This timeline communicates the anticipated timeline for completion of the projects that are a part of Proposition P, a $40 million no tax increase bond issue that was authorized by voters in June of 2020. This timeline is anticipated and dates are subject to change based on a variety of factors.
Project:
Renovation of first floor classrooms - COMPLETED AUGUST 2021
A. Lighting
B. Cabinetry
C. Painting Existing Classrooms
Timeline:
Design work and construction documents: Complete February 2021
Construction: May 2021: August 2021
Project:
Building Addition
Timeline:
Design work and construction documents: Complete February 2021
Construction: Spring 2022 - August 2023
Project:
Renovation of first floor classrooms
A. Lighting
B. Cabinetry
C. Painting Existing Classrooms
Timeline:
Construction: May 2022 - August 2022
Project:
Building Addition
Construction Timeline: Spring 2022 - August 2023
Projects:
Science, Art, and FACS Addition w/ Storm Shelter
Main Entrance Signage
Science Lab Renovations
Water Service Utility Upgrade
Construction Timeline: May 2022 through August 2024
Projects:
Secure Entry and Signage
Science Lab Renovations ‐ Four (4) Labs
Security Upgrade
A. Access Control
B. Surveillance Cameras
Construction Timeline: Summer 2022
Projects:
Secure Entry and Signage
Security Upgrade
A. Access Control
B. Surveillance Cameras
Construction Timeline: Summer 2022
Projects:
Security Upgrade
A. Access Control
B. Surveillance Cameras
Construction Timeline: Summer 2023
Preliminary Design: Complete June 2021
Design Development: Complete August 2021
Construction Documents: Complete October 2021
Renovations:
Projects:
Science Lab Renovations (3 labs)
Security Upgrades
Access Control
Surveillance Cameras
Kitchen Equipment Upgrades
Construction Timeline:
Science Lab Renovations and Security Upgrades: Summer 2022
Kitchen Upgrades: Summer 2023
Projects:
Library and Classroom Addition with Storm Shelter
Secure Entry and Signage
Science Lab Renovations (4 labs)
Electric Service Utility Upgrade
Security Upgrades
Access Control
Surveillance Cameras
Kitchen Equipment Upgrades
Construction Timeline: Spring 2022 - August 2023
Projects:
Secure Entry and Signage
Kitchen Equipment Upgrades
Water Service Utility Upgrade
Security Upgrades
Access Control
Surveillance Cameras
Construction Timeline:
Secure Entry and Security Upgrades Summer 2022
Kitchen Upgrades and Water Service Utility Upgrades: Summer 2023
Projects:
Science Lab Renovations (4 labs)
Kitchen Equipment Upgrades
Security Upgrades
Access Control
Surveillance Cameras
Construction Timeline: Summer 2023
Projects:
George Guffey Elementary
Clyde Hamrick Elementary
Ray & Nancy Hodge Elementary
Lone Dell Elementary
Rockport Heights Elementary
Sherwood Elementary
Richard Simpson Elementary
Antonia Middle School
Central Office
Bus Garage
Construction Timeline: Summer 2023