA cannot share a waste line or tap water with ST. Paul's, must move the water and waste line .
Main roof design will be changed for future maintenance reasons.
Added more classrooms to layout.
Decreased size of the Administrative office and removed Weight room for Additional classrooms.
Beams for GYM will not be available until June 2022. Cost went up by 3x. Discussion for alternatives or redesign of Gymnasium.
Awaiting evaluation from DCA for approval of payment. (Awaiting documents for materials)
First payment for 108 LOAN estimated at $488,502.33