Continue order submittal process for HVAC equipment, electrical panels/gears.
Installed construction fence at the main entrance.
Continue demo in Classroom Pod 2.
Began electrical demolition for front entrance redesign and new nurse’s office.
Excavate for proposed plumbing rough in for Classroom Pod 2 and the future nurse’s office.
Continue rough in for electrical in Classroom Pod 2.
Complete temporary restoration of the main entrance corridor.
Clean corridor at main entrance.
Install hasp and combo lock on a single exterior door into Classroom Pod 2.
Filed third party excavation and footing reports.
Completed footing excavation for addition.
Began laying CMU wall for addition.
Concurrent roof improvements, by others, happening nearby.
Saw cutting of floor for plumbing.
Continue concrete piers and slab prep at addition.
Repaired temporary partition/wall.
Continue demolition of main office walls, lighting, floors, plumbing & HVAC.
Lay out only plumbing slab cuts. No work done yet.
Installed temporary wall along existing block wall.
Concurrent roof improvements, by others, happening nearby.
Installed temporary wall along existing block wall.
Completed demolition of the main office, nurse’s office, and room 400.
Lay out only plumbing slab cuts. No work done yet.
Began duct work for the nurse’s office.
Concurrent roof improvements, by others, happening nearby.
Completed ductwork installation in former main office space.
Troubleshooted lights in three adjacent rooms.
Assessed and approved temporary make-up air supply & return to nurse’s office.
Removed dust containment plastic drapes at main entrance for arrival of staff.
Continue ductwork installation in the main corridor.
Begin saw cutting of the floor for plumbing.
Begin plumbing slab removal.
Continue order submittal process for HVAC equipment, electrical panels/gears.
Installed construction fence at the main entrance.
Begin electrical demolition and rough in.
Complete temporary restoration of the main entrance corridor.
Clean corridor at main entrance.
Install hasp and combo lock on a single exterior door into Classroom Pod 2.
Phase 1 of asbestos abatement is complete. The final phase will continue in Summer 2027.
Tape exposed duct insulation in Classroom Pods 2 & 3. These pods only have a ceiling grid, no tiles.
Continue order submittal process for HVAC equipment, electrical panels/gears.
Installed construction fence at the main entrance.
Excavated to investigate existing storm drainage.
Demolished existing sidewalk.
Demolished existing main entrance canopy.
Began demolition of corridor ceiling and previous main office.
Installed pipe insulation.
Construct proposed alcove in corridor for future nurse’s office.
Continue framing corridor radius soffits.
Clean up existing wiring in the corridor.
Install sleeves into the future nurse’s office.
Remove existing deteriorated fiberglass ceiling insulation in the future nurse’s office and corridor.
Begin heat pump repalcement in mid-to-late winter.
C. Richard Applegate Elementary School: Main entrance corridor
Joseph J. Catena Elementary School: Footing, shoring & rebar for addition.
Early Childhood Learning Center: Construction of radius ceiling soffits in the main entrance corridor
West Freehold Elementary School: Boiler room work to begin mid-to-late September. Work will include hot water boiler replacement and pump replacement.
Marshall W. Errickson Elementary School: Main entrance corridor
Laura Donovan Elementary School: Demolition of main office and nurse’s office.
Clifton T. Barkalow Middle School: Demolition of main office.
Dwight D. Eisenhower Middle School: Duct work installation in main corridor.
Roofing upgrades at Early Childhood Learning Center and Applegate Elementary School, Errickson Elementary School, Catena Elementary School, and Eisenhower Middle School.
Additions and reconfigurations at Early Childhood Learning Center, Applegate Elementary School and Errickson Elementary School. This includes proposed mechanical, electrical, plumbing, fire protection, and security projects.
HVAC upgrades, additions and reconfigurations at Catena Elementary School, West Freehold Elementary School, Donovan Elementary School, Barkalow Middle School and Eisenhower Middle School. This includes proposed mechanical, electrical, plumbing, fire protection, and security projects.
Addition of secure vestibule
Interior reconfigurations in existing main office and classroom pod 1
Boiler upgrades
Ductwork, plumbing piping installation for proposed reconfiguration of nurse’s office and main office
Interior reconfigurations in existing nurse's office and classroom pod 2
HVAC upgrades in classroom wing
Interior door/hardware replacement
Interior reconfigurations in main entrance lobby and classroom pod 3
Fire alarm system and HVAC controls upgrades
Exterior door/hardware and front entrance replacement
Switchgear replacement
Addition of secure vestibule
Interior reconfigurations in the existing main office and nurse’s office
Structural, plumbing, and sheet metal work for HVAC upgrades
Interior door/hardware and front entrance replacement
HVAC upgrades, including classroom and roof-top unit replacements
Associated structural, plumbing and sheet metal work
Exterior door/hardware and front entrance replacement
Associated structural, plumbing and sheet metal work
Fire alarm system and HVAC controls upgrades
Interior reconfigurations in main office
Boiler upgrades
Structural, plumbing and sheet metal work for HVAC upgrades
Interior door/hardware replacement
HVAC upgrades, including classroom and roof-top unit replacements
Associated structural, plumbing and sheet metal work
Exterior door/hardware and front entrance replacement
Interior reconfigurations in nurse's office
Associated structural, plumbing, and sheet metal work
Fire alarm system and HVAC controls upgrades
Interior reconfigurations in existing classrooms, including demolition of the old main office and nurse’s office
Structural, plumbing, and sheet metal work for HVAC upgrades
Interior door/hardware and front entrance replacement
HVAC upgrades, including classroom and roof-top unit replacements
Associated structural, plumbing and sheet metal work
Exterior door/hardware and front entrance replacement
Interior reconfigurations for the main office and nurse's office
Associated structural, plumbing and sheet metal work
Fire alarm system and HVAC controls upgrades
Interior reconfigurations in the existing main office
Boiler upgrades
Structural, plumbing, and sheet metal work for HVAC upgrades
Interior door/hardware, and classroom storefront/window replacement
HVAC upgrades, including classroom and roof-top unit replacements
Associated structural, plumbing and sheet metal work
Exterior door/hardware replacement
Interior reconfigurations in nurse's office
Associated structural, plumbing, and sheet metal work
Fire alarm system and HVAC controls upgrades
Addition of secure vestibule
Interior reconfigurations in existing main office and Classroom Pod 1
Boiler upgrades
Ductwork, plumbing, and piping installation for proposed HVAC upgrades
Asbestos abatement
Interior reconfigurations in existing nurse’s office and classroom pod area
HVAC upgrades in classroom wing
Interior door/hardware replacement
Interior reconfigurations in main entrance lobby and classroom pod area
Exterior door/hardware replacement
Classroom entrance replacement
Fire alarm system and HVAC controls upgrades
Interior reconfigurations in the existing main office and secure vestibule addition
Exterior stair replacement
Ductwork, plumbing, and piping installation for proposed HVAC upgrades
Interior door/hardware replacement
Rooftop and air handling unit replacement
Window replacement in the Board of Education office
Interior reconfigurations
Exterior door/hardware replacement
HVAC upgrades in the Board of Education office and classrooms
Classroom storefront/window replacement
Boiler upgrades
Fire alarm system and HVAC controls upgrades
Interior reconfigurations in main office
Boiler upgrades
Exhaust fan replacement
HVAC upgrades, heat pump replacement, plumbing and sheet metal work
Classroom door/hardware, entrance and HVAC unit replacement
Remaining HVAC upgrades, plumbing and sheet metal work
Fire alarm system HVAC controls upgrades