For the tiny house project we are building a tiny house for a customer. A nice portion of the house was built before our group got to it because of the class before us. The group was split into smaller teams and the team i'm on is the bathroom team so we are working on the finishing touches to that.
For today I did reaseach to figure of what materials would be needed to construct a wall for the tiny house bathroom. So watched videovideos that went ininto detail and looked on different website that could give me a list.
Today me and my team mate completed the other part of the wall we took measurements and came up with a plan to cut out a window.
Feb, 20
Today me and a team mate started making measurements for another wall in the tiny house while two other team members constructed the back wall. So next class period we will start cutting out our wall with a jigsaw. And put the wall up.
This class period we cut out a section of the wall making a seem. Then made some more measurements for the rest of the wall taking in alot things into consideration like the shower and window. So next class period we I'll finish the little bit of measurement we have left and check over them then start cutting out the rest of the wall and staple them up.
Today we did reasearch on how to install the shower. We had to pause on cutting out the rest of the wall because the shower is going to cover up some of the wall area we already cut out. We had to make a materials list so we could start installing the shower, sink , and toilet.
today we were a helping hand when my team put up the wall to the bathroom and I had to add 2 items to the order form as the procurement manger.