April: Identified Construction Management Firm-Story Construction out of Ames.
May-June: Posted RFP for architectural firm submissions, screen firms, interview firms, and take board action to approve architectural firm.
June-July: Identify project team (consultants), i.e. Civil, Structural, and Mechanical Engineers; send out community input survey; hold initial BCSD Facility/Project Committee Meeting; and offer public community tours of our 1916 and 1924 buildings.
July-September: Conduct program/project investigation; begin the schematic design phase; work through the design development phase; hold public forums to share progress with community; begin marketing campaign for the bond referendum on Dec. 4; and navigate through budget meetings for each phase to establish a comprehensive construction project cost.
October-November: Work through the construction document phase; and continue bond campaign.