As an intern at Aldridge Electric, serving as a project manager intern at Indianapolis International Airport, this week has been filled with several activities and a strong push to meet our deadline. Our team has been diligently working on setting down can edge lights on the taxiway, with the primary objective of making FedEx Point #8 available for plane use by the deadline of June 11th.
Every day, I've been going out to the field with Liam and we have been responsible for maintaining detailed daily logs on Procore, ensuring accurate records of progress, materials used, and any delays encountered. Additionally, we have been closely monitoring the quantities of can edge lights installed each day, tracking our progress towards meeting the project requirements.
The team has working efficiency and is determined to finish timely completion. With the deadline fast approaching, we have been working extra hours, and optimizing our resources. So far I have been enjoying what I have been doing and am constantly learning something new everyday!