We are following a well-defined implementation plan provided by Arbor to ensure all the required tasks are complete in a timely manner. Below you will see the roadmap for the different phases.
20th January - Kick-off meeting and first data upload
28th January - First Discovery meeting with project team
30th January - Data checking begins
7th February - Training information shared with staff for self-guided resources and directed sessions
21st February-1st April - Training sessions running
1st April - Final data upload
19th April - GO LIVE! Everyone using Arbor. Refresher training available during INSET day
19th April-27th May - Post-launch training & review
W/B 7th March - Kick-off meeting & start data checking in SIMS
W/B 14th March- Training
1st April - Final data upload
19th April - GO LIVE! Everyone using Arbor
19th April-13th March - Post-launch training and review