April 2018 - The ADM Board of Education approved the start of a Facility Master Planning process to study enrollment growth and determine future facility needs for the district. A Board-approved committee comprised of community members, teachers, administrators, city mayors, and board members was created to study district needs and to provide recommendations.
June 2018 - A public input meeting was held at ADM High School Auditorium.
December 2018 - A Public input meeting was held at ADM High School Auditorium.
January 2019 - The ADM Facility Master Planning Committee’s Final Report was presented to the ADM Board of Education. The final report included a recommendation for the construction of a new elementary building for grades 2-4.
February 2019 - The ADM Board of Education approved a resolution approving the petition for a special election on the issuance of $15,750,000 general obligation school bonds.
April 2019 - The ADM Board of Education called a special election for June 25th, for the consideration of the following bond referendum:
May 21, 2019 - A public informational meeting will be held at ADM High School Auditorium at 6:30 PM.
June 12, 2019 - A public informational meeting will be held at ADM High School Auditorium at 6:30 PM.
June 25, 2019 - A Special Election will be held to authorize the ADM School District to contract indebtedness and issue bonds to construct, build, furnish and equip a new elementary building and improve the site. A YES vote of 60% is required for the measure to pass.